Question No : 8
For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is

1
2
3
4

Question No : 9
The basic action involved in sheep foot rolling is

Kneading
Pressing
Tamping
Vibration

Question No : 10
An earth moving equipment costs Rs. 5,00,000 and has an estimated life of 10 years and a salvage value of Rs. 50,000. What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069?

Rs. 31050
Rs. 34500
Rs. 37950
Rs. 50000

Question No : 11
Select the incorrect statement.

A critical path always begins at the very first event.
A critical path always terminates at the last event.
Critical activities control the project duration.
Critical activity is the one for which free float is zero.

Question No : 12
Free float for any activity is defined as the difference between

Its earliest finish time and earliest start time for its successor activity
Its latest start time and earliest start time
Its latest finish time and earliest start time for its successor activity
Its earliest finish time and latest start time for its successor activity

Question No : 13
The constraints in case of resource smoothening operation would be

Resources
Project duration time
Both resources and project duration time
None of the above

Question No : 14
The process of incorporating changes and rescheduling or replanning is called

Resource levelling
Resource smoothening
Updating
Critical path scheduling