Home
Current Affairs January 2024

What is the correct answer?

4

Time study is used to

A. Determine standard costs

B. Determine the number of machines a person may run

C. Provide a basis for setting piece price or incentive wages

D. All of the above

Correct Answer :

D. All of the above


Related Questions

What is the correct answer?

4

The salient feature of functional organisation is

A. Strict adherence to specification

B. Separation of planning and design part

C. Each individual maintains functional efficiency

D. All of the above

What is the correct answer?

4

The objective of time study is to determine the time required to complete a job by

A. Fast worker

B. Average worker

C. Slow worker

D. New entrant

What is the correct answer?

4

In ABC control policy, maximum attention is given to

A. Those items which consume money

B. Those items which are not readily available

C. Those × items which are in more demand

D. Those items which consume more money

What is the correct answer?

4

The time required to complete a job is established and a bonus is paid to the worker based on the exact % of time saved. This type of incentive plan is known as

A. Dry work Plan

B. Halsey Premium Plan

C. Taylor Plan

D. Rowan Plan

What is the correct answer?

4

The time required to complete a task is established and a bonus is paid to the worker for every hour he saves from the established time required. This type of incentive plan is known as

A. Rowan Plan

B. Taylor Differential Piece rate system

C. Halsey Premium plan

D. Day work plan

What is the correct answer?

4

Pessimistic time is

A. The maximum time which an activity might require

B. The average time required for a job

C. The most probable time considering all conditions

D. The minimum time in which an activity can possibly be accomplished

What is the correct answer?

4

Routing assists engineers in deciding in advance

A. The flow of material in the plant

B. The methods of proper utilization of manpower

C. The methods of proper utilization of machines

D. The layout of factory facilities

What is the correct answer?

4

Breakeven analysis is a

A. Short term analysis

B. Long term analysis

C. Average of short and long term analysis

D. Any one of these

What is the correct answer?

4

In Emerson's efficiency plan of wage incentive system, bonus is paid to a worker

A. Whose output exceeds 67% efficiency

B. On the percentage of time saved

C. On the percentage of time worked

D. On the percentage of standard time

What is the correct answer?

4

The amount deducted from the salary of workers towards employees provident fund is

A. Credited into reserves of company

B. Deposited in nationalised bank

C. Deposited in post office

D. Deposited in the account of worker with Provident Fund Commissioner

What is the correct answer?

4

The simplex method is the basic method for

A. Value analysis

B. Operation research

C. Linear programming

D. Model analysis

What is the correct answer?

4

PERT

A. Provides an approach for keeping planning up-to-date

B. Provides a way for management to require that planning be done on a uniform and logical basis

C. Permits management to foresee quickly the impact of variations from the plan

D. All of the above

What is the correct answer?

4

The wastage of material in the store is taken into account by the following method in the evaluation of the material issued from the store

A. Inflated system

B. Primary cost method

C. Current value method

D. Fixed price method

What is the correct answer?

4

Tick the odd man out

A. Taylor

B. Drucker

C. McGregor

D. Galileo

What is the correct answer?

4

Discrepancies of bar chart techniques are

A. Consequential effects of lack in one activity on the finish date

B. Free time available for an activity can't be predicted

C. Effective monitoring/controlling can't be done

D. All of the above

What is the correct answer?

4

Micro-motion study is

A. Analysis of one stage of motion chart

B. Motion study, when seen on a time chart

C. Subdivision of an operation into therbligs and their analysis

D. Enlarged view of motion study

What is the correct answer?

4

PERT analysis is based on

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All of the above

What is the correct answer?

4

When slack of an activity is negative

A. It represents a situation where extra resources are available and the completion of project is not delayed

B. It represents that a programme falls behind schedule and additional resources are required to complete the project in time

C. The activity is critical and any delay in its performance will delay the completion of whole project

D. All of the above

What is the correct answer?

4

Actual performance of a task is called

A. An event

B. An activity

C. A duration

D. None of these

What is the correct answer?

4

PERT is applied for

A. Marketing programmes and advertising programmes

B. Installation of machinery

C. Research and development of products

D. All of these

What is the correct answer?

4

The artificial activity, which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as

A. Event

B. Free float

C. Artificial

D. Dummy

What is the correct answer?

4

Positive slack on a PERT indicates that project is

A. Ahead of schedule

B. Beyond schedule

C. As per schedule

D. On critical path

What is the correct answer?

4

If (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual time, then according to Rowan plan, wages for the job will be

A. TR

B. TR + [(S - T)/2] × R

C. TR + (S - T) × R

D. TR + [(S - T)/S] × R

What is the correct answer?

4

CPM requires

A. Single time estimate

B. Double time estimate

C. Triple time estimate

D. None of these

What is the correct answer?

4

Dummy activities are used to

A. Determine the critical path

B. Determine the project completion time

C. Maintain the required net work

D. None of these

What is the correct answer?

4

The type of layout used for manufacturing steam turbines, is

A. Product layout

B. Process layout

C. Fixed position layout

D. Any one of these

What is the correct answer?

4

In the perpetual inventory control, the material is checked when it reaches its

A. Minimum value

B. Maximum value

C. Average value

D. Alarming value

What is the correct answer?

4

In the Halsey system of wage incentive plan, a worker is

A. Paid as per efficiency

B. Ensured of minimum wages

C. Not paid any bonus till his efficiency

D. Never a loser

What is the correct answer?

4

Slack of various events on the critical path in PERT/CPM chart

A. Increases continuously

B. Decreases continuously

C. Remain constant

D. May increase or decrease depending on various factors

What is the correct answer?

4

Which of the following depreciation system ensures that the interest be charged on the cost of machine asset every year on the book value, but the rate of depreciation every year remains constant

A. Sinking fund method

B. Straight line method

C. ABC charging method

D. Annuity charging method