Home
Current Affairs January 2024

What is the correct answer?

4

The work study is done by means of

A. Planning chart

B. Process chart

C. Stop watch

D. Any one of these

Correct Answer :

C. Stop watch


Related Questions

What is the correct answer?

4

The type of organisation preferred for a steel industry, is

A. Line organisation

B. Functional organisation

C. Line and staff organisation

D. Line, staff and functional organisation

What is the correct answer?

4

CPM requires

A. Single time estimate

B. Double time estimate

C. Triple time estimate

D. None of these

What is the correct answer?

4

Expediting function consists in keeping a watch on

A. Operator's activity

B. Flow of material and in case of trouble locate source of trouble

C. Minimising the delays

D. Making efficient despatching

What is the correct answer?

4

Product layout is also known as

A. Analytical layout

B. Synthetic layout

C. Static product layout

D. None of these

What is the correct answer?

4

One time measurement unit (TMU) in method time measurement system equals

A. 0.0001 minute

B. 0.0006 minute

C. 0.006 minute

D. 0.001 minute

What is the correct answer?

4

The term 'value' in value engineering refers to

A. Total cost of the product

B. Selling price of the product

C. Utility of the product

D. Manufactured cost of the product

What is the correct answer?

4

The average time recorded by work study man for an operation is called

A. Standard time

B. Normal time

C. Representative time

D. None of these

What is the correct answer?

4

Critical path method

A. Helps in ascertaining time schedules

B. Makes better and detailed planning possible

C. Provides a standard method for communicating project plans schedules and to time and cost performance

D. All of the above

What is the correct answer?

4

The time which results in the least possible direct cost of an activity is known as

A. Normal time

B. Slow time

C. Crash time

D. Standard time

What is the correct answer?

4

Travel charts provide

A. An idea of the flow of materials at various stages

B. A compact estimate of the handling which must be done between various work sections

C. The information for changes required in rearranging material handling equipment

D. An approximate estimate of the handling which must be done at a particular station

What is the correct answer?

4

Which of the following layouts is suited for mass production?

A. Process layout

B. Product layout

C. Fixed position layout

D. Plant layout

What is the correct answer?

4

'Value' for value engineering and analysis purposes is defined as

A. Purchase value

B. Saleable value

C. Depreciated value

D. Function/cost

What is the correct answer?

4

Father of time study was

A. F.W. Taylor

B. H.L. Gantt

C. F.B. Gilbert

D. R.M. Barnes

What is the correct answer?

4

Breakeven analysis consists of

A. Fixed cost

B. Variable cost

C. Fixed and variable costs

D. Operation costs

What is the correct answer?

4

If A is the total items consumed per year, P is the procurement cost per order, and C is the annual inventory carrying cost per item, then the most economic ordering quantity is given by

A. AP/C

B. 2AP/C

C. √(AP/C)

D. (AP/C)2

What is the correct answer?

4

Scheduling gives information about

A. When work should start and how much work should be completed during a certain period

B. When work should complete

C. That how idle time can be minimized

D. Proper utilisation of machines

What is the correct answer?

4

Current assets include

A. Manufacturing plant

B. Manufacturing plant and equipment

C. Inventories

D. Common stock held by the firm

What is the correct answer?

4

In a PERT chart

A. All activities should be numbered

B. Only important activities should be numbered

C. Only critical activities are numbered

D. Only selected activities are numbered

What is the correct answer?

4

Basic tool in work study is

A. Graph paper

B. Process chart

C. Planning chart

D. Stop watch

What is the correct answer?

4

Gantt chart gives information about

A. Scheduling and routing

B. Sales

C. Production schedule

D. Machine utilisation

What is the correct answer?

4

In micro-motion study, therblig is described by

A. A symbol

B. An event

C. An activity

D. Standard symbol and colour

What is the correct answer?

4

Which of the following are the principles of material handling?

A. Keep all the handling to the minimum

B. Select only efficient handling equipment

C. Move the heaviest weight to the least distance

D. All of the above

What is the correct answer?

4

Father of industrial engineering is

A. Jack Gilbert

B. Gantt

C. Taylor

D. Newton

What is the correct answer?

4

The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode

A. Early finish

B. Early start

C. Late start

D. Late finish

What is the correct answer?

4

PMTP (predetermined motion time systems) include

A. MTM (method time measurement)

B. WFS (work factor systems)

C. BNTS (basic motion time study)

D. All of the above

What is the correct answer?

4

If (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual time, then according to Rowan plan, wages for the job will be

A. TR

B. TR + [(S - T)/2] × R

C. TR + (S - T) × R

D. TR + [(S - T)/S] × R

What is the correct answer?

4

Acceptance sampling is used in

A. Job production

B. Batch production

C. Mass production

D. All of these

What is the correct answer?

4

A low unit cost can be obtained by following

A. Product layout

B. Functional layout

C. Automatic material handling equipment

D. Specialisation of operation

What is the correct answer?

4

Which of the following conditions are necessary for applying linear programming?

A. These must be a well defined objective function.

B. The decision variables should be interrelated and nonnegative.

C. The resources must be in limited supply.

D. All of the above

What is the correct answer?

4

Routing

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with starting of processes

D. Regulates the progress of job through various processes