The type of bond in which every course contains both headers and stretchers, is called

A. English bond

B. Flemish bond

C. Russian band

D. Mixed bond

Correct Answer :

B. Flemish bond


Related Questions

What is the correct answer?

4

For different layers of cement concrete floor. Pick up the incorrect statement from the following:

A. The lowest layer consists of consolidated ground

B. A 10 cm thick clean sand is laid on consolidated ground

C. A 10 cm lime concrete (1 : 4 : 8) is laid on clean sand

D. A 10 cm thick cement concrete (1 : 2 : 4) is laid on top layer

What is the correct answer?

4

The bearing capacity of a water logged soil, may be improved by

A. Grouting

B. Chemical action

C. Drainage

D. Compaction

What is the correct answer?

4

The angular steps used for changing direction of the stairs, are called

A. Round steps

B. Angular steps

C. Winders

D. Radial steps

What is the correct answer?

4

In which of the following pairs both trees yield soft wood?

A. Deodar and Shishum

B. Chir and sal

C. Sal and teak

D. Chir and deodar

What is the correct answer?

4

Which one of the following activities is not correct as applicable to brick corbels?

A. The maximum projection of the corbel should not be more than the thickness of the wall

B. The maximum projection of each corbel course should be limited to a quarter brick at a time

C. The discontinuous corbels are used to carry heavy concentrated loads

D. Stretcher bond is generally used for the construction of brick corbel

What is the correct answer?

4

The inner section of a cavity wall, is generally known as

A. Buttress

B. Leaf wall

C. Pilaster

D. Pillar

What is the correct answer?

4

The process of making the back ground rough, before plastering, is

A. Dubbing

B. Hacking

C. Blistering

D. Peeling

What is the correct answer?

4

The pile which is provided with a bulb filled with concrete at its lower end, is known as

A. Simplex pile

B. Mac-Arthur pile

C. Raymond pile

D. Franki pile

What is the correct answer?

4

The raft slab is projected beyond the outer walls of the structure by

A. 5 to 10 cm

B. 15 to 20 cm

C. 25 to 30 cm

D. 30 to 45 cm

What is the correct answer?

4

The art of bringing the floor to a true level surface by means of screeds, is called

A. Topping

B. Bedding

C. Screeding

D. None of these

What is the correct answer?

4

A temporary rigid structure having platforms to enable masons to work at different stages of a building, is known as

A. Scaffolding

B. Dead shore

C. Raking shore

D. Under pinning

What is the correct answer?

4

Raft foundation are generally preferred to when the area required for individual footing, is more than

A. 25% to total area

B. 30% of total area

C. 40% to total area

D. 50% of total area

What is the correct answer?

4

Pick up the correct statement from the following:

A. A combined footing is so proportioned that centre of gravity of supporting area coincides with centre of gravity of two column loads

B. A combined footing may be either rectangular or trapezoidal in shape

C. Trapezoidal shaped footings may be provided under any loading

D. All the above

What is the correct answer?

4

Which one of the following rocks is used for monumental buildings?

A. Granite

B. Marble

C. Sand stone

D. Slate

What is the correct answer?

4

Pick up the correct statement about silt soil from the following:

A. The silt soil has particle size from 0.02 mm to 0.06 mm

B. In organic fine grained silt soil possesses no plasticity

C. The least plastic type normally consists of more or less equidimensional grains of quartz

D. All the above

What is the correct answer?

4

Which one of the following piles has a cast iron shoe even after removal of the hollow cylindrical steel casing?

A. Simplex pile

B. Pedestal pile

C. Vibro pile

D. Both (a) and (c) of the above

What is the correct answer?

4

The type of pile which is driven at an inclination to resist inclined forces is known as

A. Friction pile

B. Sheet pile

C. Batter pile

D. Anchor pile

What is the correct answer?

4

A floor constructed with the 4 to 6 mm marble chips, is know

A. Reinforced marble floor

B. Terrazzo floor

C. Marble floor

D. Chip floor

What is the correct answer?

4

The stepped structure provided for lateral support of a structure, is

A. Retaining wall

B. Breast wall

C. Buttress

D. Parapet wall

What is the correct answer?

4

The form work from the underside of slabs, can be removed only after

A. 1 day

B. 4 days

C. 7 days

D. 14 days

What is the correct answer?

4

The compaction of concrete in the drilled pile hole is done by compressed air in the case of

A. Simplex pile

B. Franki pile

C. Pressure pile

D. Vibro pile

What is the correct answer?

4

To support a heavy structure in sandy soil, the type of foundation generally used, is

A. Combined footing

B. Raft footing

C. Pier footing

D. Strap footing

What is the correct answer?

4

According to Rankine's formula, minimum depth of foundations, is

A. (P/w) × [(1 + sin φ)/(1 - sin φ)]²

B. (P/w) × [(1 - sin φ)/(1 + sin φ)]²

C. (P/2w) × [(1 - sin φ)/(1 + sin φ)]²

D. (P/w) × [(1 + sin φ)/(1 - sin φ)]

What is the correct answer?

4

The minimum depth of foundation in clayey soils is

A. 0.5 m

B. 0.7 m

C. 0.9 m

D. 1.2 m

What is the correct answer?

4

Black cotton soil is unsuitable for foundations because its

A. Bearing capacity is low

B. Permeability is uncertain

C. Particles are cohesive

D. Property to undergo a volumetric change due to variation of moisture content

What is the correct answer?

4

The type of footing which is used to transmit heavy loads through steel columns is

A. Raft foundation

B. Grillage foundation

C. Well foundation

D. Isolated footing

What is the correct answer?

4

The depth of concrete bed of the foundation depends upon

A. The projection of the concrete block beyond the footing over it

B. The upward soil pressure

C. The mix of the concrete

D. All the above

What is the correct answer?

4

The construction joints in buildings are provided after

A. 10 m

B. 15 m

C. 20 m

D. 40 m

What is the correct answer?

4

The brick laid with its length parallel to the face of a wall, is a known as

A. Header

B. Stretcher

C. Closer

D. None of these

What is the correct answer?

4

In ordinary residential and public buildings, the damp proof course is generally provided at

A. Ground level

B. Plinth level

C. Water table level

D. Midway ground level and water-table level