Home
Current Affairs January 2024

What is the correct answer?

4

The time which results in the leasi, possible construction cost of an activity, is known as

A. Normal time

B. Slow time

C. Crash time

D. Standard time

Correct Answer :

B. Slow time


Related Questions

What is the correct answer?

4

Bar charts are suitable for

A. Minor works

B. Major works

C. Large projects

D. All the Above

What is the correct answer?

4

Economic saving of time results by crashing

A. Cheapest critical activity

B. Cheapest noncritical activity

C. Costliest critical activity

D. Costliest noncritical activity

What is the correct answer?

4

The direct cost of a project with respect to normal time is

A. Minimum

B. Maximum

C. Zero

D. Infinite

What is the correct answer?

4

The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as

A. Duration

B. Total float

C. Free float

D. Interfering float

What is the correct answer?

4

In PERT analysis, the time estimates of activities and probability of their occurrence follow

A. Normal distribution curve

B. Poisson's distribution curve

C. Beta distribution curve

D. None of the above

What is the correct answer?

4

Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing. Reason R: If the angle of swing is decreased, the cycle time will be decreased. Select the correct answer.

A. Both A and R is true and R is the correct explanation of A

B. Both A and R is true but R is not the correct explanation of A

C. A is true but R is false

D. A is false but R is true

What is the correct answer?

4

CPM is

A. Synthesising in concepts

B. Is built of activities oriented programme

C. Is based on time estimate

D. All the above

What is the correct answer?

4

Final technical authority of a project lies with

A. Assistant Engineer

B. Executive Engineer

C. Superintending Engineer

D. Chief Engineer

What is the correct answer?

4

For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is

A. 8 days

B. 9 days

C. 10 days

D. 15 days

What is the correct answer?

4

Select the incorrect statement.

A. A critical path always begins at the very first event.

B. A critical path always terminates at the last event.

C. Critical activities control the project duration.

D. Critical activity is the one for which free float is zero.

What is the correct answer?

4

The probability of completion of any activity within its expected time is

A. 50 %

B. 84.1 %

C. 99.9 %

D. 100 %

What is the correct answer?

4

A dummy activity

A. Is artificially introduced

B. Is represented by a dotted line

C. Does not consume time

D. All the above

What is the correct answer?

4

Select the correct statement.

A. Activity arrows in a CPM network are drawn to scale

B. The tail of an arrow represents the finish of an activity

C. Arrow bead represents the start of an activity

D. None of the above

What is the correct answer?

4

In CPM analysis,

A. Emphasis is given to activities

B. Uncertainties are not allowed

C. Activities are represented by arrows

D. All the above

What is the correct answer?

4

An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is

A. Rs. 8,43,750

B. Rs. 8,75,000

C. Rs. 10,50,000

D. Rs. 11,56,250

What is the correct answer?

4

Site order book is used for recording

A. Instructions by the executive engineers

B. Construction measurements

C. Issue of store equipments

D. Names of the casual labour

What is the correct answer?

4

A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is

A. Rs. 4,75,000

B. Rs. 5,75,000

C. Rs. 6,50,000

D. Rs. 8,50,000

What is the correct answer?

4

The final selection of a construction site, is done by

A. Departmental representative or user

B. Local civil authority representative

C. Representative of engineer authority

D. All the above

What is the correct answer?

4

An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?

A. Rs. 31050

B. Rs. 34500

C. Rs. 37950

D. Rs. 50000

What is the correct answer?

4

A critical ratio scheduling

A. Determines the status of each activity

B. Adjusts automatically changes in activity progress

C. Is a dynamic system

D. None of these

What is the correct answer?

4

Sensitivity analysis is a study of

A. Comparison of profit and loss

B. Comparison of assets and liabilities

C. Change in output due to change in input

D. Economics of cost and benefits of the project

What is the correct answer?

4

PERT analysis is based on

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All the above

What is the correct answer?

4

For which of the following materials, the output of power shovels for a fixed shovel size will be maximum

A. Moist loam

B. Good common earth

C. Well blasted rock

D. Wet sticky clay

What is the correct answer?

4

The time by which a particular activity can be delayed without affecting the preceding and succeeding activities is known as

A. Total float

B. Free float

C. Interfering float

D. Independent float

What is the correct answer?

4

The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be

A. Rs. 8,800

B. Rs. 7,600

C. Rs. 6,400

D. Rs. 5,000

What is the correct answer?

4

A Milestone chart

A. Shows the interdependencies of various jobs

B. Depicts the delay of jobs, if any

C. Points outgoing ahead of schedule of jobs, if any

D. None of these

What is the correct answer?

4

Time and progress chart of a construction, is also known as

A. Bar chart

B. Gantt chart

C. Modified Mile stone chart

D. All the above

What is the correct answer?

4

Completion of an activity on CPM network diagram, is generally known

A. Event

B. Node

C. Connector

D. All the above

What is the correct answer?

4

In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having

A. Longest duration

B. Highest cost slope

C. Least cost slope

D. Shortest duration

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. The activity is the time consuming part of a project

B. The beginning and end of a job, are called events

C. The activity which consumes maximum time, is called a node

D. Logically and sequentially connected activities and events form a network