Home
Current Affairs January 2024

What is the correct answer?

4

Which of the following are the guidelines for the construction of a network diagram?

A. Each activity is represented by one and only one arrow in the network

B. Dangling must be avoided in a network diagram

C. Dummy activity consumes no time or resource

D. All of the above

Correct Answer :

D. All of the above


Related Questions

What is the correct answer?

4

Which one of the following techniques is used for determining allowances in time study?

A. Acceptance sampling

B. Linear regression

C. Performance rating

D. Work sampling

What is the correct answer?

4

Breakeven analysis is a

A. Short term analysis

B. Long term analysis

C. Average of short and long term analysis

D. Any one of these

What is the correct answer?

4

If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good

A. EF = ES + D

B. LS = LFD

C. LF = LS + D

D. All of the above

What is the correct answer?

4

In ABC control policy, maximum attention is given to

A. Those items which consume money

B. Those items which are not readily available

C. Those × items which are in more demand

D. Those items which consume more money

What is the correct answer?

4

Gantt chart provides information about the

A. Material handling

B. Proper utilisation of manpower

C. Production schedule

D. Efficient working of machine

What is the correct answer?

4

Which of the following incentive plans ensures a part of the swing to the worker and rest to the employer?

A. Emerson efficiency plan

B. Taylor plan

C. Halsey premium plan

D. Gilbert plan

What is the correct answer?

4

The value engineering technique in which experts of the same rank assemble for product development is called

A. Delphi

B. Brain storming

C. Morphological analysis

D. Direct expert comparison

What is the correct answer?

4

The aim of value engineering is to

A. Find the depreciation value of a machine

B. Determine the selling price of a product

C. Minimise the cost without change in quality of the product

D. All of the above

What is the correct answer?

4

PERT is applied for

A. Marketing programmes and advertising programmes

B. Installation of machinery

C. Research and development of products

D. All of these

What is the correct answer?

4

In the Halsey 50-50 plan, the following are rewarded more

A. Past good workers

B. Past poor workers

C. Past average workers

D. All of the above

What is the correct answer?

4

Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it

A. Consumes time, but no resources

B. Consumes resources but no time

C. Consumes neither time nor resources

D. Is a dangling event

What is the correct answer?

4

The term 'value' in value engineering refers to

A. Total cost of the product

B. Selling price of the product

C. Utility of the product

D. Manufactured cost of the product

What is the correct answer?

4

The difference between the time available to do the job and the time required to do the job, is known as

A. Event

B. Float

C. Duration

D. Constraint

What is the correct answer?

4

In Emerson's efficiency plan of wage incentive system, bonus is paid to a worker

A. Whose output exceeds 67% efficiency

B. On the percentage of time saved

C. On the percentage of time worked

D. On the percentage of standard time

What is the correct answer?

4

PERT analysis is based on

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All of the above

What is the correct answer?

4

Pick up the incorrect statement from the following

A. An activity of the project is denoted by an arrow on the net work

B. The tail of the arrow indicates the start of the activity

C. The head of the arrow indicates the end of the activity

D. The arrows are drawn (to scale from) left to right

What is the correct answer?

4

PERT is

A. An analytic tool in concept

B. Limit up of event oriented diagrams

C. Used for research and development projects

D. All of the above

What is the correct answer?

4

Actual performance of a task is called

A. An event

B. An activity

C. A duration

D. None of these

What is the correct answer?

4

Acceptance sampling is used in

A. Job production

B. Batch production

C. Mass production

D. All of these

What is the correct answer?

4

Which of the following statement is correct?

A. A-B-C analysis is based on Pareto's principle

B. Simulation can be used for inventory control

C. Economic order quantity formula ignores variations in demand pattern

D. All of the above

What is the correct answer?

4

The time which results in the least possible direct cost of an activity is known as

A. Normal time

B. Slow time

C. Crash time

D. Standard time

What is the correct answer?

4

In the Emerson efficiency plan, a worker receives only his daily wage and no bonus is paid till his efficiency reaches

A. 50 %

B. 66.67 %

C. 75 %

D. 80 %

What is the correct answer?

4

Time study is

A. The appraisal, in terms of time, of the value of work involving human effort

B. Machine setting time

C. Time taken by workers to do a job

D. Method of fixing time for workers

What is the correct answer?

4

PERT stands for

A. Programme Estimation and Reporting Technique

B. Process Estimation and Review Technique

C. Programme Evaluation and Review Technique

D. Planning Estimation and Resulting Technique

What is the correct answer?

4

PERT is the

A. Time oriented technique

B. Event oriented technique

C. Activity oriented technique

D. Target oriented technique

What is the correct answer?

4

A-B-C analysis

A. Is a basic technique of materials management

B. Is meant for relative inventory control

C. Does not depend upon the unit cost of the item but on its annual consumption

D. All of the above

What is the correct answer?

4

The main objective of work measurement is to

A. Plan and schedule of production

B. Formulate a proper incentive scheme

C. Estimate the selling prices and delivery dates

D. All of the above

What is the correct answer?

4

Travel charts provide

A. An idea of the flow of materials at various stages

B. A compact estimate of the handling which must be done between various work sections

C. The information for changes required in rearranging material handling equipment

D. An approximate estimate of the handling which must be done at a particular station

What is the correct answer?

4

For a small scale industry, the fixed cost per month is Rs. 5000. The variable cost per product is Rs. 20 and sales price is Rs. 30 per piece. The break even production per month will be

A. 300

B. 460

C. 500

D. 1000

What is the correct answer?

4

What does symbol 'O' imply in work study?

A. Operation

B. Inspection

C. Transport

D. Delay/temporary storage