You are asked to construct a massive dam, the type of cement you will use, is

A. Ordinary Portland cement

B. Rapid hardening cement

C. Low heat cement

D. Blast furnace slag cement

Correct Answer :

C. Low heat cement


Related Questions

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. In properly graded aggregates, bulk density is more

B. In single size aggregates, bulk density is least

C. In single size aggregates, bulk density is maximum

D. None of these

What is the correct answer?

4

The strength of concrete after one year as compared to 28 days strength is about

A. 10 to 15% more

B. 15 to 20% more

C. 20 to 25% more

D. 25 to 50% more

What is the correct answer?

4

The shuttering of a hall measuring 4 m × 5 m, can be removed after

A. 5 days

B. 7 days

C. 10 days

D. 14 days

What is the correct answer?

4

If fineness modulus of sand is 2.5, it is graded as

A. Very fine sand

B. Fine sand

C. Medium sand

D. Coarse sand

What is the correct answer?

4

The type of aggregates of same nominal size, which contain less voids when compacted, are

A. Rounded spherical

B. Irregular

C. Flaky

D. None of these

What is the correct answer?

4

For ensuring quality of concrete, use

A. Single sized aggregates

B. Two sized aggregate

C. Graded aggregates

D. Coarse aggregates

What is the correct answer?

4

Higher workability of concrete is required if the structure is

A. Made with cement concrete

B. Thick and reinforced

C. Thin and heavily reinforced

D. Thick and heavily reinforced

What is the correct answer?

4

The increased cohesiveness of concrete, makes it

A. Less liable to segregation

B. More liable to segregation

C. More liable to bleeding

D. More liable for surface scaling in frosty weather

What is the correct answer?

4

Grading of sand causes great variation in

A. Workability of concrete

B. Strength of concrete

C. Durability of concrete

D. All the above

What is the correct answer?

4

The factor which affects workability, is

A. Water content and its temperature

B. Shape and size of the aggregates

C. Air entraining agents

D. All the above

What is the correct answer?

4

Construction joints are generally provided in concrete

A. Roads

B. Retaining walls

C. Lining of canals

D. All the above

What is the correct answer?

4

When shear stress exceeds the permissible limit in a slab, then it is reduced by

A. Increasing the depth

B. Providing shear reinforcement

C. Using high strength steel

D. Using thinner bars but more in number

What is the correct answer?

4

The process of mixing, transporting, placing and compacting concrete using Ordinary Port land Cement should not take more than

A. 30 minutes

B. 40 minutes

C. 60 minutes

D. 90 minutes

What is the correct answer?

4

For the construction of thin R.C.C. structures, the type of cement to be avoided, is

A. Ordinary Portland cement

B. Rapid hardening cement

C. Low heat cement

D. Blast furnace slag cement

What is the correct answer?

4

Shrinkage of concrete depends upon
(i) Humidity of atmosphere
(ii) Passage of time
(iii) Stress The correct answer is

A. (i) and (ii)

B. (ii) and (iii)

C. Only (iii)

D. All (i), (ii) and (iii)

What is the correct answer?

4

Percentage of pozzolanic material containing clay upto 80% used for the manufacture of pozzolana cement, is

A. 30 %

B. 40 %

C. 50 %

D. 60 %

What is the correct answer?

4

Strength of concrete increases with

A. Increase in water-cement ratio

B. Increase in fineness of cement

C. Decrease in curing time

D. Decrease in size of aggregate

What is the correct answer?

4

Pick up the incorrect statement from the following. For performing compressive strength test of cement

A. Cement and standard sand mortar are used in the ratio of 1 : 3

B. Water is added at the rate of (P/4) + 3.0 percentage of water where P is the percentage of water for standard consistency

C. A cube mould of 10 cm × 10 cm × 10 cm is used

D. The prepared moulds are kept in a atmosphere of 50% relative humidity

What is the correct answer?

4

In counterfort type retaining walls (i) The vertical slab is designed as a continuous slab (ii) The heel slab is designed as a continuous slab (iii) The vertical slab is designed as a cantilever (iv) The heel slab is designed as a cantilever The correct answer is

A. (i) and (ii)

B. (i)and(iv)

C. (ii) and (iii)

D. (iii) and (iv)

What is the correct answer?

4

M10 grade of concrete approximates

A. 1 : 3 : 6 mix

B. 1 : 1 : 2 mix

C. 1 : 2 : 4 mix

D. 1 : 1.5 : 3 mix

What is the correct answer?

4

The minimum diameter of longitudinal bars in a column is

A. 6 mm

B. 8 mm

C. 12 mm

D. 16 mm

What is the correct answer?

4

To prevent segregation, the maximum height for placing concrete, is

A. 100 cm

B. 125 cm

C. 150 cm

D. 200 cm

What is the correct answer?

4

Assertion A : The load factor for live load is greater than that for dead load. Reason R : The live loads are more uncertain than dead loads. Select your answer based on the coding system given below:

A. Both A and R is true and R is the correct explanation of A

B. Both A and R is true but R is not the correct explanation of A

C. A is true but R is false

D. A is false but R is true

What is the correct answer?

4

The most commonly used admixture which prolongs the setting and hardening time is

A. Gypsum

B. Calcium chloride

C. Sodium silicate

D. All of the above

What is the correct answer?

4

If the effective working time is 7 hours and per batch time of concrete is 3 minutes, the output of a concrete mixer of 150 litre capacity, is

A. 15,900 litres

B. 16,900 litres

C. 17,900 litres

D. 18,900 litres

What is the correct answer?

4

Modulus of rupture of concrete is a measure of

A. Flexural tensile strength

B. Direct tensile strength

C. Compressive strength

D. Split tensile strength

What is the correct answer?

4

The diameter of ties in a column should be

A. More than or equal to one fourth of diameter of main bar

B. More than or equal to 5 mm

C. More than 5 mm but less than one-fourth of diameter of main bar

D. More than 5 mm and also more than one-fourth of diameter of main bar

What is the correct answer?

4

Separation of water or water sand cement from a freshly concrete, is known

A. Bleeding

B. Creeping

C. Segregation

D. Flooding

What is the correct answer?

4

For a cantilever of effective depth of 0.5 m, the maximum span to satisfy vertical deflection limit is

A. 3.5 m

B. 4 m

C. 4.5 m

D. 5 m

What is the correct answer?

4

If 20 kg of coarse aggregate is sieved through 80 mm, 40 mm, 20 mm, 10 mm, 4.75 mm, 2.36 mm, 1.18 mm, 600 micron, 300 micron and 150 micron standard sieves and the weights retained are 0 kg, 2 kg, 8 kg, 6 kg, 4 kg respectively, the fineness modulus of the aggregate, is

A. 7.30

B. 7.35

C. 7.40

D. 7.45