What is the correct answer?

4

which is used to measure POFOD?

A. The time between system failure

B. The frequency of occurrence with which unexpected behaviour is likely to occur

C. The elapsed repair or restart time when a system failure occurs. Given that the system must be continuously available.

D. The number of system failures given a number of systems inputs.

Correct Answer :

D. The number of system failures given a number of systems inputs.


Related Questions

What is the correct answer?

4

Which of the following is a the process metric which is useful for assessing maintainability?

A. Number of request for corrective maintenance

B. Average time required for impact analysis

C. All the above

D. Number of oustanding change request

What is the correct answer?

4

State True or False.
1. Investors and owners are also significant stakeholders who make demands on a system in terms of financial goals.
2. Experts and consultants are another stakeholder class who can strongly affect problem definition.

A. 1-False, 2-False

B. 1-True, 2-False

C. 1-False, 2-True

D. 1-True, 2-True

What is the correct answer?

4

Which of the following is one of the phase of software life cycle?

A. Design

B. Project Management

C. Maintenance

D. Quality management

What is the correct answer?

4

_____ is the most widely used single measure of information technology success

A. User satisfaction

B. Job satisfaction

C. Business success

D. Profit making

What is the correct answer?

4

Integrating business processes with the Internet leads to far greater _____ between customers and suppliers.

A. Understanding

B. Restrictions

C. Transparency

D. Controversy

What is the correct answer?

4

State True or False.
1. Ubiquitous computing lead to an environment in which the cycle time and costs of the business processes are increased.
2. Software technology facilitates communication between devices in a multimedia fashion.

A. 1-True, 2-True

B. 1-True, 2-False

C. 1-False, 2-True

D. 1-False, 2-False

What is the correct answer?

4

State True or False.
1. Curtis, Kellner, and Over identified five uses for process models.
2. Blackburn et al. identified the five most influential factors in the development process.

A. 1-True, 2-True

B. 1-True, 2-False

C. 1-False, 2-True

D. 1-False, 2-False

What is the correct answer?

4

Which of the following are the steps in identifying the transforming process of data- flow diagram to structure chart?

A. Identify system- processing transformation

B. Identify input transformation

C. Identify output transformation

D. All the above

What is the correct answer?

4

Process technology enabled the support of the rapid application development needed for iterative approaches with their greater emphasis on risk _____ and user _____.

A. Minimization, Satisfaction

B. Minimization, Dissatisfaction

C. Maximization, Satisfaction

D. Maximization, Dissatisfaction

What is the correct answer?

4

The economic success of an application is measured in terms of metrics such as _____.

A. Profit maximization

B. Cost reduction

C. Customer satisfaction

D. All of the above

What is the correct answer?

4

_____ is the open source software.

A. Internet Explorer

B. Mozilla

C. MS-Office

D. Oracle

What is the correct answer?

4

which is used to measure POFOD?

A. The time between system failure

B. The frequency of occurrence with which unexpected behaviour is likely to occur

C. The elapsed repair or restart time when a system failure occurs. Given that the system must be continuously available.

D. The number of system failures given a number of systems inputs.

What is the correct answer?

4

In object oriented design of software which of the following is not true?

A. objects inherit the properties of the class

B. classes are defined based on the attributes of the object

C. objects can belong to two classes

D. classes are always different

What is the correct answer?

4

What is meant by the term software crisis?

A. Ability to deliver software on time with good quality

B. A situation in which experienced developers leave the company

C. Inability of new software to inter-operate with existing software

D. Instability in the development team

What is the correct answer?

4

Software engineers should not use their technical skills to misuse other peoples computers.Here the term misuse refers to:

A. Unauthorized modification of computer material

B. Unauthorized access to computer material

C. Dissemination of viruses or other malware

D. All of the mentioned

What is the correct answer?

4

Design phase includes?

A. data,architectural and procedural designs only

B. architectural,procedural and interface design only

C. data,architectural and interface design only

D. data,architectural interface and procedural design

What is the correct answer?

4

Explain what is meant by PRODUCT with reference to one of the eight principles as per the ACM/IEEE Code of Ethics ?

A. Software engineers shall ensure that their products and related modifications meet the highest professional standards possible.

B. The product should be easy to use.

C. It means that the product designed /created should be easily available.

D. Software engineers shall ensure that their products and related modifications satisfy the client.

What is the correct answer?

4

_____ interacts with the system at the financial level.

A. Accounting Personnel

B. Database Manager

C. Salesman

D. System Operator

What is the correct answer?

4

_____ refers to the elimination or reduction of third-party intermediaries between the client or customer.

A. Intermediation

B. Disintermediation

C. Mediation

D. None of the above

What is the correct answer?

4

Which of the following are the activities of the function- oriented design.

A. Data- flow design

B. Structural decomposition

C. Detailed design description

D. All the above

What is the correct answer?

4

Tools used in the early phases of the life cycle are called _____ CASE tools.

A. Lower

B. Back-end

C. Intermediate

D. Upper

What is the correct answer?

4

Choose the correct option in terms of Issues related to professional responsibility

A. Confidentiality

B. Intellectual property rights

C. Managing Client Relationships

D. Both a & b

What is the correct answer?

4

Open source development model best suits for _____.

A. Large system applications

B. Small system applications

C. Medium system applications

D. Very small system applications

What is the correct answer?

4

Which of the following is a technical factor which affect software maintenance cost?

A. Application Domain

B. Staff stability

C. Programming language

D. External environment

What is the correct answer?

4

State True or False.
1. People are at the core of problem solving because business problems are solved by people for people.
2. The structure of the group and its efficiency of communications, style of management, and cohesiveness are critical factors in the effectiveness of the team.

A. 1-True, 2-True

B. 1-True, 2-False

C. 1-False, 2-True

D. 1-False, 2-False

What is the correct answer?

4

Feller and Fitzgerald observe that between _____ percent of software costs are traditionally associated with the post-development, maintenance phase of the software life cycle.

A. 70 to 80

B. 30 to 40

C. 50 to 60

D. 10 to 20

What is the correct answer?

4

In Software Engineering, people are considered as a/an _____.

A. Asset

B. Resource

C. Problem Solver

D. Knowledge Provider

What is the correct answer?

4

The SOFL model of Liu and colleagues (1997) presents an integrated approach that adopts _____ methodologies in the requirements phases and _____ methodologies in the design and implementation phases

A. Procedure-oriented, Structured

B. Structured, Procedure-oriented

C. Structured, Object-oriented

D. Object-oriented, Structured

What is the correct answer?

4

_____ focused on the Waterfall and prototype models in their empirical study, emphasizing the factors driving the usage of specific process models.

A. Boehm and Belz

B. Khalifa and Verner

C. Madhavji et al.

D. Blackburn et al.

What is the correct answer?

4

UAN stands for _____.

A. User Action Notation

B. User Action Norms

C. User Analogy Notation

D. User Analogy Norms