SSC CPO - Construction Planning and Management 1000+ MCQ [Solved] PDF Download

Thursday 9th of March 2023

Sharing is caring

1. The main disadvantage of line organisation, is
A. Rigid structure
B. Extraordinary delay in communications
C. Top level executions over work
D. All the above
Answer : D
2. For completion of a project, the critical path of the network represents
A. Minimum time
B. Maximum time
C. Maximum cost
D. Minimum cost
Answer : A
3. While filling the tender for any work, the contractor considers
A. Site survey
B. Availability of construction materials
C. Availability of labour
D. All the above
Answer : D
4. Total float for any activity is defined as the difference between
A. Its latest finish time and earliest start time for its successor activity
B. Its latest start time and earliest start time
C. Its latest start time and earliest finish time
D. Its earliest finish time and earliest start time for its successor activity
Answer : B
5. Consider the following statements for a power shovel: (i) Output can be increased by reducing the angle of swing for a given depth of cut. (ii) For a given angle of swing, output will be maximum at optimum depth of cut. (iii) Output can be increased by keeping the depth of cut less than optimum depth, (iv) Output can be increased by increasing the size of shovel. Of these statements
A. (ii), (iii) and (iv) are correct
B. (i), (ii) and (iv) are correct
C. (i), (iii) and (iv) are correct
D. (i) and (iv) are correct
Answer : B
6. Which one of the following represents an event?
A. Concrete cured
B. Fixing of door
C. Plastering of walls
D. Selecting sites
Answer : A
7. Pick up the correct statement from the following with regards to C.P.M. network analysis of projects
A. The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
B. The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
C. Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
D. All the above
Answer : D
8. Modular co-ordination of construction means proper
A. Planning
B. Designing
C. Execution
D. All the above
Answer : D
9. Pick up the correct statement from the following:
A. Programme Evaluation and Review Technique, is event oriented
B. Programme Evaluation and Review Technique is not event oriented
C. Critical Path Method is event oriented
D. Critical Path method is event oriented
Answer : A
10. For the execution of a project, a contractor is
A. A person
B. A firm
C. An agency
D. All the above
Answer : D
11. The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as
A. Duration
B. Total float
C. Free float
D. Interfering float
Answer : C
12. The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as
A. Event
B. Free float
C. Dummy
D. Constraint
Answer : C
13. Final technical authority of a project lies with
A. Assistant Engineer
B. Executive Engineer
C. Superintending Engineer
D. Chief Engineer
Answer : D
14. The probability of completion of any activity within its expected time is
A. 50 %
B. 84.1 %
C. 99.9 %
D. 100 %
Answer : A
15. The time corresponding to minimum total project cost is
A. Crash time
B. Normal time
C. Optimistic time
D. Between normal time and crash time
Answer : D
16. A golden rule for the procurement of construction stones, suggests
A. 100% at the site
B. 67% at the site and 33% under procurement
C. 50% at the site and 50% under procurement
D. 33% at the site and 67% under procurement
Answer : B
17. If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be
A. Started 5 days later
B. Completed 5 days later
C. Performed at slower rate in 15 days
D. All the above
Answer : D
18. A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is
A. Rs. 4,75,000
B. Rs. 5,75,000
C. Rs. 6,50,000
D. Rs. 8,50,000
Answer : B
19. Which of the following does not represent an activity?
A. Site located
B. Foundation is being dug
C. The office area is being cleaned
D. The invitations are being sent
Answer : A
20. Critical Path Net Work helps an engineer
A. To concentrate his attention on critical activities
B. To divert the resources from non-critical advanced activities to critical activities
C. To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
D. All the above
Answer : D
21. In PERT analysis, the time estimates of activities and probability of their occurrence follow
A. Normal distribution curve
B. Poisson's distribution curve
C. Beta distribution curve
D. None of the above
Answer : C
22. A dummy activity
A. Is artificially introduced
B. Is represented by a dotted line
C. Does not consume time
D. All the above
Answer : D
23. The time which results in the leasi, possible construction cost of an activity, is known as
A. Normal time
B. Slow time
C. Crash time
D. Standard time
Answer : B
24. PERT analysis is based on
