Construction Planning and Management MCQ Solved Paper for SSC GD

Thursday 9th of March 2023

Sharing is caring

1. The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack Of these statements
A. (i), (ii) and (iv) are correct
B. (ii), (iii) and (iv) are correct
C. (i), (iii) and (iv) are correct
D. (i), (ii) and (iii) are correct
Answer : D
2. An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?
A. Rs. 31050
B. Rs. 34500
C. Rs. 37950
D. Rs. 50000
Answer : A
3. Pick up the correct statement from the following:
A. The difference of latest occurrence time and earliest expected time, is called slack
B. The activities connecting the events having zero slack, lie on the critical path
C. The critical path consumes the maximum time
D. All the above
Answer : D
4. The first stage of a construction, is
A. Preparation of estimate
B. Survey of the site
C. Initiation of proposal
D. Preparation of tender
Answer : C
5. The independent float affects only
A. Preceding activities
B. Succeeding activities
C. The particular activity involved
D. None of the above
Answer : C
6. Consider the following activities in a building construction:
1. Concreting of roof slabs
2. Brick-jelly lime concrete terracing
3. Erection of form work for slab
4. Construction of parapet wall in terrace
The correct sequence of these activities is

A. 1, 3, 2, 4
B. 3, 1, 4, 2
C. 3, 1, 2, 4
D. 1, 3, 4, 2
Answer : C
7. Power stations are generally treated as
A. Light construction
B. Heavy construction
C. Industrial construction
D. Electrical construction
Answer : C
8. The reduction in project time normally results in
A. Decreasing the direct cost and increasing indirect cost
B. Increasing the direct cost and decreasing the indirect cost
C. Increasing the direct cost and indirect cost both
D. Decreasing the direct cost and indirect cost both
Answer : B
9. Whenever an activity has zero total float, then
A. Free float of the activity must be zero but independent float need not be zero
B. Independent float must be zero but free float need not be zero
C. Free float and independent float both must be zero
D. Free float and independent float both need not be zero
Answer : C
10. In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
A. Longest duration
B. Highest cost slope
C. Least cost slope
D. Shortest duration
Answer : C
11. The time corresponding to minimum total project cost is
A. Crash time
B. Normal time
C. Optimistic time
D. Between normal time and crash time
Answer : D
12. Batching refers to
A. Controlling the total quantity at each batch
B. Weighing accurately, the quantity of each material for a job before mixing
C. Controlling the quantity of each material into each batch
D. Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch
Answer : C
13. The main principle of an organisation, is
A. Unity of command
B. Effective control at all levels
C. Delegation of authority
D. All the above
Answer : D
14. Mile Stone charts were invented in the year of
A. 1910
B. 1920
C. 1930
D. 1940
Answer : D
15. A dummy activity
A. Is artificially introduced
B. Is represented by a dotted line
C. Does not consume time
D. All the above
Answer : D
16. The final selection of a construction site, is done by
A. Departmental representative or user
B. Local civil authority representative
C. Representative of engineer authority
D. All the above
Answer : D
17. Which of the following earth moving machines has the shortest cycle time?
A. Drag line
B. Hoe
C. Clam shell
D. Dipper shovel
Answer : D
18. Rolling resistance of a wheel depends upon (i) Vehicle load (ii) Grade (iii) Ground conditions Of these statements
A. Only (i) is correct
B. (i) and (ii) are correct
C. (i) and (iii) are correct
D. (ii) and (iii) are correct
Answer : C
19. Critical path method
A. Is an improvement upon bar chart method
B. Provides a realistic approach to daily problems
C. Avoids delays which are very common in bar charts
D. All the above
Answer : D
20. If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be
A. Started 5 days later
B. Completed 5 days later
C. Performed at slower rate in 15 days
D. All the above
Answer : D
21. Earliest finish of an activity is always
A. Greater than earliest event time of the following node
B. Less than earliest event time of the following node
C. Less than or equal to earliest event time of the following node
D. Greater than or equal to earliest event time of the following node
Answer : C
22. Which of the following is not a PERT event?
A. Site investigation started
B. Sessional work completed
C. Bus starts from Jaipur
D. Class is being attended
Answer : D
23. The main advantage of line organisation is:
A. Effective command and control
B. Rigid discipline in the organisation
C. Defined responsibilities at all levels
D. All the above
Answer : D
24. If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be
A. 50 %
B. Less than 50 %
C. More than 50 %
D. 100 %
Answer : C
25. A tractor whose weight is 20 tonnes has a drawbar pull of 2500 kg, when operated on a level road having a rolling resistance of 30 kg per tonne. If this tractor is operated on a level road having a rolling resistance of 40 kg per tonne, then the drawbar pull of the tractor will
