Home

Which of the following statement is correct?

A. When slack of an activity is zero, it falls only on critical path.

B. CPM technique is useful to minimise the direct and indirect expenses.

C. Critical path of a net work represents the minimum time required for completion of project.

D. All of the above

Please do not use chat terms. Example: avoid using "grt" instead of "great".

You can do it
  1. Frederick W. Taylor introduced a system of working known as
  2. Which of the following statement is correct about the network diagram?
  3. Statistical quality control techniques are based on the theory of
  4. Two alternatives can produce a product. First have a fixed cost of Rs. 2000 and a variable cost of Rs.…
  5. The factors which are to be considered while developing a good wage incentive plan will include
  6. Acceptance sampling is used in
  7. Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is _________…
  8. The production cost per unit can be reduced by
  9. Which of the following equations is not in conformity with others?
  10. The deductions for, employees provident fund start
  11. In PERT analysis, critical path is obtained by joining events having
  12. The reasons which are basically responsible for the formation of a queue should be that
  13. Pick up the correct statement about relationship between various floats
  14. The probability distribution of activity times in PERT follows following distribution
  15. Father of time study was
  16. The most suitable incentive plan for the maintenance section of an industry will be
  17. In the Halsey 50-50 plan, the following are rewarded more
  18. Standing orders which are statutory are applicable to
  19. Inventory control in production, planning and control aims at
  20. The unit cost in case of batch production is ________ as compared to jobbing production.
  21. Product layout is employed for
  22. In the cost structure of a product, the selling price is determined by the factors such as
  23. If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start…
  24. A dummy activity in a net work diagram
  25. An event is indicated on the network by
  26. According to MAPI formula, the old machine should be replaced by new one when (CAM = Challenger's Adverse…
  27. A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations…
  28. The time taken by a trained worker to perform an operation, while working a steady pace, is known as
  29. For material transportation, conveyors are used when the prevailing conditions include
  30. A dummy activity