Home

The first method invented for planning projects was

A. Bar chart method

B. Milestone chart

C. Critical path method (CPM)

D. Programme evaluation and review technique (PERT)

Please do not use chat terms. Example: avoid using "grt" instead of "great".

You can do it
  1. A dummy activity in a net work diagram
  2. Micro-motion study is
  3. The production cost per unit can be reduced by
  4. The employees provident fund act is applicable to
  5. PERT
  6. P.M.T.S. (Predetermined Motion Time Systems) include
  7. In ABC control policy, maximum attention is given to
  8. One time measurement unit (TMU) in method time measurement system equals
  9. Product layout is employed for
  10. For material transportation, conveyors are used when the prevailing conditions include
  11. CPM stands for
  12. Which one of the following chart gives simultaneously information about the progress of work and machine…
  13. In the Halsey system of wage incentive plan, a worker is
  14. In order to avoid excessive multiplication of facilities, the layout preferred is
  15. The probability distribution of project completion in PERT follows following distribution
  16. The most important objective behind plant layout is
  17. The time required to complete a task is established and a bonus is paid to the worker for every hour…
  18. Which of the following are the guidelines for the construction of a network diagram?
  19. The deductions for, employees provident fund start
  20. The objective of time study is to determine the time required to complete a job by
  21. Performance rating is equal to
  22. In product layout
  23. A-B-C analysis
  24. Job enrichment technique is applied to
  25. Percent idle time for men or machines is found by
  26. Travel charts provide
  27. Which of the following statement is correct?
  28. 'Value' for value engineering and analysis purposes is defined as
  29. Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it
  30. If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start…