In working drawings, these show all necessary information not given directly on the drawing with its dimensions and notes:
D. Title and record strips
What is the correct answer?
4
This type of structural steel drawing shows all dimensions necessary for fabrication:
What is the correct answer?
4
A partial auxiliary view is used to show only the ________ in the auxiliary view.
A. Projected inclined plane
B. The projected top view
C. The projected side view
What is the correct answer?
4
Center lines are used to locate or represent the centers of ________.
What is the correct answer?
4
This is the plane upon which the top view is projected:
What is the correct answer?
4
When creating an isometric drawing in Auto-CAD the drafter can utilize the Dynamic Input and Polar Coordinate system to place both vertical and horizontal lines. A line created from one point 3 inches at 180 degrees would be a ________ line.
What is the correct answer?
4
To avoid having to dimension to a hidden feature the drafter can utilize a ________ section.
What is the correct answer?
4
The MASSPROP shortcut will provide the following information.
What is the correct answer?
4
Using this as a communication and design review tool can help shorten the process and eliminate productivity barriers:
B. Portable document files
C. The Internet and e-mail
What is the correct answer?
4
Newer versions of Auto-CAD utilize the ________ to make block library management very easy.
What is the correct answer?
4
Acceptable parts must not extend beyond this:
What is the correct answer?
4
On a floor plan the dashed line that appears approximately 24 outside the exterior wall represents the __________.
What is the correct answer?
4
In order to convert fractional inches into decimal inches ________.
A. Look on a metric conversion chart
B. Divide the numerator (top number) by the denominator (bottom number)
C. Check the engineer's scale
What is the correct answer?
4
In order to create an isometric circle to represent a hole through the top surface of a box, the drafter must insure that the correct iso-plane has been selected by scrolling through the iso-planes using the ________ key.
What is the correct answer?
4
An oil refinery relies on which type of drafter to maintain and update the technical piping drawings used for the construction and maintenance of the facility.
What is the correct answer?
4
Architectural dimensioning is usually done in ________.
What is the correct answer?
4
In architectural drawing ________ are often used to illustrate and detail structural components.
A. Foundation beam detail sections
What is the correct answer?
4
In the mechanical design process the first step is to ________.
B. Prepare rough sketches
What is the correct answer?
4
The distance a screw thread advances axially in one turn is the:
What is the correct answer?
4
In an oblique drawing, equally spaced partial circles may be used to show this:
What is the correct answer?
4
The thread note for a typical bolt will include the ________.
A. Major diameter of the thread
What is the correct answer?
4
This is a rounded exterior blend between surfaces:
What is the correct answer?
4
The dimension text size is determined by what the architect deems necessary in __________.
What is the correct answer?
4
A partial auxiliary view usually shows only features on the ________ of the inclined line and not any projection of other planes.
What is the correct answer?
4
This type of auxiliary view is projected onto a plane that is perpendicular to one of the principal planes of projection:
What is the correct answer?
4
When lettering a CAD drawing, for clarity you should limit the number of fonts to:
What is the correct answer?
4
The foundation contractor will work with the following architectural plans.
What is the correct answer?
4
This type of section is not in direct projection from the view containing the cutting plane:
What is the correct answer?
4
These weld symbols have no arrow-side or other-side significance:
A. Projection or seam weld
C. Surface or groove weld
What is the correct answer?
4
A ________ is the person responsible for verifying that the drawings in a project set are free of mistakes.