Home
Current Affairs January 2024

What is the correct answer?

4

Work study is most useful

A. Where production activities are involved

B. In judging the rating of machines

C. In improving industrial relations

D. In judging the output of a man and improving it

Correct Answer :

A. Where production activities are involved


Related Questions

What is the correct answer?

4

If TL is the largest allowable event occurrence time, total activity slack (s) is equal to

A. Latest start time earliest start time

B. Latest finish time earliest finish time (EFT)

C. TLEFT

D. All of the above

What is the correct answer?

4

Time study is carried out to determine the time required to complete job by

A. A slow worker

B. A fast worker

C. An average worker

D. An apprentice

What is the correct answer?

4

The type of layout used for manufacturing steam turbines, is

A. Product layout

B. Process layout

C. Fixed position layout

D. Any one of these

What is the correct answer?

4

According to MAPI formula, the old machine should be replaced by new one when (CAM = Challenger's Adverse minimum DAM = Defender's Adverse minimum)

A. CAM < DAM

B. CAM > DAM

C. CAM = DAM

D. There is no such criterion

What is the correct answer?

4

The most suitable incentive plan for the maintenance section of an industry will be

A. Piece rate system

B. Group incentive plan

C. Profit sharing plans

D. Simplification

What is the correct answer?

4

An event is indicated on the network by

A. A straight line

B. A number enclosed in a circle or a square

C. A straight line with circles at the ends

D. A dotted line

What is the correct answer?

4

Time study is carried out

A. By finding all the significant informations regarding the job, work place and machine tool etc.

B. By breaking up each operation into small elements which are measurable with the help of the measuring device accurately

C. By observing and recording the time taken by the operator for an operation

D. All of the above

What is the correct answer?

4

An optimum project schedule implies

A. Optimum utilization of men, machines and materials

B. Lowest possible cost and shortest possible time for project

C. Timely execution of project

D. To produce best results under given constraints

What is the correct answer?

4

Direct expenses include

A. Factory expenses

B. Selling expenses

C. Administrative expenses

D. None of these

What is the correct answer?

4

The simplex method is the basic method for

A. Value analysis

B. Operation research

C. Linear programming

D. Model analysis

What is the correct answer?

4

The breakeven point represents

A. The most economical level of operation of any industry

B. The time when unit can run without i loss and profit

C. Time when industry will undergo loss

D. The time when company can make maximum profits

What is the correct answer?

4

A milestone chart

A. Shows the inter dependences of various jobs

B. Depicts the delay of jobs, if any

C. Points outgoing ahead of schedule of jobs, if any

D. None of the above

What is the correct answer?

4

Scheduling gives information about

A. When work should start and how much work should be completed during a certain period

B. When work should complete

C. That how idle time can be minimized

D. Proper utilisation of machines

What is the correct answer?

4

Line organisation is suitable for

A. Sugar industries

B. Oil refining industries

C. Spinning and weaving industries

D. All of these

What is the correct answer?

4

Templates are used for

A. A planning layout

B. Flow of material

C. Advancing a programme in automatic machines

D. Copying complicated profiles

What is the correct answer?

4

Value engineering aims at finding out the

A. Depreciation value of a product

B. Resale value of a product

C. Major function of the item and accomplishing the same at least cost without change in quality

D. Breakeven point when machine requires change

What is the correct answer?

4

The factors to be considered for production scheduling are

A. Component design

B. Route sheet

C. Time standards

D. All of these

What is the correct answer?

4

Earliest finish time can be regarded as

A. Earliest start time + duration of activity

B. Earliest start time duration of activity

C. Latest finish time + duration of activity

D. Latest finish time duration of activity

What is the correct answer?

4

Work study is mainly aimed at

A. Determining the most efficient method of performing a job

B. Establishing the minimum time of completion of a job

C. Developing the standard method and standard time of a job

D. Economising the motions involved on the part of the worker while performing a job

What is the correct answer?

4

Which of the following is independent of sales forecast?

A. Productivity

B. Inventory control

C. Production planning

D. Production control

What is the correct answer?

4

M.T.M. is used to

A. Improve existing methods

B. Establish time standards

C. Develop effective methods in advance of the beginning of production

D. All of the above

What is the correct answer?

4

F. W. Taylor introduced a system of organisation known as

A. Line organisation

B. Functional organisation

C. Line and staff organisation

D. Line, staff and functional organisation

What is the correct answer?

4

Routing

A. Prescribes the sequence of operations to be followed

B. Determines the programme for the operations

C. Is concerned with starting of processes

D. Regulates the progress of job through various processes

What is the correct answer?

4

Which of the following statement is correct?

A. When slack of an activity is zero, it falls only on critical path.

B. CPM technique is useful to minimise the direct and indirect expenses.

C. Critical path of a net work represents the minimum time required for completion of project.

D. All of the above

What is the correct answer?

4

Which of the following plans motivates supervisors by paying a premium on time saved by workers?

A. Halsey plan

B. Rowan plan

C. Haynes plan

D. Emerson's plan

What is the correct answer?

4

O on a PERT/CPM chart represents

A. An ordinary event

B. A significant event representing some milestone

C. An event to be transferred to other network chart

D. Dangling event

What is the correct answer?

4

The type of organisation preferred for a steel industry, is

A. Line organisation

B. Functional organisation

C. Line and staff organisation

D. Line, staff and functional organisation

What is the correct answer?

4

The basic difference between PERT and CPM is that

A. PERT deals with events and CPM with activities

B. Critical path is determined in PERT only

C. Costs are considered on CPM only and not in PERT

D. Guessed times are used in PERT and evaluated times in CPM

What is the correct answer?

4

The work study is done by means of

A. Planning chart

B. Process chart

C. Stop watch

D. Any one of these

What is the correct answer?

4

The technique for establishing and maintaining priorities among the various jobs of any project is known as

A. Event flow scheduling technique

B. Critical ratio scheduling

C. Slotting technique for scheduling

D. Short interval scheduling