Construction Planning and Management MCQ Question with Answer

Construction Planning and Management MCQ with detailed explanation for interview, entrance and competitive exams. Explanation are given for understanding.

Download Construction Planning and Management MCQ Question Answer PDF

Question No : 22
Critical Path Net Work helps an engineer

To concentrate his attention on critical activities
To divert the resources from non-critical advanced activities to critical activities
To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
All the above

Question No : 23
Select the incorrect statement.

Start float and finish float are always equal.
Total float can be either start float or finish float.
Start float and finish float need not be equal.
Start float and finish float are the differences between activity times and not event times.

Question No : 24
Pick up the incorrect statement from the following:

The various functions under each activity, are shown by one bar on Bar Charts
Bar chart establishes the interdependency of one event on another
Only approximate percentage of the completed work is reported
None of these

Question No : 25
Pick up the correct statement from the following:

CPM analysis is activity oriented
PERT analysis is event oriented
In CPM, the time is related to cost
All the above

Question No : 26
A construction schedule is prepared after collecting

Number of operations
Output of labour
Output of machinery
All the above

Question No : 27
Consider the following statements: In the bar chart planning
1. Interdependence of the operations cannot be portrayed.
2. Progress of work can be measured.
3. Spare time of the activities can be determined.
4. Schedule cannot be updated. Of these statements

1, 2 and 3 are correct
1 and 4 are correct
2, 3 and 4 are correct
1, 2 and 4 are correct

Question No : 28
Pick up the correct statement from the following:

The difference of latest occurrence time and earliest expected time, is called slack
The activities connecting the events having zero slack, lie on the critical path
The critical path consumes the maximum time
All the above