3 day
7 days
14 days
21 days
C. 14 days
Ground level and springing line
Crown and springing line
Crown and ground level
Intrados and extrados
10 mm
20 mm
30 mm
40 mm
Purlin
Cleat
Batten
Strut
One course of headers to three or five course of stretchers
Queen closer in provided in each heading course
The middle course of stretchers is started with a header to give proper vertical joints
All the above
Strength
Workability
Stability of structure
All the above
The function of foundation is to distribute the load of super structure over a large bearing area
No timbering is required for shallow trenches
Shallow foundations can be constructed on made-up soil
Black cotton soil is very good for foundation bed
Q = Wh/6 (S + 2.5)
Q = Wh/2.5 (S + 6)
Q = (W × 6)/h (S + 2.5)
Q = (W × 2.5)/6 (S + h)
Compressible
Water logged
Made up
All the above
Stone steps
Built up steps
Spandril steps
None of these
Lack of ventilation
Alternate wet and dry conditions
Complete submergence in water
None of the above
2 metres
2.5 metres
3 metres
None of the above
wh × [(1 - sin φ)/(1 + sin φ)]
(wh/2) × [(1 - sin φ)/(1 + sin φ)]
wh × √[(1 - sin φ)/(1 + sin φ)]
wh × √[(1 + sin φ)/(1 - sin φ)]
Trowelling
Laying
Grouting
Placing
H-pile
Screw pile
Disc pile
Pipe pile
Perpendicular distance between intrados and extrados
Vertical distance between springing line and intrados
Perpendicular distance between springing line and extrados
None of the above
Reverberation
Echo
Intensity of sound
Interference
Two curved arches
Gothic arches
Ogee arches
Drop gothic arches
Pudlo
Impermo
Snowcem
All of these
Simplex pile
Vibro pile
Raymond pile
Franki pile
Scaffolding
Dead shore
Raking shore
Under pinning
Are cohesionless aggregates
Vary in size between 2 to 20 mm
Never swell when they come into contact with water
All the above
Deodar and Shishum
Chir and sal
Sal and teak
Chir and deodar
The roof slabs of multi-storeyed buildings are constructed monolithically to carry the various floor loads
The beams of multi-storeyed buildings rest on girders and are the main load transferring members to the columns
The slab is spanned across the secondary beams provided between the main beams
All of these
Dormer window
Sky light window
Lantern window
Louvered window
Retaining wall
Breast wall
Buttress
Parapet wall
Topping
Bedding
Screeding
None of these
Hip
Gable
Ridge
Eaves
5 cm
10 cm
15 cm
20 cm
Random rubble masonry
Coursed rubble masonry
Dry rubble masonry
Ashlar masonry
In a king post truss, principal rafter and tie beams are jointed together with a bridle joint
Joint between the principal rafter and the king post is made by making tenon and mortise respectively
Joint between strut and king post, is generally of mortise and tenon type
All the above