By finding all the significant informations regarding the job, work place and machine tool etc.
By breaking up each operation into small elements which are measurable with the help of the measuring device accurately
By observing and recording the time taken by the operator for an operation
All of the above
D. All of the above
Analyse material handling
Determine inventory control difficulties
Plan material handling procedure and routes
All of the above
Latest allowable time and the normal expected time
Latest allowable time and the earliest expected time
Proposed allowable time and the earliest expected time
Normal allowable time and the latest expected time
All industries
All industries other than small and medium industries
Volunteers
The industries notified by Government
Jack Gilbert
Gantt
Taylor
Newton
Analysis of a man-work method by using a motion picture camera with a timing device in the field of view
Motion study observed on enhanced time intervals
Motion study of a sequence of operations conducted systematically
Study of man and machine conducted simultaneously
Strict adherence to specification
Separation of planning and design part
Each individual maintains functional efficiency
All of the above
A project will always be behind schedule, if left uncorrected
Cost of project will always be more than the estimated cost, if no timely corrections are taken
A project can be subdivided into a set of predictable, independent activities
Activities are fixed and can't be changed
Greater
Smaller
Equal
There is no such correlation
Combined Process Method
Critical Path Method
Common Planning Method
Critical Process Method
Prescribes the sequence of operations to be followed
Determines the programme for the operations
Is concerned with starting of processes
Regulates the progress of job through various processes
Maximum float
Minimum float
Zero float
Average float
CPA (Critical Path Analysis)
CPP (Critical Path Plotted)
CPS (Critical Path Scheduling)
All of the above
Minimum value
Maximum value
Average value
Middle value
Improving a work method
Improvising a work method
Designing a work method
Reducing inventory costs
Halsey plan
Gantt plan
Emerson's efficiency plan
Rowan plan
50 %
66.67 %
75 %
80 %
Analytical-layout
Synthetic layout
Static product layout
None of these
Value analysis
Network analysis
Linear programming
Queuing theory
Inspection
Transport
Delay/temporary storage
Permanent storage
Free float = total float
Independent float = total float
Independent float > free float
Independent float < free float
Complicated items only
Simple items only
Crash programmer items only
Any item
Factory overheads
Factory and administration overheads
Factory, administration and sales overheads
Factory, administration, sales overheads and profit
Where low volume of production is required
Where similar jobs are manufactured on similar machines
Where machines are arranged on functional basis
All of the above
Differential piece rate system
Rowan plan
Emerson plan
Taylor plan
Highly skilled workers are needed
Unit costs are high
Operations are labour-intensive
All of these
A slow worker
A fast worker
An average worker
An apprentice
Work sampling
Time study
Method study
Work study
0.50
0.66
0.84
0.95
Earliest start time + duration of activity
Earliest start time duration of activity
Latest finish time + duration of activity
Latest finish time duration of activity
Functional organisation
Line organisation
Staff organisation
Line and staff organisations