1. If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be
A. 2.3% and 84.1%
B. 97.7% and 84.1%
C. 97.7 % and 15.9%
D. 15.9% and 97.7%
Answer : A
2. If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is
A. 500 cum
B. 1000 cum
C. 1500 cum
D. 2000 cum
Answer : A
3. Pick up the incorrect statement from the following:
A. An activity of a project is denoted by an arrow on the net work
B. The tail of the arrow indicates the start of the activity
C. The head of the arrow indicates the end of the activity
D. The arrows are drawn to scale from left to right
Answer : D
4. Final technical authority of a project lies with
A. Assistant Engineer
B. Executive Engineer
C. Superintending Engineer
D. Chief Engineer
Answer : D
5. Bar charts are suitable for
A. Minor works
B. Major works
C. Large projects
D. All the Above
Answer : A
6. Frequency distribution curves
A. Having a single lump, are called uninodal curves
B. If symmetrical, are called normal curves
C. If not symmetrical, are called skew curves
D. All the above
Answer : D
7. PERT technique of network analysis is mainly useful for
A. Small projects
B. Large and complex projects
C. Research and development projects
D. Deterministic activities
Answer : C
8. The Overall in-charge of an organisation at the site responsible for the execution of the works, is
A. Executive Engineer
B. Engineer
C. Junior Engineer
D. Assistant Engineer
Answer : B
9. Consider the following activities in a building construction:
1. Concreting of roof slabs
2. Brick-jelly lime concrete terracing
3. Erection of form work for slab
4. Construction of parapet wall in terrace
The correct sequence of these activities is

