Home
Current Affairs January 2024

What is the correct answer?

4

Which of the following is independent of sales forecast?

A. Productivity

B. Inventory control

C. Production planning

D. Production control

Correct Answer :

A. Productivity


Related Questions

What is the correct answer?

4

For ship vessel industry the following layout is best suited

A. Process layout

B. Product layout

C. Fixed position layout

D. Plant layout

What is the correct answer?

4

Job evaluation is the method of determining the

A. Relative worth of jobs

B. Skills required by a worker

C. Contribution of a worker

D. Contribution of a job

What is the correct answer?

4

The time which results in the least possible direct cost of an activity is known as

A. Normal time

B. Slow time

C. Crash time

D. Standard time

What is the correct answer?

4

A systematic job improvement sequence will consist of

A. Motion study

B. Time study

C. Job enrichment

D. All of these

What is the correct answer?

4

The technique of value analysis can be applied to

A. Complicated items only

B. Simple items only

C. Crash programmer items only

D. Any item

What is the correct answer?

4

The probability distribution of activity times in PERT follows following distribution

A. Normal

B. Binomial

C. Beta

D. Exponential

What is the correct answer?

4

Bar chart is suitable for

A. Large project

B. Major work

C. Minor work

D. All of these

What is the correct answer?

4

Earliest finish time can be regarded as

A. Earliest start time + duration of activity

B. Earliest start time duration of activity

C. Latest finish time + duration of activity

D. Latest finish time duration of activity

What is the correct answer?

4

The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as

A. Duration

B. Total float

C. Free float

D. Interfering float

What is the correct answer?

4

Travel charts are used to

A. Analyse material handling

B. Determine inventory control difficulties

C. Plan material handling procedure and routes

D. All of the above

What is the correct answer?

4

PERT requires

A. Single time estimate

B. Double time estimate

C. Triple time estimate

D. None of these

What is the correct answer?

4

A dummy activity in a net work diagram

A. Is represented by a dotted line

B. Is an artificial activity

C. Does not consume time or resources

D. All of these

What is the correct answer?

4

PERT

A. Provides an approach for keeping planning up-to-date

B. Provides a way for management to require that planning be done on a uniform and logical basis

C. Permits management to foresee quickly the impact of variations from the plan

D. All of the above

What is the correct answer?

4

The bonus increases in proportion to the increase in efficiency. This statement applies to

A. Halsey plan

B. Gantt plan

C. Emerson's efficiency plan

D. Rowan plan

What is the correct answer?

4

Standard time as compared to normal time is

A. Greater

B. Smaller

C. Equal

D. There is no such correlation

What is the correct answer?

4

PERT has following time estimate

A. One time estimate

B. Two time estimate

C. Three time estimate

D. Four time estimate

What is the correct answer?

4

PMTP (predetermined motion time systems) include

A. MTM (method time measurement)

B. WFS (work factor systems)

C. BNTS (basic motion time study)

D. All of the above

What is the correct answer?

4

Pick up the incorrect statement about advantages of work sampling

A. Permits a fine breakdown of activities and delays

B. Simultaneous study of many operators may be made by a single observer

C. Calculations are easier, method is economical and less time consuming

D. No time measuring devices are generally needed

What is the correct answer?

4

The two bin system is concerned with

A. Ordering procedure

B. Forecasting sales

C. Production planning

D. Despatching and expediting

What is the correct answer?

4

For handling materials during manufacture of cement, a _________ is widely used.

A. Belt conveyor

B. Bucket conveyor

C. Fork lift truck

D. Overhead crane

What is the correct answer?

4

In process layout

A. Handling and backtracking of materials is too much

B. Production control is more difficult and costly

C. Routing and scheduling is more difficult

D. All of the above

What is the correct answer?

4

An event is indicated on the network by

A. A straight line

B. A number enclosed in a circle or a square

C. A straight line with circles at the ends

D. A dotted line

What is the correct answer?

4

A CPM family includes

A. CPA (Critical Path Analysis)

B. CPP (Critical Path Plotted)

C. CPS (Critical Path Scheduling)

D. All of the above

What is the correct answer?

4

Micro-motion study is

A. Analysis of one stage of motion chart

B. Motion study, when seen on a time chart

C. Subdivision of an operation into therbligs and their analysis

D. Enlarged view of motion study

What is the correct answer?

4

The type of layout used for manufacturing steam turbines, is

A. Product layout

B. Process layout

C. Fixed position layout

D. Any one of these

What is the correct answer?

4

Which of the following wage incentive plan is applied to all workers?

A. Halsey plan

B. Gantt plan

C. Emerson's efficiency plan

D. Rowan plan

What is the correct answer?

4

Routing

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with starting of processes

D. Regulates the progress of job through various processes

What is the correct answer?

4

M.T.M. is used to

A. Improve existing methods

B. Establish time standards

C. Develop effective methods in advance of the beginning of production

D. All of the above

What is the correct answer?

4

Activity slack or float of any event on a PERT/CPM chart is represented by

A. Latest start time of succeeding event earliest finish time of preceding event activity time

B. Latest start time of the event earliest start time of the event

C. Latest finish time of event earliest finish time of the event

D. Anyone of the above

What is the correct answer?

4

If TL is the largest allowable event occurrence time, total activity slack (s) is equal to

A. Latest start time earliest start time

B. Latest finish time earliest finish time (EFT)

C. TLEFT

D. All of the above