Home
Current Affairs January 2024

What is the correct answer?

4

Which of the following statement is correct about the network diagram?

A. The events are represented graphically by circles or nodes at the beginning and the end of activity by arrows.

B. The tail end of the arrow represents the start of an activity.

C. The head of the arrow represents the end of an activity.

D. All of the above

Correct Answer :

D. All of the above


Related Questions

What is the correct answer?

4

CPM is

A. Synthesising in concepts

B. Is built of activities oriented programmes

C. Is used for repetitive works

D. All of the above

What is the correct answer?

4

CPM requires

A. Single time estimate

B. Double time estimate

C. Triple time estimate

D. None of these

What is the correct answer?

4

The most suitable incentive plan for the maintenance section of an industry will be

A. Piece rate system

B. Group incentive plan

C. Profit sharing plans

D. Simplification

What is the correct answer?

4

Travel charts are used to

A. Analyse material handling

B. Determine inventory control difficulties

C. Plan material handling procedure and routes

D. All of the above

What is the correct answer?

4

PERT requires

A. Single time estimate

B. Double time estimate

C. Triple time estimate

D. None of these

What is the correct answer?

4

An activity of the project is graphically represented by ________ on the network diagram.

A. A circle

B. A straight line

C. An arrow

D. None of these

What is the correct answer?

4

The linear programming techniques can be applied successfully to industries like

A. Iron and steel

B. Food processing

C. Oil and chemical

D. All of the above

What is the correct answer?

4

Merit Rating is the method of determining worth of

A. A job

B. An individual employee

C. A particular division in workshop

D. Machine

What is the correct answer?

4

Basic tool in work study is

A. Graph paper

B. Process chart

C. Planning chart

D. Stop watch

What is the correct answer?

4

Process layout is employed for

A. Batch production

B. Continuous type of product

C. Effective utilisation of machines

D. All of the above

What is the correct answer?

4

Gantt chart provides information about the

A. Material handling

B. Proper utilisation of manpower

C. Production schedule

D. Efficient working of machine

What is the correct answer?

4

According to MAPI formula, the old machine should be replaced by new one when (CAM = Challenger's Adverse minimum DAM = Defender's Adverse minimum)

A. CAM < DAM

B. CAM > DAM

C. CAM = DAM

D. There is no such criterion

What is the correct answer?

4

Routing prescribes the

A. Flow of material in the plant

B. Proper utilization of man power

C. Proper utilization of machines

D. Inspection of final product

What is the correct answer?

4

Breakeven analysis consists of

A. Fixed cost

B. Variable cost

C. Fixed and variable costs

D. Operation costs

What is the correct answer?

4

The basic difference between PERT and CPM is that

A. PERT deals with events and CPM with activities

B. Critical path is determined in PERT only

C. Costs are considered on CPM only and not in PERT

D. Guessed times are used in PERT and evaluated times in CPM

What is the correct answer?

4

Gantt charts are used for

A. Forecasting sales

B. Production schedule

C. Scheduling and routing

D. Linear programming

What is the correct answer?

4

In the perpetual inventory control, the material is checked when it reaches its

A. Minimum value

B. Maximum value

C. Average value

D. Alarming value

What is the correct answer?

4

Standard time is defined as

A. Normal time + allowances

B. Normal time + idle time + allowances

C. Normal time + idle time

D. Only normal time for an operation

What is the correct answer?

4

Which of the following statement is correct about the network diagram?

A. The events are represented graphically by circles or nodes at the beginning and the end of activity by arrows.

B. The tail end of the arrow represents the start of an activity.

C. The head of the arrow represents the end of an activity.

D. All of the above

What is the correct answer?

4

The process layout is best suited where

A. Specialisation exists

B. Machines are arranged according to sequence of operation

C. Few number of non-standardised units is to be produced

D. Mass production is envisaged

What is the correct answer?

4

The correct sequence of phases in value engineering is

A. Creative phase, information phase, investigation phase, evaluation phase

B. Information phase, creative phase, investigation phase, evaluation phase

C. Investigation phase, information phase, creative phase, evaluation phase

D. Creative phase, investigation phase, evaluation phase, information phase

What is the correct answer?

4

The aim of value engineering is to

A. Find the depreciation value of a machine

B. Determine the selling price of a product

C. Minimise the cost without change in quality of the product

D. All of the above

What is the correct answer?

4

Which one of the following represents a group incentive plan?

A. Halsey Premium Plan

B. Lincoln Plan

C. Rowan Plan

D. Taylor Plan

What is the correct answer?

4

Fixed position layout is also known as

A. Analytical layout

B. Synthetic layout

C. Static product layout

D. None of these

What is the correct answer?

4

Pick up the correct statement about relationship between various floats

A. Free float = total float

B. Independent float = total float

C. Independent float > free float

D. Independent float < free float

What is the correct answer?

4

Which of the following incentive plans ensures a part of the swing to the worker and rest to the employer?

A. Emerson efficiency plan

B. Taylor plan

C. Halsey premium plan

D. Gilbert plan

What is the correct answer?

4

Routing

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with starting of processes

D. Regulates the progress of job through various processes

What is the correct answer?

4

The critical path of a network represents

A. The minimum time required for completion of project

B. The maximum time required for completion of project

C. Maximum cost required for completion of project

D. Minimum cost required for completion of project

What is the correct answer?

4

The most important function of inventory control is

A. Stock control system

B. To run the stores effectively

C. Technical responsibility for the state of materials

D. All of the above

What is the correct answer?

4

F. W. Taylor introduced a system of organisation known as

A. Line organisation

B. Functional organisation

C. Line and staff organisation

D. Line, staff and functional organisation