Home
Current Affairs January 2024

What is the correct answer?

4

The linear programming techniques can be applied successfully to industries like

A. Iron and steel

B. Food processing

C. Oil and chemical

D. All of the above

Correct Answer :

D. All of the above


Related Questions

What is the correct answer?

4

The standard time for a job is

A. Total work content

B. Base time + relaxation time

C. Total work content + basic time

D. Total work content + delay contingency allowance

What is the correct answer?

4

Two alternatives can produce a product. First have a fixed cost of Rs. 2000 and a variable cost of Rs. 20 per piece. The second method has a fixed cost of Rs. 1500 and a variable cost of Rs. 30. The break even quantity between the two alternatives is

A. 25

B. 50

C. 75

D. 100

What is the correct answer?

4

In a line organisation

A. Responsibility of each individual is fixed

B. Discipline is strong

C. Quick decisions are taken

D. All of these

What is the correct answer?

4

What does symbol 'D' imply in work study?

A. Inspection

B. Transport

C. Delay/temporary storage

D. Permanent storage

What is the correct answer?

4

Which of the following are the guidelines for the construction of a network diagram?

A. Each activity is represented by one and only one arrow in the network

B. Dangling must be avoided in a network diagram

C. Dummy activity consumes no time or resource

D. All of the above

What is the correct answer?

4

PERT analysis is based on

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All of the above

What is the correct answer?

4

M.T.M. is used to

A. Improve existing methods

B. Establish time standards

C. Develop effective methods in advance of the beginning of production

D. All of the above

What is the correct answer?

4

F. W. Taylor introduced a system of organisation known as

A. Line organisation

B. Functional organisation

C. Line and staff organisation

D. Line, staff and functional organisation

What is the correct answer?

4

A-B-C analysis is used in

A. CPM

B. PERT

C. Inventory control

D. All of these

What is the correct answer?

4

The assumption in PERT is

A. A project will always be behind schedule, if left uncorrected

B. Cost of project will always be more than the estimated cost, if no timely corrections are taken

C. A project can be subdivided into a set of predictable, independent activities

D. Activities are fixed and can't be changed

What is the correct answer?

4

In order to avoid excessive multiplication of facilities, the layout preferred is

A. Product layout

B. Process layout

C. Group layout

D. Static layout

What is the correct answer?

4

According to MAPI formula, the old machine should be replaced by new one when (CAM = Challenger's Adverse minimum DAM = Defender's Adverse minimum)

A. CAM < DAM

B. CAM > DAM

C. CAM = DAM

D. There is no such criterion

What is the correct answer?

4

When slack of an activity is negative

A. It represents a situation where extra resources are available and the completion of project is not delayed

B. It represents that a programme falls behind schedule and additional resources are required to complete the project in time

C. The activity is critical and any delay in its performance will delay the completion of whole project

D. All of the above

What is the correct answer?

4

Work study is most useful

A. Where production activities are involved

B. In judging the rating of machines

C. In improving industrial relations

D. In judging the output of a man and improving it

What is the correct answer?

4

CPM has following time estimate

A. One time estimate

B. Two time estimate

C. Three time estimate

D. Four time estimate

What is the correct answer?

4

The production cost per unit can be reduced by

A. Producing more with increased inputs

B. Producing more with the same inputs

C. Eliminating idle time

D. Minimising resource waste

What is the correct answer?

4

The time taken by a trained worker to perform an operation, while working a steady pace, is known as

A. Standard time

B. Normal time

C. Representative time

D. None of these

What is the correct answer?

4

PERT stands for

A. Programme Estimation and Reporting Technique

B. Process Estimation and Review Technique

C. Programme Evaluation and Review Technique

D. Planning Estimation and Resulting Technique

What is the correct answer?

4

Work study comprises following main techniques

A. Method study and work measurement

B. Method study and time study

C. Time study and work measurement

D. Method study and job evaluation

What is the correct answer?

4

The essential condition for the decompression of an activity is that

A. The project time should change due to decompression

B. After decompression the time of an activity invariably exceeds its normal time

C. An activity could be decompressed to the maximum extent of its normal time

D. None of the above

What is the correct answer?

4

A CPM family includes

A. CPA (Critical Path Analysis)

B. CPP (Critical Path Plotted)

C. CPS (Critical Path Scheduling)

D. All of the above

What is the correct answer?

4

Abbreviated work factor data is applied for

A. Material handling operation

B. Maintenance operation

C. Packing and shipping operation

D. All of these

What is the correct answer?

4

According to Muther, the basic principle of best layout is

A. Principle of overall integration

B. Principle of flow

C. Principle of flexibility

D. All of these

What is the correct answer?

4

Motion study involves analysis of

A. Actions of operator

B. Layout of work place

C. Tooling and equipment

D. All of the above

What is the correct answer?

4

Which of the following is not wage incentive plan?

A. Differential piece rate system

B. Rowan plan

C. Emerson plan

D. Taylor plan

What is the correct answer?

4

The main disadvantage of line organisation is

A. Top level executives have to do excessive work

B. Structure is rigid

C. Communication delays occur

D. All of the above

What is the correct answer?

4

A critical activity has

A. Maximum slack

B. Minimum slack

C. Zero slack

D. Average slack

What is the correct answer?

4

In the Emerson efficiency plan, a worker receives only his daily wage and no bonus is paid till his efficiency reaches

A. 50 %

B. 66.67 %

C. 75 %

D. 80 %

What is the correct answer?

4

Pick up the correct statement about relationship between various floats

A. Free float = total float

B. Independent float = total float

C. Independent float > free float

D. Independent float < free float

What is the correct answer?

4

A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is

A. 0.50

B. 0.66

C. 0.84

D. 0.95