An arch may fail due to

A. Uneven settlement of abutments

B. Sliding of voussoirs

C. Crushing of the material

D. All the above

Correct Answer :

D. All the above


Related Questions

What is the correct answer?

4

The ceiling height of a building is

A. Between ceiling and ground level

B. Between ceiling and floor level

C. Upto roof above ground level

D. Upto ceiling from the ground level

What is the correct answer?

4

For brick construction, the lime-sand mortar, is

A. 1 : 1

B. 1 : 2

C. 1 : 3

D. 1 : 4

What is the correct answer?

4

Pick up the correct statement from the following:

A. Sand consists of coarse particles of silica formed due to the disintegration of rocks

B. The grains of sand are not affected by frost

C. Sand beds are permeable and do not allow water to rise up between pores due to capillary action

D. All the above

What is the correct answer?

4

The form work from the slabs excluding props, can be removed only after

A. 1 day

B. 4 days

C. 7 days

D. 14 days

What is the correct answer?

4

Stability of an existing structure may be disturbed by

A. Rising of water table

B. Vibrations caused by traffic movements

C. Mining in the neighbourhood

D. All the above

What is the correct answer?

4

Which one of the following factors is considered for the orientation of buildings?

A. The direction of the prevailing winds in the area

B. The exposure of the walls and roof of the buildings to the rays of sun

C. The extent up to which the sunrays penetrate with the verandah

D. All the above

What is the correct answer?

4

The arrangement made to support an unsafe structure temporarily, is known as

A. Shoring

B. Scaffolding

C. Underpinning

D. Jacking

What is the correct answer?

4

The size of a floor tile commonly used, is

A. 15 cm × 15 cm × 1.8 cm

B. 20 cm × 20 cm × 2 cm

C. 22.5 × 22.5 cm × 2.2 cm

D. All the above

What is the correct answer?

4

Higher pitch of the roof
(i) Results in stronger roof
(ii) Results in weaker roof
(iii) Requires more covering material
(iv) Requires less covering material
The correct answer is

A. (i) and (iii)

B. (i) and (iv)

C. (ii) and (iii)

D. (ii) and (iv)

What is the correct answer?

4

The function of king post in a king post roof truss is

A. To support the frame work of the roof

B. To receive the ends of principal rafter

C. To prevent the walls from spreading outward

D. To prevent the tie beam from sagging at its centre

What is the correct answer?

4

For constructing a terrazzo floor, Pick up the incorrect statement from the following:

A. A base course is prepared as in cement concrete flooring

B. A 32 mm thick layer of cement concrete (1 : 2 : 4) is laid on the base course and the surface is made smooth by trowelling

C. Glass strips are driven into the layer according to the pattern required

D. After final grinding is over, oxalic acid mixed with water is spread over and rubbed hard with soft material

What is the correct answer?

4

The piece of a brick cut along the centre of width in such a way that its length is equal to that of full brick, is called

A. Half brick

B. Queen closer

C. King closer

D. Bevelled closer

What is the correct answer?

4

The type of joint commonly used at the junction of a principal rafter and tie beam in timber trusses is

A. Mortise and tenon joint

B. Oblique mortise and tenon joint

C. Butt joint

D. Mitred joint

What is the correct answer?

4

Cast iron piles

A. Are suitable for works under sea water

B. Resist shocks or vibrations

C. Are suitable for use as batter piles

D. Are useful for heavy vertical loads

What is the correct answer?

4

Which one of the following activities is not correct as applicable to brick corbels?

A. The maximum projection of the corbel should not be more than the thickness of the wall

B. The maximum projection of each corbel course should be limited to a quarter brick at a time

C. The discontinuous corbels are used to carry heavy concentrated loads

D. Stretcher bond is generally used for the construction of brick corbel

What is the correct answer?

4

Depth or height of the arch is the

A. Perpendicular distance between intrados and extrados

B. Vertical distance between springing line and intrados

C. Perpendicular distance between springing line and extrados

D. None of the above

What is the correct answer?

4

In verandah floors outward slope is

A. 1 in 40

B. 1 in 50

C. 1 in 60

D. 1 in 70

What is the correct answer?

4

The range of spread from the wall base to outer edge of a brick work foundation does not exceed

A. 1/2 horizontal to 1 vertical

B. 2/3 horizontal to 1 vertical

C. 1 horizontal to 1 vertical

D. 2 horizontals to 1 vertical

What is the correct answer?

4

In grillage foundations, distance between flanges of grillage beams, is kept

A. 40 cm

B. Equal to flange width

C. Twice the flange width

D. Maximum of (a), (b) and (c)

What is the correct answer?

4

The Auger boring method is not suitable for

A. Very hard soil

B. Cemented soil

C. Vary soft soil

D. All the above

What is the correct answer?

4

In which of the following pairs both trees yield soft wood?

A. Deodar and Shishum

B. Chir and sal

C. Sal and teak

D. Chir and deodar

What is the correct answer?

4

The type of roof suitable in plains where rainfall is meagre and temperature is high is

A. Pitched and sloping roof

B. Flat roof

C. Shell roof

D. None of the above

What is the correct answer?

4

The number of steps in a flight generally should not be less than

A. 2

B. 3

C. 5

D. No limit

What is the correct answer?

4

Pick up the correct statements from the following:

A. Cracks appear on the plastered surface in the form of hair cracks

B. In brick work, the efflorescence is removed by applying a solution of zinc sulphate and water

C. Excessive thermal variations in the backing or plaster causes the plaster to fall

D. All the above

What is the correct answer?

4

Rotary drilling is the fastest method in case of

A. Rocky soils

B. Clay soils

C. Sandy soil

D. All of these

What is the correct answer?

4

Pick up the correct statement from the following:

A. The pile driven in sand is called sand pile

B. The drilled hole filled with sand is called sand pile

C. The sand piles are used for bearing purposes

D. None of these

What is the correct answer?

4

Pick up the correct statement from the following:

A. Louvered door is generally provided in bath rooms

B. Flush door is generally provided in dining room

C. Revolving door is generally provided in cinema halls

D. Sliding door is generally provided in show rooms

What is the correct answer?

4

Pick up the correct statement from the following:

A. D.P.C. should be continuous

B. D.P.C. should be of good impervious material

C. D.P.C. may be horizontal or vertical

D. All the above

What is the correct answer?

4

The process of making the back ground rough, before plastering, is

A. Dubbing

B. Hacking

C. Blistering

D. Peeling

What is the correct answer?

4

Bearing capacity of soils cannot be improved by

A. Draining sub-soil water

B. Ramming crushed stone in soil

C. Driving sand piles

D. Watering surface of soil