Related Questions
What is the correct answer?
4
Once the architect has finalized the house plans with the client any changes to the design requested by the client will require a ________.
C. Whole new set of drawings
What is the correct answer?
4
These maps are used to plan construction projects that locate construction features so they fit the topography of the area:
C. Structural topography maps
D. Structure location plans
What is the correct answer?
4
Some of the common terms used to describe technical drawing include:
What is the correct answer?
4
The most common geometric form used in gears today is this:
What is the correct answer?
4
The condition of a part when it contains the least amount of material is referred to as ________.
What is the correct answer?
4
On typical electronic diagrams, these items need not be shown unless they are needed for clarification:
What is the correct answer?
4
In architectural drawing ________ are often used to illustrate and detail structural components.
A. Foundation beam detail sections
What is the correct answer?
4
In this type of drawing, vertical pipes may be revolved into the horizontal plane:
What is the correct answer?
4
The UCS icon represents the intersection of the ________.
What is the correct answer?
4
The Auto-CAD command used to combine two or more primitive shapes into a single complex 3-dimensional model is ________.
What is the correct answer?
4
This material is used in masonry construction, most commonly for ornamental facing:
What is the correct answer?
4
This type of circuit is a semiconductor wafer or chip:
What is the correct answer?
4
This type of thread is a thread on the inside of a member:
What is the correct answer?
4
Objects that are symmetric can be shown effectively using this type of section:
What is the correct answer?
4
Which of the following is one of the basic types of welded joints:
What is the correct answer?
4
This is a rounded exterior blend between surfaces:
What is the correct answer?
4
The top, front, and bottom views align in this manner:
C. According to the planar views
D. Parallel to the frontal plane
What is the correct answer?
4
Once a drawing is determined to be complete, the title block is used to document the change from:
A. A draft to a finished drawing
B. A finished to a working drawing
C. An assembly to a finished drawing
D. A working drawing to a draft
What is the correct answer?
4
This is a systematic approach that integrates the design and manufacture of products with the goal of optimizing the process:
A. Traditional engineering design
B. The manufacturing process
What is the correct answer?
4
This means that a feature of a finished product contains the maximum amount of material permitted by the tolerance dimensions for that feature:
A. Maximum material condition
B. Machined material condition
C. Maximum machined indication
D. Machine mark indication
What is the correct answer?
4
Acceptable parts must not extend beyond this:
What is the correct answer?
4
This type of projection is when projectors are parallel to each other, but is at an angle other than 90 degrees to the plane of projection:
B. Perpendicular projection
What is the correct answer?
4
In order to create one solid model from two or more separate solid shapes the drafter will need to position them and then ________.
A. Use Union to join them
C. Use the Add Parts tool
What is the correct answer?
4
Using the Relative Polar Coordinate System to add a 3 inch line that is 45 degrees from the end point of the line created above the drafter would ________.
B. Type 3 back slash and enter
C. Type 3 forward slash and enter
D. Type 3 and try to use the Dynamic Input readout to find the end point
What is the correct answer?
4
Dimensions are used on the elevation plan to describe ________.
A. Finished floor elevations
What is the correct answer?
4
In offset sections, offsets or bends in the cutting plane are all:
C. Either 90 or 180 degrees
What is the correct answer?
4
Three dimensional models are often used in the design process to __________.
A. Help the client understand the overall design concept
B. Help the client select a color for their carpet
C. Provide the client with a model which they can use to impress their friends
D. Determine the quantity of brick needed to build the house
What is the correct answer?
4
A projection weld is a type of:
What is the correct answer?
4
In U.S. structural and architectural drafting, all dimensions of this length are usually expressed in feet and inches:
What is the correct answer?
4
The ________ dimension tool will place the length of an angled line.