Home
Current Affairs January 2024

What is the correct answer?

4

The production scheduling is simpler and high volume of output and high labour efficiency are achieved in the case of

A. Product layout

B. Process layout

C. Fixed position layout

D. A combination of line and process layout

Correct Answer :

A. Product layout


Related Questions

What is the correct answer?

4

In time study, the rating factor is applied to determine

A. Standard time of a job

B. Merit rating of the worker

C. Fixation of incentive rate

D. Normal time of a worker

What is the correct answer?

4

Value engineering aims at finding out the

A. Depreciation value of a product

B. Resale value of a product

C. Major function of the item and accomplishing the same at least cost without change in quality

D. Breakeven point when machine requires change

What is the correct answer?

4

A milestone chart

A. Shows the inter dependences of various jobs

B. Depicts the delay of jobs, if any

C. Points outgoing ahead of schedule of jobs, if any

D. None of the above

What is the correct answer?

4

The routing function in a production system design is concerned with

A. Manpower utilisation

B. Quality assurance of the product

C. Machine utilisation

D. Optimising material flow through the plant

What is the correct answer?

4

When slack of an activity is positive

A. It represents a situation where extra resources are available and the completion of project is not delayed

B. It represents that a programme falls behind schedule and additional resources are required to complete the project in time

C. The activity is critical and any delay in its performance will delay the completion of whole project

D. Any one of the above

What is the correct answer?

4

Which of the following depreciation system ensures that the interest be charged on the cost of machine asset every year on the book value, but the rate of depreciation every year remains constant

A. Sinking fund method

B. Straight line method

C. ABC charging method

D. Annuity charging method

What is the correct answer?

4

If a worker gets a daily wage of Rs HA, then according to Rowan plan, his maximum daily earnings can be

A. 2 HA

B. 1.33 HA

C. 1.5 HA

D. 1.15 HA

What is the correct answer?

4

Halsey plan of wage incentive

A. Is not applied to all level of workers

B. Is applied to all level of workers

C. Does not guarantee minimum wage

D. Is based upon efficiency of worker

What is the correct answer?

4

The term 'value' in value engineering refers to

A. Total cost of the product

B. Selling price of the product

C. Utility of the product

D. Manufactured cost of the product

What is the correct answer?

4

The deductions for, employees provident fund start

A. Immediately on joining the service

B. After 60 days of joining the service

C. After 100 days of joining the service

D. After 240 days of joining the service

What is the correct answer?

4

The main disadvantage of line organisation is

A. Top level executives have to do excessive work

B. Structure is rigid

C. Communication delays occur

D. All of the above

What is the correct answer?

4

Which of the following plans motivates supervisors by paying a premium on time saved by workers?

A. Halsey plan

B. Rowan plan

C. Haynes plan

D. Emerson's plan

What is the correct answer?

4

Merit Rating is the method of determining worth of

A. A job

B. An individual employee

C. A particular division in workshop

D. Machine

What is the correct answer?

4

Which of the following organisations is best suited for steel plants

A. Functional organisation

B. Line organisation

C. Staff organisation

D. Line, staff and functional organisations

What is the correct answer?

4

Father of industrial engineering is

A. Jack Gilbert

B. Gantt

C. Taylor

D. Newton

What is the correct answer?

4

The time taken by a trained worker to perform an operation, while working a steady pace, is known as

A. Standard time

B. Normal time

C. Representative time

D. None of these

What is the correct answer?

4

In a line organisation

A. Responsibility of each individual is fixed

B. Discipline is strong

C. Quick decisions are taken

D. All of these

What is the correct answer?

4

The reasons which are basically responsible for the formation of a queue should be that

A. The average service rate Hess than the average arrival rate

B. Output rate is linearly proportional to input

C. Output rate is constant and the input varies in a random manner

D. All of the above

What is the correct answer?

4

The breakeven point represents

A. The most economical level of operation of any industry

B. The time when unit can run without i loss and profit

C. Time when industry will undergo loss

D. The time when company can make maximum profits

What is the correct answer?

4

The unit cost in case of batch production is ________ as compared to jobbing production.

A. Same

B. Low

C. High

D. None of these

What is the correct answer?

4

ABC analysis deals with

A. Analysis of process chart

B. Flow of material

C. Ordering schedule of job

D. Controlling inventory costs money

What is the correct answer?

4

Direct expenses include

A. Factory expenses

B. Selling expenses

C. Administrative expenses

D. None of these

What is the correct answer?

4

The most important objective behind plant layout is

A. Overall simplification, safety of integration

B. Economy in space

C. Maximum travel time in plant

D. To provide conveniently located shops

What is the correct answer?

4

Micro motion study is

A. Analysis of a man-work method by using a motion picture camera with a timing device in the field of view

B. Motion study observed on enhanced time intervals

C. Motion study of a sequence of operations conducted systematically

D. Study of man and machine conducted simultaneously

What is the correct answer?

4

Scheduling

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with starting of processes

D. Regulates the progress of job through various processes

What is the correct answer?

4

The value engineering technique in which experts of the same rank assemble for product development is called

A. Delphi

B. Brain storming

C. Morphological analysis

D. Direct expert comparison

What is the correct answer?

4

Process layout is employed

A. Where low volume of production is required

B. Where similar jobs are manufactured on similar machines

C. Where machines are arranged on functional basis

D. All of the above

What is the correct answer?

4

One time measurement unit (TMU) in method time measurement system equals

A. 0.0001 minute

B. 0.0006 minute

C. 0.006 minute

D. 0.001 minute

What is the correct answer?

4

Military type of organisation is known as

A. Line organisation

B. Functional organisation

C. Line and staff organisation

D. Line, staff and functional organisation

What is the correct answer?

4

The performance of a specific task in CPM is known as

A. Dummy

B. Event

C. Activity

D. Contract