First class bricks are used
Vertical joints in alternate courses are kept in plumb line
Bats are used where necessary
All the above
D. All the above
Sedimentary rock
Metamorphic rock
Igneous rock
None of the above
Heart shakes
Cupshakes
Starshakes
Rindgalls
0.5 m
0.7 m
0.9 m
1.2 m
Free from voids
Glossy
Durable
Uniform
The pile driven in sand is called sand pile
The drilled hole filled with sand is called sand pile
The sand piles are used for bearing purposes
None of these
5 cm
10 cm
15 cm
20 cm
To support the frame work of the roof
To receive the ends of principal rafter
To prevent the walls from spreading outward
To prevent the tie beam from sagging at its centre
2 metres
2.5 metres
3 metres
None of the above
25 to 50 mm
30 to 125 mm
50 to 100 mm
75 to 125 mm
55 cm
70 cm
85 cm
100 cm
(i) and (iii)
(i) and (iv)
(ii) and (iii)
(ii) and (iv)
Friction pile
Sheet pile
Batter pile
Anchor pile
Are vertical wooden members
Is the upper horizontal wooden member
Is the lower horizontal wooden member
Are the intermediate horizontal wooden members
The column spacing
One-third the column spacing
Half the column spacing
Three-fourth the column spacing
25 to 50 mm
25 to 75 mm
30 to 125 mm
50 to 100 mm
Verticals
Reveals
Jambs
None of these
b/2
b/3
b/4
b/6
10 cm
15 cm
Equal to its projection beyond wall base
Less than its projection beyond wall base
Cornice
Coping
Frieze
Lintel
Scaffolding
Dead shore
Raking shore
Under pinning
Swelling and shrinkage characteristics prevail
Consolidation continues even after several years of construction
Differential settlement is generally prevalent
All the above
H-pile
Pipe pile
Screw pile
Disc pile
Lean concrete bed is provided
Thick concrete bed is provided
Reinforced concrete bed is provided
Both (a) and (c) of the above
Simplex pile
Pedestal pile
Vibro pile
Both (a) and (c) of the above
Double Flemish bond facing and English bond backing in each course
English bond facing and double Flemish bond backing in each course
Stretcher bond facing and double Flemish bond backing in each course
Double Flemish bond facing and header bond backing in each course
Intrados
Rise
Spandril
Extrados
Ridge
Hip
Valley
None of these
Cavity of a cavity wall should start near ground level
Cavity of a cavity wall should terminate near eaves level of sloping roof
Cavity of a cavity wall should terminate near coping of flat roof with parapet wall
All the above
1 day
4 days
7 days
14 days
Equal to width of stairs
Half the width of stairs
Twice the width of stairs
One fourth the width of stairs