Home
Current Affairs January 2024

What is the correct answer?

4

The architectural drafter usually begins a set of working drawings by creating the ________ plan first.

A. Foundation

B. Floor plan

C. Elevations

D. Building section

Correct Answer :

B. Floor plan


Related Questions

What is the correct answer?

4

EDM is the acronym for:

A. Enterprise data management

B. Engineering drawing management

C. Enterprise drawing manipulation

D. Engineering data manipulation

What is the correct answer?

4

There should be a visible gap between the wall and the ________ line.

A. Dimension

B. Extension

C. Center

D. Leader

What is the correct answer?

4

In this type of view, the cutting plane line indicates both the location of the cutting plane and the direction of sight:

A. Removed section

B. Revolved section

C. Auxiliary section

D. Partial section

What is the correct answer?

4

This is the bottom surface joining the sides of two adjacent threads:

A. Lead

B. Pitch

C. Crest

D. Root

What is the correct answer?

4

This is used to indicate that a surface is to be machined:

A. Finish mark

B. Machining mark

C. Roughness indicator

D. Coordinate mark

What is the correct answer?

4

This is the most common application for developments and intersections:

A. Sheet metal construction

B. Piping

C. Architecture

D. Mechanical engineering

What is the correct answer?

4

When using versions of Auto-CAD prior to Release 2006 it may be necessary to ________ a block in order to edit it.

A. Copy

B. Explode

C. Offset

D. None of the above

What is the correct answer?

4

Perspective drawings are classified according to their number of these features:

A. Station points

B. Picture planes

C. Vanishing points

D. Ground lines

What is the correct answer?

4

The Conceptual Visual Style tool is located on the ________ toolbar.

A. Visual Styles

B. Modify

C. 3-D Modeling

D. All of the above

What is the correct answer?

4

Understanding the Cartesian coordinate system will help the beginning drafter ________.

A. Control the accuracy of the drawing

B. Produce a visible grid system

C. Select a different text style

D. Choose various line types

What is the correct answer?

4

The default position of the UCS icon is positioned at ________ on the AutoCAD grid.

A. 0, 0, 0

B. 10, 10, 10

C. 20, 20, 20

D. None of the above

What is the correct answer?

4

One way to evenly space dimensions on a drawing is to use the ________.

A. Dimension Space tool

B. Linear tool

C. Continue tool

D. Baseline tool

What is the correct answer?

4

In this type of section, one quarter of the object is removed:

A. Revolved section

B. Removed section

C. Quarter section

D. Half section

What is the correct answer?

4

When adding dimensions to an auxiliary view it will be necessary to use the ________ tool.

A. Linear dimension

B. Aligned dimension

C. Baseline dimension

D. Angle dimension

What is the correct answer?

4

Schematic and single-line diagrams should be arranged so that signal or transmission path from input to output proceeds in this fashion:

A. Right to left and top to bottom

B. Right to left and bottom to top

C. Left to right and top to bottom

D. Left to right and bottom to top

What is the correct answer?

4

This type of axonometric drawing has equal foreshortening along two axis directions and a different amount on the third axis:

A. Dimetric

B. Multiview

C. Isometric

D. Trimetric

What is the correct answer?

4

Several of the tools used in traditional drafting include the following:

A. Parallel straight edge

B. 45 degree triangle

C. Circle template

D. All of the above

What is the correct answer?

4

These maps are used to plan construction projects that locate construction features so they fit the topography of the area:

A. Subdivision plats

B. Landscape maps

C. Structural topography maps

D. Structure location plans

What is the correct answer?

4

In this type of auxiliary view, a break line is used to indicate the imaginary break in the views:

A. Primary

B. Secondary

C. Revolved

D. Partial

What is the correct answer?

4

In order to convert fractional inches into decimal inches ________.

A. Look on a metric conversion chart

B. Divide the numerator (top number) by the denominator (bottom number)

C. Check the engineer's scale

D. All of the above

What is the correct answer?

4

This is the theoretically exact size from which limits of size are determined:

A. Actual Size

B. Dimensioned size

C. Production size

D. Basic size

What is the correct answer?

4

The architectural and construction industries use the United States National CAD standard (NCS) system on many ________ projects.

A. Residential

B. Commercial

C. Aerospace

D. Publicly funded

What is the correct answer?

4

In U.S. structural and architectural drafting, all dimensions of this length are usually expressed in feet and inches:

A. One inch or over

B. One foot or over

C. One yard or over

D. One rod or over

What is the correct answer?

4

In order to create one solid model from two or more separate solid shapes the drafter will need to position them and then ________.

A. Use Union to join them

B. Use the Join command

C. Use the Add Parts tool

D. None of the above

What is the correct answer?

4

These weld symbols have no arrow-side or other-side significance:

A. Projection or seam weld

B. Back or backing weld

C. Surface or groove weld

D. Flash and upset weld

What is the correct answer?

4

In this type of drawing, vertical pipes may be revolved into the horizontal plane:

A. Standard view

B. Elevation view

C. Transverse piping

D. Developed piping

What is the correct answer?

4

A full scale technical drawing will have a scale factor of ________.

A. 1 : 1

B. 1 : 2

C. 2 : 1

D. 1 : 4

What is the correct answer?

4

This line pattern is composed of three dashes, one long dash on each end with a short dash in the middle:

A. Object

B. Hidden

C. Center

D. Phantom

What is the correct answer?

4

This type of solid is egg-shaped and can be created by revolving an ellipse around one of its axes:

A. Ellipsoid

B. Torus

C. Cone

D. Cylinder

What is the correct answer?

4

Inserting blocks into a drawing file usually requires exacting placement. The drafter should insure that ________ is turned on.

A. O Snaps

B. Ortho

C. Grid

D. Dynamic Input