Question No : 22
Queueing theory is used for

Inventory problems
Traffic congestion studies
Job-shop scheduling
All of the above

Question No : 23
In a PERT chart

All activities should be numbered
Only important activities should be numbered
Only critical activities are numbered
Only selected activities are numbered

Question No : 24
The first method invented for planning projects was

Bar chart method
Milestone chart
Critical path method (CPM)
Programme evaluation and review technique (PERT)

Question No : 25
A dummy activity

Is artificially introduced
Is represented by a dotted line
Does not require any time
All of the above

Question No : 26
The bonus increases in proportion to the increase in efficiency. This statement applies to

Halsey plan
Gantt plan
Emerson's efficiency plan
Rowan plan

Question No : 27
Which of the following statement is correct?

When slack of an activity is zero, it falls only on critical path.
CPM technique is useful to minimise the direct and indirect expenses.
Critical path of a net work represents the minimum time required for completion of project.
All of the above

Question No : 28
In manufacturing management, the term 'Dispatching' is used to describe

Dispatch of sales order
Dispatch of factory mail
Dispatch of finished product of the user
Dispatch of work orders through shop floor