Home
Current Affairs January 2024

What is the correct answer?

4

The aim of value engineering is to

A. Find the depreciation value of a machine

B. Determine the selling price of a product

C. Minimise the cost without change in quality of the product

D. All of the above

Correct Answer :

C. Minimise the cost without change in quality of the product


Related Questions

What is the correct answer?

4

PERT

A. Provides an approach for keeping planning up-to-date

B. Provides a way for management to require that planning be done on a uniform and logical basis

C. Permits management to foresee quickly the impact of variations from the plan

D. All of the above

What is the correct answer?

4

Product layout is used for

A. Job production

B. Batch production

C. Mass production

D. Any one of these

What is the correct answer?

4

Acceptance sampling is used in

A. Job production

B. Batch production

C. Mass production

D. All of these

What is the correct answer?

4

In CPM, the cost slope is determined by

A. Crash cost/Normal Cost

B. (Crash Cost - Normal cost)/ (Normal time - Crash time)

C. Normal Cost/Crash cost

D. (Normal cost - Crash cost)/ (Normal time - Crash time)

What is the correct answer?

4

Basic motion time study gives times for basic motions in ten thousandths of

A. Second

B. Minute

C. Hour

D. Day

What is the correct answer?

4

Frederick W. Taylor introduced a system of working known as

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. Effective organisation

What is the correct answer?

4

Slack of various events on the critical path in PERT/CPM chart

A. Increases continuously

B. Decreases continuously

C. Remain constant

D. May increase or decrease depending on various factors

What is the correct answer?

4

Which of the following wage incentive plan guarantees minimum wage to a worker and bonus is paid for the fixed percentage of time saved?

A. Halsey plan

B. Gantt plan

C. Rowan plan

D. Emerson's efficiency plan

What is the correct answer?

4

An optimum project schedule implies

A. Optimum utilization of men, machines and materials

B. Lowest possible cost and shortest possible time for project

C. Timely execution of project

D. To produce best results under given constraints

What is the correct answer?

4

If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good

A. EF = ES + D

B. LS = LFD

C. LF = LS + D

D. All of the above

What is the correct answer?

4

For a small scale industry, the fixed cost per month is Rs. 5000. The variable cost per product is Rs. 20 and sales price is Rs. 30 per piece. The break even production per month will be

A. 300

B. 460

C. 500

D. 1000

What is the correct answer?

4

Pick up the incorrect statement from the following

A. An activity of the project is denoted by an arrow on the net work

B. The tail of the arrow indicates the start of the activity

C. The head of the arrow indicates the end of the activity

D. The arrows are drawn (to scale from) left to right

What is the correct answer?

4

Which one of the following represents a group incentive plan?

A. Halsey Premium Plan

B. Lincoln Plan

C. Rowan Plan

D. Taylor Plan

What is the correct answer?

4

Bin card is used in

A. Administrative wing

B. Workshop

C. Foundry shop

D. Stores

What is the correct answer?

4

For ship vessel industry the following layout is best suited

A. Process layout

B. Product layout

C. Fixed position layout

D. Plant layout

What is the correct answer?

4

Tick the odd man out

A. Taylor

B. Drucker

C. McGregor

D. Galileo

What is the correct answer?

4

A CPM family includes

A. CPA (Critical Path Analysis)

B. CPP (Critical Path Plotted)

C. CPS (Critical Path Scheduling)

D. All of the above

What is the correct answer?

4

If F is the fixed cost, V is the variable cost per unit (or total variable costs) and P is the selling price of each unit (or total sales value), then breakeven point is equal to

A. (F × V)/P

B. (F × P)/V

C. F/[1 + (V/P)]

D. F/[1 - (V/P)]

What is the correct answer?

4

PERT and CPM are

A. Techniques to determine project status

B. Decision making techniques

C. Charts which increase aesthetic appearance of rooms

D. Aids to the decision maker

What is the correct answer?

4

The main advantage of line organisation is its

A. Effective command and control

B. Defined responsibilities at all levels

C. Rigid discipline in the organisation

D. All of the above

What is the correct answer?

4

The product layout

A. Lowers overall manufacturing time

B. Requires less space for placing machines

C. Utilises machine and labour better

D. All of these

What is the correct answer?

4

Gantt chart gives information about

A. Scheduling and routing

B. Sales

C. Production schedule

D. Machine utilisation

What is the correct answer?

4

When slack of an activity is negative

A. It represents a situation where extra resources are available and the completion of project is not delayed

B. It represents that a programme falls behind schedule and additional resources are required to complete the project in time

C. The activity is critical and any delay in its performance will delay the completion of whole project

D. All of the above

What is the correct answer?

4

A low unit cost can be obtained by following

A. Product layout

B. Functional layout

C. Automatic material handling equipment

D. Specialisation of operation

What is the correct answer?

4

Work study is most useful

A. Where production activities are involved

B. In judging the rating of machines

C. In improving industrial relations

D. In judging the output of a man and improving it

What is the correct answer?

4

The factors to be considered for production scheduling are

A. Component design

B. Route sheet

C. Time standards

D. All of these

What is the correct answer?

4

When slack of an activity is positive

A. It represents a situation where extra resources are available and the completion of project is not delayed

B. It represents that a programme falls behind schedule and additional resources are required to complete the project in time

C. The activity is critical and any delay in its performance will delay the completion of whole project

D. Any one of the above

What is the correct answer?

4

Pick up the correct statement from the following

A. Programmer evaluation and review technique is event oriented

B. Programmer evaluation and review technique is not event oriented

C. Critical path method is event oriented

D. None of the above

What is the correct answer?

4

Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is _________ the standard time.

A. One-fourth

B. One-half

C. Equal to

D. Twice

What is the correct answer?

4

O on a PERT/CPM chart represents

A. An ordinary event

B. A significant event representing some milestone

C. An event to be transferred to other network chart

D. Dangling event