Question No : 57
Minimum width of landing should be

Equal to width of stairs
Half the width of stairs
Twice the width of stairs
One fourth the width of stairs

Question No : 58
The Auger boring method is not suitable for

Very hard soil
Cemented soil
Vary soft soil
All the above

Question No : 59
Pick up the commonly adopted geophysical method in civil engineering from the following:

The seismic method
Electrical resistivity method
Gravitational method
Both (a) and (b) of the above

Question No : 60
Depth or height of the arch is the

Perpendicular distance between intrados and extrados
Vertical distance between springing line and intrados
Perpendicular distance between springing line and extrados
None of the above

Question No : 61
The form Work including the props can be removed from beams, only after

3 day
7 days
14 days
21 days

Question No : 62
An arch may fail due to

Uneven settlement of abutments
Sliding of voussoirs
Crushing of the material
All the above

Question No : 63
In grillage foundations a minimum 15 cm cover is provided on

Upper flange of top tier
Lower beam of lower tier
Ends of external beams
None to these