Product layout
Process layout
Fixed position layout
Any one of these
C. Fixed position layout
The minimum time required for completion of project
The maximum time required for completion of project
Maximum cost required for completion of project
Minimum cost required for completion of project
Helps in ascertaining time schedules
Makes better and detailed planning possible
Provides a standard method for communicating project plans schedules and to time and cost performance
All of the above
Fixed expenses
Variable cost
Sales revenue
All of these
Process layout
Product layout
Fixed position layout
Plant layout
Sinking fund method
Straight line method
ABC charging method
Annuity charging method
Top level executives have to do excessive work
Structure is rigid
Communication delays occur
All of the above
Minimum value
Maximum value
Average value
Middle value
CPA (Critical Path Analysis)
CPP (Critical Path Plotted)
CPS (Critical Path Scheduling)
All of the above
Producing more with increased inputs
Producing more with the same inputs
Eliminating idle time
Minimising resource waste
Component design
Route sheet
Time standards
All of these
The most economical level of operation of any industry
The time when unit can run without i loss and profit
Time when industry will undergo loss
The time when company can make maximum profits
Estimation of the percentage utilisation of machine tools
Estimating the percentage of the time consumed by various job activities
Finding out time standards, specially where the job is not repetitive and where time study by stop watch method is not possible
All of the above
The project time should change due to decompression
After decompression the time of an activity invariably exceeds its normal time
An activity could be decompressed to the maximum extent of its normal time
None of the above
An event
An activity
A duration
None of these
Relations between factors must be linear (positive)
Relations between factors must be linear (negative)
Either (A) or (B)
Only one factor should change at a time, others remaining constant
Motion study
Time study
Job enrichment
All of these
Batch production
Job production
Mass production
All of the above
All industries have to necessarily train the apprentices
Industries have to train apprentices according to their requirement
All industries employing more than 100 workers have to recruit apprentices
Only industries employing more than 500 workers have to recruit apprentices
Bar chart method
Milestone chart
Critical path method (CPM)
Programme evaluation and review technique (PERT)
It represents a situation where extra resources are available and the completion of project is not delayed
It represents that a programme falls behind schedule and additional resources are required to complete the project in time
The activity is critical and any delay in its performance will delay the completion of whole project
Any one of the above
Material handling
Reducing the waiting time or idle time
Better utilization of man services
Effective use of machines
Fast worker
Average worker
Slow worker
New entrant
Job enlargement
Job enrichment
Job rotation
Job evaluation
Sales revenue > total cost
Sales revenue = total cost
Sales revenue < total cost
Variable cost < fixed cost
Whose output exceeds 67% efficiency
On the percentage of time saved
On the percentage of time worked
On the percentage of standard time
Halsey plan
Rowan plan
Haynes plan
Emerson's plan
An ordinary event
A significant event representing some milestone
An event to be transferred to other network chart
Dangling event
Method study and work measurement
Method study and time study
Time study and work measurement
Method study and job evaluation
(to + tp + tn)/3
(to + 2tp + tn)/4
(to + 4tp + tn)/5
(to + tp + 4tn)/6
If the float is positive and the activity is delayed by a period equal to its total float, the completion of project in no delayed
If the float of an activity is negative, delay in its performance is bound to delay the completion of project
If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project
All of the above