Home
Current Affairs January 2024

What is the correct answer?

4

Time study is carried out to determine the time required to complete job by

A. A slow worker

B. A fast worker

C. An average worker

D. An apprentice

Correct Answer :

C. An average worker


Related Questions

What is the correct answer?

4

The objective of time study is to determine the time required to complete a job by

A. Fast worker

B. Average worker

C. Slow worker

D. New entrant

What is the correct answer?

4

Father of time study was

A. F.W. Taylor

B. H.L. Gantt

C. F.B. Gilbert

D. R.M. Barnes

What is the correct answer?

4

Bar chart is suitable for

A. Large project

B. Major work

C. Minor work

D. All of these

What is the correct answer?

4

The chart which gives an estimate about the amount of materials handling between various work stations is known as

A. Flow chart

B. Process chart

C. Travel chart

D. Operation chart

What is the correct answer?

4

The start or completion of task is called

A. An event

B. An activity

C. A duration

D. None of these

What is the correct answer?

4

The purpose of micro-motion study is to

A. Assist in finding out the most efficient way of doing work

B. Train the individual operator regarding the motion economy principles

C. Help in collecting the motion time data for synthetic time standards

D. All of the above

What is the correct answer?

4

The main object of scientific layout is

A. To produce better quality of product

B. To utilise maximum floor area

C. To minimise production delays

D. All of these

What is the correct answer?

4

Bar charts are suitable for

A. Minor works

B. Major works

C. Large projects

D. All of the above

What is the correct answer?

4

Halsey plan of wage incentive

A. Is not applied to all level of workers

B. Is applied to all level of workers

C. Does not guarantee minimum wage

D. Is based upon efficiency of worker

What is the correct answer?

4

Work study is concerned with

A. Improving present method and finding standard time

B. Motivation of workers

C. Improving production capability

D. Improving production planning and control

What is the correct answer?

4

The process capability of a machine is defined as the capability of the machine to

A. Produces a definite volume of work per minute

B. Perform definite number of operations

C. Produce job at a definite spectrum of speed

D. Holds a definite spectrum of tolerance and surface finish

What is the correct answer?

4

Travel charts are used to

A. Analyse material handling

B. Determine inventory control difficulties

C. Plan material handling procedure and routes

D. All of the above

What is the correct answer?

4

The critical activity has

A. Maximum float

B. Minimum float

C. Zero float

D. Average float

What is the correct answer?

4

In manufacturing management, the term 'Dispatching' is used to describe

A. Dispatch of sales order

B. Dispatch of factory mail

C. Dispatch of finished product of the user

D. Dispatch of work orders through shop floor

What is the correct answer?

4

Pick up the incorrect statement from the following. A critical ratio scheduling

A. Establishes the relative priorities among various activities on a common basis

B. Determines the status of each activity

C. Adjusts automatically changes in activity progress

D. None of the above

What is the correct answer?

4

Routing prescribes the

A. Flow of material in the plant

B. Proper utilization of man power

C. Proper utilization of machines

D. Inspection of final product

What is the correct answer?

4

Critical path moves along the activities having total float of

A. Positive value

B. Negative value

C. Zero value

D. Same value

What is the correct answer?

4

A feasible solution to the linear programming problem should

A. Satisfy the problem constraints

B. Optimise the objective function

C. Satisfy the problem constraints and non-negativity restrictions

D. Satisfy the non-negativity restrictions

What is the correct answer?

4

Which of the following organisations is best suited for steel plants

A. Functional organisation

B. Line organisation

C. Staff organisation

D. Line, staff and functional organisations

What is the correct answer?

4

The most important objective behind plant layout is

A. Overall simplification, safety of integration

B. Economy in space

C. Maximum travel time in plant

D. To provide conveniently located shops

What is the correct answer?

4

Military organisation is known as

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. All of the above

What is the correct answer?

4

Templates are used for

A. A planning layout

B. Flow of material

C. Advancing a programme in automatic machines

D. Copying complicated profiles

What is the correct answer?

4

Choose the wrong statement. Motion study is used for

A. Improving a work method

B. Improvising a work method

C. Designing a work method

D. Reducing inventory costs

What is the correct answer?

4

One time measurement unit (TMU) in method time measurement system equals

A. 0.0001 minute

B. 0.0006 minute

C. 0.006 minute

D. 0.001 minute

What is the correct answer?

4

Production cost refers to prime cost plus

A. Factory overheads

B. Factory and administration overheads

C. Factory, administration and sales overheads

D. Factory, administration, sales overheads and profit

What is the correct answer?

4

According to Rowan plan of wage incentive system, bonus is paid to a worker

A. Whose output exceeds 67% efficiency

B. On the percentage of time saved

C. On the percentage of time worked

D. On the percentage of standard time

What is the correct answer?

4

The correct sequence of phases in value engineering is

A. Creative phase, information phase, investigation phase, evaluation phase

B. Information phase, creative phase, investigation phase, evaluation phase

C. Investigation phase, information phase, creative phase, evaluation phase

D. Creative phase, investigation phase, evaluation phase, information phase

What is the correct answer?

4

Breakeven analysis consists of

A. Fixed cost

B. Variable cost

C. Fixed and variable costs

D. Operation costs

What is the correct answer?

4

Time study is used to

A. Determine standard costs

B. Determine the number of machines a person may run

C. Provide a basis for setting piece price or incentive wages

D. All of the above

What is the correct answer?

4

If a worker gets a daily wage of Rs HA, then according to Rowan plan, his maximum daily earnings can be

A. 2 HA

B. 1.33 HA

C. 1.5 HA

D. 1.15 HA