Home
Current Affairs January 2024

What is the correct answer?

4

The basic difference between PERT and CPM is that

A. PERT deals with events and CPM with activities

B. Critical path is determined in PERT only

C. Costs are considered on CPM only and not in PERT

D. Guessed times are used in PERT and evaluated times in CPM

Correct Answer :

D. Guessed times are used in PERT and evaluated times in CPM


Related Questions

What is the correct answer?

4

Slack represents the difference between the

A. Latest allowable time and the normal expected time

B. Latest allowable time and the earliest expected time

C. Proposed allowable time and the earliest expected time

D. Normal allowable time and the latest expected time

What is the correct answer?

4

An activity of the project is graphically represented by ________ on the network diagram.

A. A circle

B. A straight line

C. An arrow

D. None of these

What is the correct answer?

4

The amount deducted from the salary of workers towards employees provident fund is

A. Credited into reserves of company

B. Deposited in nationalised bank

C. Deposited in post office

D. Deposited in the account of worker with Provident Fund Commissioner

What is the correct answer?

4

For ship vessel industry the following layout is best suited

A. Process layout

B. Product layout

C. Fixed position layout

D. Plant layout

What is the correct answer?

4

At the breakeven point,

A. Total cost is more than the sales revenue

B. Total cost is less than the sales revenue

C. Total cost is equal to sales revenue

D. Fixed cost is equal to variable cost

What is the correct answer?

4

Pick up the correct statement from the following

A. Programmer evaluation and review technique is event oriented

B. Programmer evaluation and review technique is not event oriented

C. Critical path method is event oriented

D. None of the above

What is the correct answer?

4

Queuing theory is associated with

A. Sales

B. Inspection time

C. Waiting time

D. Production time

What is the correct answer?

4

Pick up the correct statement from the following

A. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project in no delayed

B. If the float of an activity is negative, delay in its performance is bound to delay the completion of project

C. If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project

D. All of the above

What is the correct answer?

4

The probability distribution of activity times in PERT follows following distribution

A. Normal

B. Binomial

C. Beta

D. Exponential

What is the correct answer?

4

Work sampling observations are taken on the basis of

A. Detailed calculations

B. Convenience

C. Table of random numbers

D. Past experience

What is the correct answer?

4

Which of the following statement is correct?

A. When slack of an activity is zero, it falls only on critical path.

B. CPM technique is useful to minimise the direct and indirect expenses.

C. Critical path of a net work represents the minimum time required for completion of project.

D. All of the above

What is the correct answer?

4

A-B-C analysis is used in

A. CPM

B. PERT

C. Inventory control

D. All of these

What is the correct answer?

4

In perpetual inventory control, the material is checked as it reaches its

A. Minimum value

B. Maximum value

C. Average value

D. Middle value

What is the correct answer?

4

The start or completion of task is called

A. An event

B. An activity

C. A duration

D. None of these

What is the correct answer?

4

The production scheduling is simpler and high volume of output and high labour efficiency are achieved in the case of

A. Product layout

B. Process layout

C. Fixed position layout

D. A combination of line and process layout

What is the correct answer?

4

Discrepancies of bar chart techniques are

A. Consequential effects of lack in one activity on the finish date

B. Free time available for an activity can't be predicted

C. Effective monitoring/controlling can't be done

D. All of the above

What is the correct answer?

4

The allowed time for a job equals standard time plus

A. Policy allowance

B. Interference allowance

C. Process allowance

D. Learning allowance

What is the correct answer?

4

The two bin system is concerned with

A. Ordering procedure

B. Forecasting sales

C. Production planning

D. Despatching and expediting

What is the correct answer?

4

Gantt chart is used for

A. Inventory control

B. Material handling

C. Production schedule

D. Machine repair schedules

What is the correct answer?

4

What does symbol 'D' imply in work study?

A. Inspection

B. Transport

C. Delay/temporary storage

D. Permanent storage

What is the correct answer?

4

Job evaluation is the method of determining the

A. Relative worth of jobs

B. Skills required by a worker

C. Contribution of a worker

D. Contribution of a job

What is the correct answer?

4

Choose the wrong statement. Motion study is used for

A. Improving a work method

B. Improvising a work method

C. Designing a work method

D. Reducing inventory costs

What is the correct answer?

4

In a line organisation

A. Responsibility of each individual is fixed

B. Discipline is strong

C. Quick decisions are taken

D. All of these

What is the correct answer?

4

Critical path moves along the activities having total float of

A. Positive value

B. Negative value

C. Zero value

D. Same value

What is the correct answer?

4

In value engineering, important consideration is given to

A. Customer satisfaction

B. Function concept

C. Profit maximisation

D. Cost reduction

What is the correct answer?

4

The basic difference between PERT and CPM is that

A. PERT deals with events and CPM with activities

B. Critical path is determined in PERT only

C. Costs are considered on CPM only and not in PERT

D. Guessed times are used in PERT and evaluated times in CPM

What is the correct answer?

4

In the Halsey 50-50 plan, the following are rewarded more

A. Past good workers

B. Past poor workers

C. Past average workers

D. All of the above

What is the correct answer?

4

A big advantage of PERT over Gantt charts is that in the former case

A. Activities and events are clearly shown

B. Early start and late finish of an activity are clearly marked

C. Activity times are clear

D. Interrelationship among activities is clearly shown.

What is the correct answer?

4

What does symbol 'O' imply in work study?

A. Operation

B. Inspection

C. Transport

D. Delay/temporary storage

What is the correct answer?

4

Material handling in automobile industry is done by

A. Overhead crane

B. Trolley

C. Belt conveyor

D. All of the above