A critical path always begins at the very first event.
A critical path always terminates at the last event.
Critical activities control the project duration.
Critical activity is the one for which free float is zero.
D. Critical activity is the one for which free float is zero.
Number of operations
Output of labour
Output of machinery
All the above
Excavation for foundation
Curing of concrete
Setting of question paper
All the above
The difference of latest occurrence time and earliest expected time, is called slack
The activities connecting the events having zero slack, lie on the critical path
The critical path consumes the maximum time
All the above
1
2
3
4
1, 3 and 4 are correct
2, 3 and 4 are correct
1, 2 and 3 are correct
1, 2 and 4 are correct
Concrete
Loose sand
Asphalt
Firm earth
Determines the status of each activity
Adjusts automatically changes in activity progress
Is a dynamic system
None of these
Rigid structure
Extraordinary delay in communications
Top level executions over work
All the above
On commencement of work at site for payment of loan taken by him
For the purchase of construction materials
For the payment of advances to labour and other staff
For all activities required to start the work at site on finalization of the contract document
Controlling the total quantity at each batch
Weighing accurately, the quantity of each material for a job before mixing
Controlling the quantity of each material into each batch
Adjusting the water to be added in each batch according to the moisture content of the materials being mixed in the batch
Rs. 8,800
Rs. 7,600
Rs. 6,400
Rs. 5,000
Cheapest critical activity
Cheapest noncritical activity
Costliest critical activity
Costliest noncritical activity
Optimistic time estimate refers to activities
Pessimistic time estimate refers to activities
Most likely time estimate refers to activities
All the above
Light construction
Heavy construction
Industrial construction
None of these
The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
All the above
20
25
35
15
Resources
Project duration time
Both resources and project duration time
None of the above
Comparison of profit and loss
Comparison of assets and liabilities
Change in output due to change in input
Economics of cost and benefits of the project
10000 kg
12500 kg
22500 kg
5000 kg
Greater than earliest event time of the following node
Less than earliest event time of the following node
Less than or equal to earliest event time of the following node
Greater than or equal to earliest event time of the following node
Event
Node
Connector
All the above
Change of critical path
Decrease of project completion time
Increase of project completion time
All of the above
A circle
A square
A triangle
All the above
Interdependencies of activities
Project progress
Uncertainties
All of the above
2.3% and 84.1%
97.7% and 84.1%
97.7 % and 15.9%
15.9% and 97.7%
An activity of a project is denoted by an arrow on the net work
The tail of the arrow indicates the start of the activity
The head of the arrow indicates the end of the activity
The arrows are drawn to scale from left to right
Crash time
Normal time
Optimistic time
Between normal time and crash time
Kneading
Pressing
Tamping
Vibration
Rs. 1740
Rs. 3480
Rs. 5220
Rs. 6960
Forward pass is used for calculating earliest expected time
Backward pass is used for calculating the latest occurrence time
Maximum value of earliest expected time is used if there is more than one value of any event
All the above