Resources
Project duration time
Both resources and project duration time
None of the above
B. Project duration time
Yes, because of heavier overheads and handling cost
Yes, because of the very high order of quality control for the factory made components
No, because of repetitive manufacture of a number of elements
No, because of savings in site labour
Number of operations
Output of labour
Output of machinery
All the above
Concrete
Loose sand
Asphalt
Firm earth
Any project
Major projects
Minor projects
All the above
Reduce by 200 kg
Increase by 200 kg
Increase by 250 kg
Reduce by 250 kg
Resource levelling
Resource smoothening
Updating
Critical path scheduling
Duration
Total float
Free float
Interfering float
Preparation of specifications
Preparation of estimates
Initiating the procurement action of resources
All the above
Event
Free float
Dummy
Constraint
EF = ES + D
LS = LF - D
LF = LS + D
All the above
Activity of an excavation of a footing
Activity of an excavation which starts at event No. 1 and ends at even No. 2
Activity of excavation which takes 8 units of time
None of these
On all the activities
On all the activities lying on the critical path
Only on activities lying on the original critical path and having flatter cost slopes
On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope
Total float and free float
Total float and independent float
Free float and independent float
None of the above
Resources
Project duration time
Both resources and project duration time
None of the above
Event
Dummy
Duration
Float
Light construction
Heavy construction
Industrial construction
None of these
The difference of latest occurrence time and earliest expected time, is called slack
The activities connecting the events having zero slack, lie on the critical path
The critical path consumes the maximum time
All the above
Maximum float
Minimum float
Zero float
None of these
50 %
Less than 50 %
More than 50 %
100 %
1, 2, 4, 3, 5
1, 3, 2, 4, 5
1, 2, 3, 4, 5
1, 3, 4, 2, 5
Is an improvement upon bar chart method
Provides a realistic approach to daily problems
Avoids delays which are very common in bar charts
All the above
Shows the interdependencies of various jobs
Depicts the delay of jobs, if any
Points outgoing ahead of schedule of jobs, if any
None of these
(i) and (iii) are correct
(i) and (iv) are correct
(ii) and (iii) are correct
(ii) and (iv) are correct
4 days
6 days
10 days
16 days
CPA (Critical Path Analysis)
CPP (Critical Path Plotted)
MCE (Minimum Cost Expenditure)
All the above
Digging of foundation started
Digging of foundation completed
Laying of concrete started
All the above
Is artificially introduced
Is represented by a dotted line
Does not consume time
All the above
Acquisition of land
Selection of site
Fmalisation of alignment of work
All the above
A project is divided into various activities
Required time for each activity is established
Net work is drawn by connecting the activities and the events
All the above
Bar chart method
Milestone chart
Critical path method (CPM)
Programme Evaluation and Review Technique (PERT)