A. Reduce by 200 kg
B. Increase by 200 kg
C. Increase by 250 kg
D. Reduce by 250 kg
Answer : A
26. The critical activity has
A. Maximum float
B. Minimum float
C. Zero float
D. None of these
Answer : C
27. Select the incorrect statement.
A. Start float and finish float are always equal.
B. Total float can be either start float or finish float.
C. Start float and finish float need not be equal.
D. Start float and finish float are the differences between activity times and not event times.
Answer : C
28. A four wheel truck or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be
A. 20 kg/tonne
B. 30 kg/tonne
C. 40 kg/tonne
D. 50 kg/tonne
Answer : C
29. Final technical authority of a project lies with
A. Assistant Engineer
B. Executive Engineer
C. Superintending Engineer
D. Chief Engineer
Answer : D
30. Select the correct statement.
A. Activity arrows in a CPM network are drawn to scale
B. The tail of an arrow represents the finish of an activity
C. Arrow bead represents the start of an activity
D. None of the above
Answer : D
31. The first method invented for planning projects, was
A. Bar chart method
B. Milestone chart
C. Critical path method (CPM)
D. Programme Evaluation and Review Technique (PERT)
Answer : A
32. The probability of completion of any activity within its expected time is
A. 50 %
B. 84.1 %
C. 99.9 %
D. 100 %
Answer : A
33. Free float for any activity is defined as the difference between
A. Its earliest finish time and earliest start time for its successor activity
B. Its latest start time and earliest start time
C. Its latest finish time and earliest start time for its successor activity
D. Its earliest finish time and latest start time for its successor activity
Answer : A
34. The salient feature of functional organisation is
A. Strict adherence to specifications
B. Separation of planning and design part
C. Each individual maintains functional efficiency
D. All the above
Answer : D
35. Sensitivity analysis is a study of
A. Comparison of profit and loss
B. Comparison of assets and liabilities
C. Change in output due to change in input
D. Economics of cost and benefits of the project
Answer : C
36. If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
A. (a + m + b)/6
B. (a + 2m + b)/6
C. (a + 4m + b)/6
D. (a + 5m + b)/6
Answer : C
37. If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is
A. (t1 - t2) - t
B. t - (t1 - t2)
C. (t1 + t2) - t
D. t + (t1 - t2)
Answer : A
38. Pick up the correct statement from the following:
A. Earliest expected time is denoted by TE
B. Latest occurrence time is denoted by TL
C. Contractual obligation time is denoted by Ts
D. All the above
Answer : D
39. Completion of an activity on CPM network diagram, is generally known
A. Event
B. Node
C. Connector
D. All the above
Answer : D
40. The Overall in-charge of an organisation at the site responsible for the execution of the works, is
A. Executive Engineer
B. Engineer
C. Junior Engineer
D. Assistant Engineer
Answer : B
41. Construction team means
A. An engineer
B. An architect
C. An owner
D. All the above
Answer : D
42. PERT technique of network analysis is mainly useful for
A. Small projects
B. Large and complex projects
C. Research and development projects
D. Deterministic activities
Answer : C
43. Pick up the correct statement from the following:
A. The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'
B. The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float
C. The difference between total float and free float, is called interfering float
D. All the above
Answer : D
44. If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively
A. 3.5 and 5/6
B. 5 and 25/36
C. 3.5 and 25/36
D. 4 and 5/6
Answer : C
45. Consider the following statements: In the bar chart planning
1. Interdependence of the operations cannot be portrayed.
2. Progress of work can be measured.
3. Spare time of the activities can be determined.
4. Schedule cannot be updated. Of these statements

A. 1, 2 and 3 are correct
B. 1 and 4 are correct
C. 2, 3 and 4 are correct
D. 1, 2 and 4 are correct
Answer : B
46. Pick up the correct statement from the following:
A. CPM analysis is activity oriented
B. PERT analysis is event oriented
C. In CPM, the time is related to cost
D. All the above
Answer : D
47. For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is
A. 1
B. 2
C. 3
D. 4
Answer : A
48. Consider the following features/factors:
1. Projects are of the non-repetitive type
2. Time required need not be known
3. Time required is known precisely
4. Events have been established for planning
5. Emphasis is given to activities of project PERT is preferred for planning because of

A. 1, 2 and 4
B. 3, 4 and 5
C. 1, 3 and 4
D. 1, 2 and 5
Answer : A
49. Updating may result in
A. Change of critical path
B. Decrease of project completion time
C. Increase of project completion time
D. All of the above
Answer : D
50. Total float for any activity is defined as the difference between
A. Its latest finish time and earliest start time for its successor activity
B. Its latest start time and earliest start time
C. Its latest start time and earliest finish time
D. Its earliest finish time and earliest start time for its successor activity
Answer : B