Home
Current Affairs January 2024

What is the correct answer?

4

The maximum value of hoop compression in a dome is given by

A. wR / 4d

B. wR/2d

C. wR/d

D. 2wR/d Where, w = load per unit area of surface of dome R = radius of curvature d = thickness of dome

Correct Answer :

B. wR/2d


Related Questions

What is the correct answer?

4

Slump test of concrete is a measure of its

A. Consistency

B. Compressive strength

C. Tensile strength

D. Impact value

What is the correct answer?

4

The compaction of concrete, improves

A. Density

B. Strength

C. Durability

D. All the above

What is the correct answer?

4

Modulus of elasticity of steel as per IS: 4561978 shall be taken as

A. 20 kN/cm²

B. 200 kN/cm²

C. 200 kN/mm²

D. 2 × 106 N/cm²

What is the correct answer?

4

Separation of water or water sand cement from a freshly concrete, is known

A. Bleeding

B. Creeping

C. Segregation

D. Flooding

What is the correct answer?

4

An excess of flaky particles in concrete aggregates

A. Decreases the workability

B. Increases the quantity of water and sand

C. More than 15% are not desirable

D. All the above

What is the correct answer?

4

Expansion joints are provided if the length of concrete structures exceeds

A. 10 m

B. 15 m

C. 15 m

D. 45 m

What is the correct answer?

4

Le-Chatelier's apparatus is used for testing

A. Soundness of cement

B. Hardness of cement

C. Strength of cement

D. Durability of cement

What is the correct answer?

4

Minimum pitch of transverse reinforcement in a column is

A. The least lateral dimension of the member

B. Sixteen times the smallest diameter of longitudinal reinforcement bar to be tied

C. Forty-eight times the diameter of transverse reinforcement

D. Lesser of the above three values

What is the correct answer?

4

Setting time of cement increases by adding

A. Gypsum

B. Hydrogen peroxide

C. Calcium chloride

D. Sodium oxide

What is the correct answer?

4

The produce impermeable concrete

A. Thorough mixing of concrete is required

B. Proper compaction of concrete is required

C. Proper curing of concrete is required

D. All the above

What is the correct answer?

4

Modulus of rupture of concrete is a measure of

A. Flexural tensile strength

B. Direct tensile strength

C. Compressive strength

D. Split tensile strength

What is the correct answer?

4

Concrete containing

A. Siliceous aggregates, has higher co-efficient of expansion

B. Igneous aggregates, has intermediate coefficient of expansion

C. Lime stones, has lowest co-efficient of expansion

D. All the above

What is the correct answer?

4

As compared to ordinary Portland cement, high alumina cement has

A. Higher initial setting time but lower final setting time

B. Lower initial setting time but higher final setting time

C. Higher initial and final setting times

D. Lower initial and final setting times

What is the correct answer?

4

Pick up the correct statement from the following:

A. Water enables chemical reaction to take place with cement

B. Water lubricates the mixture of gravel, sand and cement

C. Strength of concrete structure largely depends upon its workability

D. All the above

What is the correct answer?

4

Increase in the moisture content in concrete

A. Reduces the strength

B. Increases the strength

C. Does not change the strength

D. All of the above

What is the correct answer?

4

If the slump of a concrete mix is 60 mm, its workability is

A. Very low

B. Low

C. Medium

D. High

What is the correct answer?

4

1% of voids in a concrete mix would reduce its strength by about

A. 5 %

B. 10 %

C. 15 %

D. 20 %

What is the correct answer?

4

Hardening of cement occurs at

A. Rapid rate during the first few days and afterwards it continues to increase at a decreased rate

B. Slow rate during the first few days and afterwards it continues to increase at a rapid rate

C. Uniform rate throughout its age

D. None of these

What is the correct answer?

4

For a cantilever of effective depth of 0.5 m, the maximum span to satisfy vertical deflection limit is

A. 3.5 m

B. 4 m

C. 4.5 m

D. 5 m

What is the correct answer?

4

Ratio of permissible stress in direct compression and bending compression is

A. Less than 1

B. Between 1 and 1.5

C. Between 1.5 and 2.0

D. Greater than 2

What is the correct answer?

4

I.S. Sieve Nos. 10 mm and 4.75 mm are generally used for grading of

A. Coarse aggregates

B. Fine aggregates

C. Neither (a) nor (b)

D. Both (a) and (b)

What is the correct answer?

4

Pick up the incorrect statement from the following. For performing compressive strength test of cement

A. Cement and standard sand mortar are used in the ratio of 1 : 3

B. Water is added at the rate of (P/4) + 3.0 percentage of water where P is the percentage of water for standard consistency

C. A cube mould of 10 cm × 10 cm × 10 cm is used

D. The prepared moulds are kept in a atmosphere of 50% relative humidity

What is the correct answer?

4

Gypsum is added for

A. Colour

B. Strength

C. Controlling setting time

D. None of these

What is the correct answer?

4

The type of aggregates of same nominal size, which contain less voids when compacted, are

A. Rounded spherical

B. Irregular

C. Flaky

D. None of these

What is the correct answer?

4

Pick up the correct statement from the following:

A. High percentage of C3S and low percentage of C2S cause rapid hardening

B. High percentage of C3S and low percentage of C2S make the cement less resistive to chemical attack

C. Low percentage of C3S and high percentage of C2S contribute to slow hardening

D. All the above

What is the correct answer?

4

To ensure constant moisture content in aggregates

A. Area of each aggregate pile should be large

B. Height of each aggregate pile should not exceed 1.50 m

C. Aggregate pile should be left for 24 hours before aggregates are used

D. All the above

What is the correct answer?

4

The grade of concrete not recommended by I.S. : 456, is

A. M 100

B. M 200

C. M 300

D. M 500

What is the correct answer?

4

The percentage of the aggregate of F.M. 2.6 to be combined with coarse aggregate of F.M. 6.8 for obtaining the aggregates of F.M. 5.4, is

A. 30 %

B. 40 %

C. 50 %

D. 60 %

What is the correct answer?

4

An ideal ware house, is provided

A. Water proof masonry walls

B. Water proof roof

C. Few windows which remain generally closed

D. All the above

What is the correct answer?

4

Construction joints are generally provided in concrete

A. Roads

B. Retaining walls

C. Lining of canals

D. All the above