Home
Current Affairs January 2024

What is the correct answer?

4

Too wet concrete may cause

A. Weakness of concrete

B. Excessive laitance

C. Segregation

D. All the above

Correct Answer :

D. All the above


Related Questions

What is the correct answer?

4

The maximum value of hoop compression in a dome is given by

A. wR / 4d

B. wR/2d

C. wR/d

D. 2wR/d Where, w = load per unit area of surface of dome R = radius of curvature d = thickness of dome

What is the correct answer?

4

During erection, the pile of length l is supported by a crane at a distance of

A. 0.207 l

B. 0.293 l

C. 0.707 l

D. 0.793 l From the driving end of pile which rests on the ground

What is the correct answer?

4

Pick up the correct statement from the following:

A. Segregation is necessary for a workable concrete

B. Consistency does not affect the workability of concrete

C. If the concrete mix is dry, the slump is maximum

D. None of these

What is the correct answer?

4

Horizontal construction joints in concrete walls are generally provided at

A. Soffit level

B. Window sill level

C. Floor level

D. All the above

What is the correct answer?

4

I.S. Sieve Nos. 10 mm and 4.75 mm are generally used for grading of

A. Coarse aggregates

B. Fine aggregates

C. Neither (a) nor (b)

D. Both (a) and (b)

What is the correct answer?

4

The diameter of ties in a column should be

A. More than or equal to one fourth of diameter of main bar

B. More than or equal to 5 mm

C. More than 5 mm but less than one-fourth of diameter of main bar

D. More than 5 mm and also more than one-fourth of diameter of main bar

What is the correct answer?

4

The specifications of a cement bag for storage, are

A. Weight 50 kg

B. Height 18 cm

C. Plan area 3000 sq. cm

D. All the above

What is the correct answer?

4

Workability improved by adding

A. Fly ash

B. Hydrated lime

C. Calcium chloride

D. All the above

What is the correct answer?

4

Pre-stress loss due to friction occurs

A. Only in post-tensioned beams

B. Only in pre-tensioned beams

C. In both post-tensioned and pre-tensioned beams

D. None of the above

What is the correct answer?

4

Select the incorrect statement

A. Lean mixes bleed more as compared to rich ones.

B. Bleeding can be minimized by adding pozzolana finer aggregate

C. Bleeding can be increased by addition 'of calcium chloride

D. None of the above

What is the correct answer?

4

In a counterfort retaining wall, the main reinforcement is provided on the (i) Bottom face in front counterfort (ii) Inclined face in front counterfort (iii) Bottom face in back counterfort (iv) Inclined face in back counterfort The correct answer is

A. (i) and (ii),

B. (ii) and (iii)

C. (i) and (iv)

D. (iii) and (iv)

What is the correct answer?

4

Which of the following has high tensile strength?

A. Plain hot rolled wires

B. Cold drawn wires

C. Heat treated rolled wires

D. All have same tensile strength

What is the correct answer?

4

For preparing ordinary concrete, the quantity of water used, is

A. 5% by weight of aggregates plus 20% of weight of cement

B. 10% by weight of aggregates plus 10% of weight of cement

C. 5% by weight of aggregates plus 30% of weight of cement

D. 30% by weight of aggregates plus 10% of weight of cement

What is the correct answer?

4

The depth of footing for an isolated column is governed by (i) Maximum bending moment (ii) Shear force (iii) Punching shear The correct answer is

A. Only (i)

B. (i) and (ii)

C. (i) and (iii)

D. All (i), (ii) and (iii)

What is the correct answer?

4

For batching 1:3:6 concrete mix by volume, the ingredients required per bag of 50 kg cement, are:

A. 70 litres of sand and 120 litres of aggregates

B. 70 kg of sand and 140 litres of aggregates

C. 105 litres of sand and 140 litres of aggregates

D. 105 litres of sand and 210 litres of aggregates

What is the correct answer?

4

The grade of concrete M 150 means that compressive strength of a 15 cm cube after 28 days, is

A. 100 kg/cm2

B. 150 kg/cm2

C. 200 kg/cm2

D. 250 kg/cm2

What is the correct answer?

4

Pozzolana cement is used with confidence for construction of

A. Dams

B. Massive foundations

C. R.C.C. structures

D. All the above

What is the correct answer?

4

The commonly used material in the manufacture of cement is

A. Sand stone

B. Slate

C. Lime stone

D. Graphite

What is the correct answer?

4

The main reason for providing number of reinforcing bars at a support in a simply supported beam is to resist in that zone

A. Compressive stress

B. Shear stress

C. Bond stress

D. Tensile stress

What is the correct answer?

4

The property of fresh concrete, in which the water in the mix tends to rise to the surface while placing and compacting, is called

A. Segregation

B. Bleeding

C. Bulking

D. Creep

What is the correct answer?

4

The most commonly used admixture which prolongs the setting and hardening time is

A. Gypsum

B. Calcium chloride

C. Sodium silicate

D. All of the above

What is the correct answer?

4

Pick up the correct statement from the following:

A. The free water is the amount of water added while mixing and the amount of water held on the surface of the aggregates prior to mixing

B. The total water is the free water and the amount actually absorbed by the aggregates

C. Neither (a) nor (b)

D. Both (a) and (b)

What is the correct answer?

4

For a concrete mix 1:3:6 and water cement ratio 0.6 both by weight, the quantity of water required per bag, is

A. 10 kg

B. 12 kg

C. 14 kg

D. 16 kg

What is the correct answer?

4

Specified compressive strength of concrete is obtained from cube tests at the end of

A. 3 days

B. 7 days

C. 21 days

D. 28 days

What is the correct answer?

4

According to ISI recommendations, the maximum depth of stress block for balanced section of a beam of effective depth d is

A. 0.43 d

B. 0.55 d

C. 0.68 d

D. 0.85 d

What is the correct answer?

4

The risk of segregation is more for

A. Wetter mix

B. Larger proportion of maximum size aggregate

C. Coarser grading

D. All the above

What is the correct answer?

4

The compressive strength of 100 mm cube as compared to 150 mm cube is always

A. Less

B. More

C. Equal

D. None of the above

What is the correct answer?

4

Pick up the incorrect statement from the following. While performing preliminary test on concrete

A. Proportions of the material and water should be the same as to be used at the work site

B. Cement should be mixed by hand in order to maintain uniformity

C. Concrete mix should be stored in air-tight containers

D. Concrete ingredients should be kept at a temperature of 37° ± 2°C

What is the correct answer?

4

For quality control of Portland cement, the test essentially done is

A. Setting time

B. Tensile strength

C. Consistency

D. All the above

What is the correct answer?

4

1% of voids in a concrete mix would reduce its strength by about

A. 5 %

B. 10 %

C. 15 %

D. 20 %