A. Optimistic time
B. Pessimistic time
C. Most likely time
D. All the above
Answer : D
25. Sensitivity analysis is a study of
A. Comparison of profit and loss
B. Comparison of assets and liabilities
C. Change in output due to change in input
D. Economics of cost and benefits of the project
Answer : C
26. The salient feature of functional organisation is
A. Strict adherence to specifications
B. Separation of planning and design part
C. Each individual maintains functional efficiency
D. All the above
Answer : D
27. Which of the following is not a PERT event?
A. Site investigation started
B. Sessional work completed
C. Bus starts from Jaipur
D. Class is being attended
Answer : D
28. Construction team means
A. An engineer
B. An architect
C. An owner
D. All the above
Answer : D
29. Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer.
A. A is correct but R is not correct
B. R is correct but A is not correct
C. Both A and R is correct
D. Both A and R is incorrect
Answer : A
30. Pre-tender stage requires
A. Acquisition of land
B. Selection of site
C. Fmalisation of alignment of work
D. All the above
Answer : D
31. Henry Gantt developed Bar charts for planning and scheduling of projects in
A. 1880
B. 1900
C. 1920
D. 1940
Answer : B
32. Which of the following excavators is most suitable for digging under water?
A. Drag line
B. Hoe
C. Clam shell
D. Dipper shovel
Answer : A
33. A critical ratio scheduling
A. Determines the status of each activity
B. Adjusts automatically changes in activity progress
C. Is a dynamic system
D. None of these
Answer : D
34. Updating may result in
A. Change of critical path
B. Decrease of project completion time
C. Increase of project completion time
D. All of the above
Answer : D
35. The main advantage of line organisation is:
A. Effective command and control
B. Rigid discipline in the organisation
C. Defined responsibilities at all levels
D. All the above
Answer : D
36. An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?
A. Rs. 31050
B. Rs. 34500
C. Rs. 37950
D. Rs. 50000
Answer : A
37. If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be
A. 2.3% and 84.1%
B. 97.7% and 84.1%
C. 97.7 % and 15.9%
D. 15.9% and 97.7%
Answer : A
38. The time with which direct cost does not reduce with the increase in time is known as
A. Crash time
B. Normal time
C. Optimistic time
D. Standard time
Answer : B
39. In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
A. Longest duration
B. Highest cost slope
C. Least cost slope
D. Shortest duration
Answer : C
40. For a given size of bucket, the ideal output of a dragline will be least in
A. Moist loam
B. Sand and gravel
C. Good common earth
D. Wet sticky clay
Answer : D
41. Military organisation is known as
A. Line organisation
B. Line and staff organisation
C. Functional organisation
D. None of these
Answer : A
42. Pick up the correct statement from the following:
A. Forward pass is used for calculating earliest expected time
B. Backward pass is used for calculating the latest occurrence time
C. Maximum value of earliest expected time is used if there is more than one value of any event
D. All the above
Answer : D
43. A CPM family includes
A. CPA (Critical Path Analysis)
B. CPP (Critical Path Plotted)
C. MCE (Minimum Cost Expenditure)
D. All the above
Answer : D
44. Free float for any activity is defined as the difference between
A. Its earliest finish time and earliest start time for its successor activity
B. Its latest start time and earliest start time
C. Its latest finish time and earliest start time for its successor activity
D. Its earliest finish time and latest start time for its successor activity
Answer : A
45. Sinking fund is
A. The fund for rebuilding a structure when its economic life is over
B. Raised to meet maintenance costs
C. The total sum to be paid to the municipal authorities by the tenants
D. A part of the money kept in reserve for providing additional structures and structural modifications
Answer : A
46. Which one of the following represents an activity?
A. Excavation for foundation
B. Curing of concrete
C. Setting of question paper
D. All the above
Answer : D
47. A Milestone chart
A. Shows the interdependencies of various jobs
B. Depicts the delay of jobs, if any
C. Points outgoing ahead of schedule of jobs, if any
D. None of these
Answer : D
48. An event is indicated on the network by a number enclosed in
A. A circle
B. A square
C. A triangle
D. All the above
Answer : D
49. A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be
A. 3.7 years
B. 4.23 years
C. 5 years
D. 7.87 years
Answer : B
50. If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be
A. 50 %
B. Less than 50 %
C. More than 50 %
D. 100 %
Answer : C