The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as

A. Duration

B. Total float

C. Free float

D. Interfering float

Please do not use chat terms. Example: avoid using "grt" instead of "great".

You can do it
  1. Slack represents the difference between the
  2. Simplex method is the method used for
  3. Which of the following wage incentive plan guarantees minimum wage to a worker and bonus is paid for…
  4. Which of the following statement is correct about the network diagram?
  5. Job enrichment technique is applied to
  6. F. W. Taylor introduced a system of organisation known as
  7. Break-even analysis consists of
  8. P.M.T.S. (Predetermined Motion Time Systems) include
  9. Pick up the incorrect statement from the following. A critical ratio scheduling
  10. The average time recorded by work study man for an operation is called
  11. In steel plant the most important system for materials handling is
  12. Time study is carried out to determine the time required to complete job by
  13. Line organisation is suitable for
  14. Pick up the correct step used for scheduling a project by C.P.M.
  15. The linear programming techniques can be applied successfully to industries like
  16. In Halsey 50-50 plan, output standards are established
  17. Pick up the correct statement about relationship between various floats
  18. Production cost refers to prime cost plus
  19. Breakeven analysis consists of
  20. Bar chart is suitable for
  21. The deductions for, employees provident fund start
  22. Acceptance sampling is used in
  23. PERT/CPM, techniques can be used for following applications
  24. Value engineering aims at finding out the
  25. The two bin system is concerned with
  26. The critical activity has
  27. Fixed position layout is also known as
  28. Product layout is also known as
  29. Break-even analysis shows profit when
  30. Routing