Home
Current Affairs January 2024

What is the correct answer?

4

Templates are used for

A. A planning layout

B. Flow of material

C. Advancing a programme in automatic machines

D. Copying complicated profiles

Correct Answer :

A. A planning layout


Related Questions

What is the correct answer?

4

Dummy activities are used to

A. Determine the critical path

B. Determine the project completion time

C. Maintain the required net work

D. None of these

What is the correct answer?

4

Acceptance sampling is widely used in

A. Batch production

B. Job production

C. Mass production

D. All of the above

What is the correct answer?

4

A-B-C analysis

A. Is a basic technique of materials management

B. Is meant for relative inventory control

C. Does not depend upon the unit cost of the item but on its annual consumption

D. All of the above

What is the correct answer?

4

In queuing theory, the nature of the waiting situation can be studied and analysed mathematically if

A. Complete details of items in, waiting line are known

B. Arrival and waiting times are known and can be grouped to form a waiting line model

C. All variables and constants are known and form a linear equation

D. The laws governing arrivals, service times, and the order in which the arriving units are taken into source are known

What is the correct answer?

4

Service time in queuing theory is usually assumed to follow

A. Normal distribution

B. Poissons distribution

C. Erlang distribution

D. Exponential law

What is the correct answer?

4

Basic motion time study gives times for basic motions in ten thousandths of

A. Second

B. Minute

C. Hour

D. Day

What is the correct answer?

4

Break-even analysis can be used for

A. Short run analysis

B. Long run analysis

C. Average of above two run analysis

D. There is no such criterion

What is the correct answer?

4

Which of the following is independent of sales forecast?

A. Productivity

B. Inventory control

C. Production planning

D. Production control

What is the correct answer?

4

Expediting function consists in keeping a watch on

A. Operator's activity

B. Flow of material and in case of trouble locate source of trouble

C. Minimising the delays

D. Making efficient despatching

What is the correct answer?

4

Micro motion study is

A. Analysis of a man-work method by using a motion picture camera with a timing device in the field of view

B. Motion study observed on enhanced time intervals

C. Motion study of a sequence of operations conducted systematically

D. Study of man and machine conducted simultaneously

What is the correct answer?

4

A feasible solution to the linear programming problem should

A. Satisfy the problem constraints

B. Optimise the objective function

C. Satisfy the problem constraints and non-negativity restrictions

D. Satisfy the non-negativity restrictions

What is the correct answer?

4

Father of industrial engineering is

A. Jack Gilbert

B. Gantt

C. Taylor

D. Newton

What is the correct answer?

4

Two alternatives can produce a product. First have a fixed cost of Rs. 2000 and a variable cost of Rs. 20 per piece. The second method has a fixed cost of Rs. 1500 and a variable cost of Rs. 30. The break even quantity between the two alternatives is

A. 25

B. 50

C. 75

D. 100

What is the correct answer?

4

The difference between the time available to do the job and the time required to do the job, is known as

A. Event

B. Float

C. Duration

D. Constraint

What is the correct answer?

4

The most important objective behind plant layout is

A. Overall simplification, safety of integration

B. Economy in space

C. Maximum travel time in plant

D. To provide conveniently located shops

What is the correct answer?

4

Micro-motion study is

A. Analysis of one stage of motion chart

B. Motion study, when seen on a time chart

C. Subdivision of an operation into therbligs and their analysis

D. Enlarged view of motion study

What is the correct answer?

4

Process layout is also known as

A. Analytical-layout

B. Synthetic layout

C. Static product layout

D. None of these

What is the correct answer?

4

Which of the following layouts is suited to job production?

A. Process layout

B. Product layout

C. Fixed position layout

D. Plant layout

What is the correct answer?

4

Time study is carried out

A. By finding all the significant informations regarding the job, work place and machine tool etc.

B. By breaking up each operation into small elements which are measurable with the help of the measuring device accurately

C. By observing and recording the time taken by the operator for an operation

D. All of the above

What is the correct answer?

4

A dummy activity

A. Is artificially introduced

B. Is represented by a dotted line

C. Does not require any time

D. All of the above

What is the correct answer?

4

Queuing theory is associated with

A. Sales

B. Inspection time

C. Waiting time

D. Production time

What is the correct answer?

4

PERT is

A. An analytic tool in concept

B. Limit up of event oriented diagrams

C. Used for research and development projects

D. All of the above

What is the correct answer?

4

Slack of various events on the critical path in PERT/CPM chart

A. Increases continuously

B. Decreases continuously

C. Remain constant

D. May increase or decrease depending on various factors

What is the correct answer?

4

An activity of the project is graphically represented by ________ on the network diagram.

A. A circle

B. A straight line

C. An arrow

D. None of these

What is the correct answer?

4

Routing prescribes the

A. Flow of material in the plant

B. Proper utilization of man power

C. Proper utilization of machines

D. Inspection of final product

What is the correct answer?

4

Product layout is employed for

A. Batch production

B. Continuous production

C. Effective utilization of machine

D. All of the above

What is the correct answer?

4

Inventory control in production, planning and control aims at

A. Achieving optimisation

B. Ensuring against market fluctuations

C. Acceptable customer service at low capital investment in inventory

D. Discounts allowed in bulk purchase

What is the correct answer?

4

In perpetual inventory control, the material is checked as it reaches its

A. Minimum value

B. Maximum value

C. Average value

D. Middle value

What is the correct answer?

4

PERT stands for

A. Programme Estimation and Reporting Technique

B. Process Estimation and Review Technique

C. Programme Evaluation and Review Technique

D. Planning Estimation and Resulting Technique

What is the correct answer?

4

Choose the wrong statement. Motion study is used for

A. Improving a work method

B. Improvising a work method

C. Designing a work method

D. Reducing inventory costs