A. 1, 3, 2, 4
B. 3, 1, 4, 2
C. 3, 1, 2, 4
D. 1, 3, 4, 2
Answer : C
10. Which of the following is a weakness of bar chart?
A. Interdependencies of activities
B. Project progress
C. Uncertainties
D. All of the above
Answer : D
11. An excavator costs Rs. 20,00,000 and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is
A. Rs. 8,43,750
B. Rs. 8,75,000
C. Rs. 10,50,000
D. Rs. 11,56,250
Answer : A
12. Select the incorrect statement.
A. Start float and finish float are always equal.
B. Total float can be either start float or finish float.
C. Start float and finish float need not be equal.
D. Start float and finish float are the differences between activity times and not event times.
Answer : C
13. Which one of the following represents an event?
A. Concrete cured
B. Fixing of door
C. Plastering of walls
D. Selecting sites
Answer : A
14. Free float for any activity is defined as the difference between
A. Its earliest finish time and earliest start time for its successor activity
B. Its latest start time and earliest start time
C. Its latest finish time and earliest start time for its successor activity
D. Its earliest finish time and latest start time for its successor activity
Answer : A
15. If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is
A. (t1 - t2) - t
B. t - (t1 - t2)
C. (t1 + t2) - t
D. t + (t1 - t2)
Answer : A
16. The reduction in project time normally results in
A. Decreasing the direct cost and increasing indirect cost
B. Increasing the direct cost and decreasing the indirect cost
C. Increasing the direct cost and indirect cost both
D. Decreasing the direct cost and indirect cost both
Answer : B
17. CPM is
A. Synthesising in concepts
B. Is built of activities oriented programme
C. Is based on time estimate
D. All the above
Answer : D
18. The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is
A. 3425 kg
B. 5515 kg
C. 4350 kg
D. 2975 kg
Answer : B
19. Slack time refers to
A. An activity
B. An event
C. Both event and activity
D. None of the above
Answer : B
20. Time and progress chart of a construction, is also known as
A. Bar chart
B. Gantt chart
C. Modified Mile stone chart
D. All the above
Answer : D
21. Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions Of these statements
A. Only (i) is correct
B. (i) and (ii) are correct
C. (i) and (iii) are correct
D. (ii) and (iii) are correct
Answer : C
22. If TL is the latest allowable event occurrence time, total activity slack(s), is equal to
A. LST-EST
B. LFT-EFT
C. TL-EFT
D. All the above
Answer : D
23. In resources levelling
A. Total duration of project is reduced
B. Total duration of project is increased
C. Uniform demand of resources is achieved
D. Cost of project is controlled
Answer : C
24. Free float is mainly used to
A. Identify the activities which can be delayed without affecting the total float of preceding activity
B. Identify the activities, which can be delayed without affecting the total float of succeeding activity
C. Establish priorities
D. Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
Answer : B
25. The time which results in the leasi, possible construction cost of an activity, is known as
A. Normal time
B. Slow time
C. Crash time
D. Standard time
Answer : B
26. Pick up the correct statement from the following:
A. Forward pass is used for calculating earliest expected time
B. Backward pass is used for calculating the latest occurrence time
C. Maximum value of earliest expected time is used if there is more than one value of any event
D. All the above
Answer : D
27. Which one of the following is not an excavating and moving type of equipment?
A. Bulldozer
B. Clam shell
C. Scraper
D. Dump truck
Answer : D
28. Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing. Reason R: If the angle of swing is decreased, the cycle time will be decreased. Select the correct answer.
A. Both A and R is true and R is the correct explanation of A
B. Both A and R is true but R is not the correct explanation of A
C. A is true but R is false
D. A is false but R is true
Answer : A
29. The constraints in case of resource smoothening operation would be
A. Resources
B. Project duration time
C. Both resources and project duration time
D. None of the above
Answer : B
30. A CPM family includes
A. CPA (Critical Path Analysis)
B. CPP (Critical Path Plotted)
C. MCE (Minimum Cost Expenditure)
D. All the above
Answer : D
31. Which one of the following represents an activity?
A. Excavation for foundation
B. Curing of concrete
C. Setting of question paper
D. All the above
Answer : D
32. Pick up the correct statement from the following:
A. The difference of latest occurrence time and earliest expected time, is called slack
B. The activities connecting the events having zero slack, lie on the critical path
C. The critical path consumes the maximum time
D. All the above
Answer : D
33. The technique for establishing and maintaining priorities among the various jobs of a project, is known
A. Event flow scheduling technique
B. Critical ratio scheduling
C. Slotting technique for scheduling
D. Short interval scheduling
Answer : B
34. The time corresponding to minimum total project cost is
A. Crash time
B. Normal time
C. Optimistic time
D. Between normal time and crash time
Answer : D
35. The difference between the time avail-to do a job and the time required to do the job, is known as
A. Event
B. Float
C. Duration
D. Constraint
Answer : B
36. Total float for any activity is defined as the difference between
A. Its latest finish time and earliest start time for its successor activity
B. Its latest start time and earliest start time
C. Its latest start time and earliest finish time
D. Its earliest finish time and earliest start time for its successor activity
Answer : B
37. PERT analysis is based on
A. Optimistic time
B. Pessimistic time
C. Most likely time
D. All the above
Answer : D
38. The first method invented for planning projects, was
A. Bar chart method
B. Milestone chart
C. Critical path method (CPM)
D. Programme Evaluation and Review Technique (PERT)
Answer : A
39. An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?
A. Rs. 31050
B. Rs. 34500
C. Rs. 37950
D. Rs. 50000
Answer : A
40. At a work site, statistical quality control of concrete means
A. Measurement of risks to eliminate failures
B. Applying the theory' of probability to sample testing or inspection
C. Reduction in wastage of inspection costs
D. Reduction in costs for the removal of defects
Answer : B
41. Batching refers to
A. Controlling the total quantity at each batch
B. Weighing accurately, the quantity of each material for a job before mixing
C. Controlling the quantity of each material into each batch
D. Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch
Answer : C
42. A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be
A. Rs. 1740
B. Rs. 3480
C. Rs. 5220
D. Rs. 6960
Answer : B
43. The area under the Beta distribution curve is divided into two equal parts by
A. Most likely time
B. Optimistic time
C. Pessimistic time
D. Expected time
Answer : D
44. The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack Of these statements
A. (i), (ii) and (iv) are correct
B. (ii), (iii) and (iv) are correct
C. (i), (iii) and (iv) are correct
D. (i), (ii) and (iii) are correct
Answer : D
45. Which of the following excavators is most suitable for digging under water?
A. Drag line
B. Hoe
C. Clam shell
D. Dipper shovel
Answer : A
46. Residential buildings are treated as
A. Light construction
B. Heavy construction
C. Industrial construction
D. Private construction
Answer : A
47. The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as
A. Event
B. Free float
C. Dummy
D. Constraint
Answer : C
48. Pick up the incorrect statement from the following:
A. The activity is the time consuming part of a project
B. The beginning and end of a job, are called events
C. The activity which consumes maximum time, is called a node
D. Logically and sequentially connected activities and events form a network
Answer : C
49. For completion of a project, the critical path of the network represents
A. Minimum time
B. Maximum time
C. Maximum cost
D. Minimum cost
Answer : A
50. A contractor has two options;
(I): Invest his money in project A or
(II): Invest his money in project B.
If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he

A. Should invest in neither of the two projects
B. Could invest in either of the two projects
C. Should invest in project A
D. Should invest in project B
Answer : A

Sharing is caring