Question No : 22
Critical Path Net Work helps an engineer
Question No : 23
Select the incorrect statement.
Question No : 24
Pick up the incorrect statement from the following:
Question No : 25
Pick up the correct statement from the following:
Question No : 26
A construction schedule is prepared after collecting
Question No : 27
Consider the following statements: In the bar chart planning
1. Interdependence of the operations cannot be portrayed.
2. Progress of work can be measured.
3. Spare time of the activities can be determined.
4. Schedule cannot be updated. Of these statements
Question No : 28
Pick up the correct statement from the following: