Home

Which of the following statement is correct about the network diagram?

A. The events are represented graphically by circles or nodes at the beginning and the end of activity by arrows.

B. The tail end of the arrow represents the start of an activity.

C. The head of the arrow represents the end of an activity.

D. All of the above

Please do not use chat terms. Example: avoid using "grt" instead of "great".

You can do it
  1. According to Rowan plan of wage incentive system, bonus is paid to a worker
  2. The product layout
  3. PERT stands for
  4. Bar chart is suitable for
  5. Work sampling is applied for
  6. Works cost implies
  7. A-B-C analysis is used in
  8. Critical Path Net Work helps an engineer
  9. The most suitable incentive plan for the maintenance section of an industry will be
  10. The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time, and tn = Most…
  11. The process capability of a machine is defined as the capability of the machine to
  12. The time by which the activity completion time can be delayed without affecting the start of succeeding…
  13. Break-even analysis can be used for
  14. In CPM, the cost slope is determined by
  15. The assumption in PERT is
  16. The average time recorded by work study man for an operation is called
  17. An optimum project schedule implies
  18. In the Halsey system of wage incentive plan, a worker is
  19. Micro motion study is
  20. Which of the following equations is not in conformity with others?
  21. Standing orders which are statutory are applicable to
  22. 'Value' for value engineering and analysis purposes is defined as
  23. Pick up the incorrect statement from the following. A critical ratio scheduling
  24. Acceptance sampling is widely used in
  25. Probabilistic time for completion of any activity can be found out from
  26. The factors to be considered for production scheduling are
  27. The main objective of work measurement is to
  28. Pick up the correct statement from the following
  29. The time of completing a project in network analysis is given by following time of the critical activity…
  30. Dispatching