Home
Current Affairs January 2024

What is the correct answer?

4

The critical activity has

A. Maximum float

B. Minimum float

C. Zero float

D. Average float

Correct Answer :

C. Zero float


Related Questions

What is the correct answer?

4

Breakeven analysis consists of

A. Fixed cost

B. Variable cost

C. Fixed and variable costs

D. Operation costs

What is the correct answer?

4

Statistical quality control techniques are based on the theory of

A. Quality

B. Statistics

C. Probability

D. All of the above

What is the correct answer?

4

Pick up the correct step used for scheduling a project by C.P.M.

A. A project is divided into various activities

B. Required time for each activity is established

C. Sequence of various activities is made according to their importance

D. All of the above

What is the correct answer?

4

Production cost refers to prime cost plus

A. Factory overheads

B. Factory and administration overheads

C. Factory, administration and sales overheads

D. Factory, administration, sales overheads and profit

What is the correct answer?

4

Critical path method

A. Helps in ascertaining time schedules

B. Makes better and detailed planning possible

C. Provides a standard method for communicating project plans schedules and to time and cost performance

D. All of the above

What is the correct answer?

4

Routing prescribes the

A. Flow of material in the plant

B. Proper utilization of man power

C. Proper utilization of machines

D. Inspection of final product

What is the correct answer?

4

If TL is the largest allowable event occurrence time, total activity slack (s) is equal to

A. Latest start time earliest start time

B. Latest finish time earliest finish time (EFT)

C. TLEFT

D. All of the above

What is the correct answer?

4

Merit Rating is the method of determining worth of

A. A job

B. An individual employee

C. A particular division in workshop

D. Machine

What is the correct answer?

4

The reasons which are basically responsible for the formation of a queue should be that

A. The average service rate Hess than the average arrival rate

B. Output rate is linearly proportional to input

C. Output rate is constant and the input varies in a random manner

D. All of the above

What is the correct answer?

4

Dummy activities are used to

A. Determine the critical path

B. Determine the project completion time

C. Maintain the required net work

D. None of these

What is the correct answer?

4

In value engineering, important consideration is given to

A. Customer satisfaction

B. Function concept

C. Profit maximisation

D. Cost reduction

What is the correct answer?

4

The process layout is best suited where

A. Specialisation exists

B. Machines are arranged according to sequence of operation

C. Few number of non-standardised units is to be produced

D. Mass production is envisaged

What is the correct answer?

4

In the cost structure of a product, the selling price is determined by the factors such as

A. Sales turn over

B. Lowest competitive price

C. Various elements of the cost

D. All of the above

What is the correct answer?

4

Pick up the incorrect statement about advantages of work sampling

A. Permits a fine breakdown of activities and delays

B. Simultaneous study of many operators may be made by a single observer

C. Calculations are easier, method is economical and less time consuming

D. No time measuring devices are generally needed

What is the correct answer?

4

The difference between the time available to do the job and the time required to do the job, is known as

A. Event

B. Float

C. Duration

D. Constraint

What is the correct answer?

4

The employees provident fund act is applicable to

A. All industries

B. All industries other than small and medium industries

C. Volunteers

D. The industries notified by Government

What is the correct answer?

4

Which one of the following represents a group incentive plan?

A. Halsey Premium Plan

B. Lincoln Plan

C. Rowan Plan

D. Taylor Plan

What is the correct answer?

4

Two alternatives can produce a product. First have a fixed cost of Rs. 2000 and a variable cost of Rs. 20 per piece. The second method has a fixed cost of Rs. 1500 and a variable cost of Rs. 30. The break even quantity between the two alternatives is

A. 25

B. 50

C. 75

D. 100

What is the correct answer?

4

Emergency rush order can be pushed more effectively in

A. Job production

B. Automatic production

C. Continuous production

D. Intermittent production

What is the correct answer?

4

The essential condition for the decompression of an activity is that

A. The project time should change due to decompression

B. After decompression the time of an activity invariably exceeds its normal time

C. An activity could be decompressed to the maximum extent of its normal time

D. None of the above

What is the correct answer?

4

For a product layout the material handling equipment must

A. Have full flexibility

B. Employ conveyor belts, trucks, tractors etc.

C. Be a general purpose type

D. Be designed as special purpose for a particular application

What is the correct answer?

4

Bar charts are suitable for

A. Minor works

B. Major works

C. Large projects

D. All of the above

What is the correct answer?

4

Scheduling

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with starting of processes

D. Regulates the progress of job through various processes

What is the correct answer?

4

Work study is done with the help of

A. Process chart

B. Material handling

C. Stop watch

D. All of the above

What is the correct answer?

4

Which one of the following represents a group incentive plan?

A. Scanlon Plan

B. Rowan Plan

C. Taylor Differential Piece Rate System

D. Halsey Premium Plan

What is the correct answer?

4

The main disadvantage of line organisation is

A. Top level executives have to do excessive work

B. Structure is rigid

C. Communication delays occur

D. All of the above

What is the correct answer?

4

What does symbol 'V' employ in work study

A. Operation

B. Inspection

C. Delay/ temporary Storage

D. Permanent storage

What is the correct answer?

4

The chart which gives an estimate about the amount of materials handling between various work stations is known as

A. Flow chart

B. Process chart

C. Travel chart

D. Operation chart

What is the correct answer?

4

In breakeven analysis, total cost consists of

A. Fixed cost

B. Variable cost

C. Fixed cost + variable cost

D. Fixed cost + variable cost + overheads

What is the correct answer?

4

In order that linear programming techniques provide valid results

A. Relations between factors must be linear (positive)

B. Relations between factors must be linear (negative)

C. Either (A) or (B)

D. Only one factor should change at a time, others remaining constant