Home
Current Affairs January 2024

What is the correct answer?

4

Which of the following wage incentive plan is applied to all workers?

A. Halsey plan

B. Gantt plan

C. Emerson's efficiency plan

D. Rowan plan

Correct Answer :

A. Halsey plan


Related Questions

What is the correct answer?

4

A device used for lifting or lowering objects suspended from a hook at the end of retractable chains or cable is called

A. Hoist

B. Jib crane

C. Portable elevator

D. Chain conveyor

What is the correct answer?

4

Break-even analysis consists of

A. Fixed expenses

B. Variable cost

C. Sales revenue

D. All of these

What is the correct answer?

4

In order that linear programming techniques provide valid results

A. Relations between factors must be linear (positive)

B. Relations between factors must be linear (negative)

C. Either (A) or (B)

D. Only one factor should change at a time, others remaining constant

What is the correct answer?

4

Pick up the correct statement from the following

A. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project in no delayed

B. If the float of an activity is negative, delay in its performance is bound to delay the completion of project

C. If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project

D. All of the above

What is the correct answer?

4

In steel plant the most important system for materials handling is

A. Conveyors

B. Cranes and hoists

C. Trucks

D. Locos

What is the correct answer?

4

The type of layout used for manufacturing steam turbines, is

A. Product layout

B. Process layout

C. Fixed position layout

D. Any one of these

What is the correct answer?

4

Gantt chart gives information about

A. Scheduling and routing

B. Sales

C. Production schedule

D. Machine utilisation

What is the correct answer?

4

Critical path method

A. Helps in ascertaining time schedules

B. Makes better and detailed planning possible

C. Provides a standard method for communicating project plans schedules and to time and cost performance

D. All of the above

What is the correct answer?

4

The technique of value analysis can be applied to

A. Complicated items only

B. Simple items only

C. Crash programmer items only

D. Any item

What is the correct answer?

4

The most popular type of organisation used for Civil Engineering Constructions is

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. Effective organisation

What is the correct answer?

4

Which of the following layouts is suited to job production?

A. Process layout

B. Product layout

C. Fixed position layout

D. Plant layout

What is the correct answer?

4

Acceptance sampling is used in

A. Job production

B. Batch production

C. Mass production

D. All of these

What is the correct answer?

4

Which one of the following chart gives simultaneously information about the progress of work and machine loading?

A. Process chart

B. Machine load chart

C. Man-machine chart

D. Gantt chart

What is the correct answer?

4

In Lincoln plan (one type of group incentive plan), the amount of the profit which an employee receives in addition to the guaranteed basic pay/wages, is based on:

A. A standard rating system

B. A merit rating system

C. A job evaluation system

D. His individual performance

What is the correct answer?

4

In a line organisation

A. Responsibility of each individual is fixed

B. Discipline is strong

C. Quick decisions are taken

D. All of these

What is the correct answer?

4

A big advantage of PERT over Gantt charts is that in the former case

A. Activities and events are clearly shown

B. Early start and late finish of an activity are clearly marked

C. Activity times are clear

D. Interrelationship among activities is clearly shown.

What is the correct answer?

4

Pick up the incorrect statement from the following. A critical ratio scheduling

A. Establishes the relative priorities among various activities on a common basis

B. Determines the status of each activity

C. Adjusts automatically changes in activity progress

D. None of the above

What is the correct answer?

4

Which of the following incentive plans ensures a part of the swing to the worker and rest to the employer?

A. Emerson efficiency plan

B. Taylor plan

C. Halsey premium plan

D. Gilbert plan

What is the correct answer?

4

The value engineering technique in which experts of the same rank assemble for product development is called

A. Delphi

B. Brain storming

C. Morphological analysis

D. Direct expert comparison

What is the correct answer?

4

Break-even analysis can be used for

A. Short run analysis

B. Long run analysis

C. Average of above two run analysis

D. There is no such criterion

What is the correct answer?

4

The most important objective behind plant layout is

A. Overall simplification, safety of integration

B. Economy in space

C. Maximum travel time in plant

D. To provide conveniently located shops

What is the correct answer?

4

PERT has following time estimate

A. One time estimate

B. Two time estimate

C. Three time estimate

D. Four time estimate

What is the correct answer?

4

Merit rating is the method of determining the

A. Relative values of a job

B. Workers performance on a job

C. Worth of a machine

D. Value of overall production

What is the correct answer?

4

Work study is done with the help of

A. Process chart

B. Material handling

C. Stop watch

D. All of the above

What is the correct answer?

4

The process layout is best suited where

A. Specialisation exists

B. Machines are arranged according to sequence of operation

C. Few number of non-standardised units is to be produced

D. Mass production is envisaged

What is the correct answer?

4

The start or completion of task is called

A. An event

B. An activity

C. A duration

D. None of these

What is the correct answer?

4

In a functional organisation

A. Quality of work is better

B. Wastage of material is minimum

C. Specialised knowledge and guidance to individual worker is provided

D. All of the above

What is the correct answer?

4

Father of industrial engineering is

A. Jack Gilbert

B. Gantt

C. Taylor

D. Newton

What is the correct answer?

4

The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as

A. Duration

B. Total float

C. Free float

D. Interfering float

What is the correct answer?

4

For a product layout the material handling equipment must

A. Have full flexibility

B. Employ conveyor belts, trucks, tractors etc.

C. Be a general purpose type

D. Be designed as special purpose for a particular application