The concrete slump recommended for foundations, is

25 to 50 mm
30 to 125 mm
50 to 100 mm
75 to 125 mm

Question No : 30
The line of intersection of the surfaces of a sloping roof forming an external angle exceeding 180°, is

Ridge
Hip
Valley
None of these

Question No : 31
The single stage well point system of dewatering an excavation can be used if the depth of excavation does not exceed

5 m
10 m
15 m
20 m

Question No : 32
Pick up the correct statement from the following:

Cavity of a cavity wall should start near ground level
Cavity of a cavity wall should terminate near eaves level of sloping roof
Cavity of a cavity wall should terminate near coping of flat roof with parapet wall
All the above

Question No : 33
The vertical side member of a shutter frame, is known

Style
Reveal
Mullion
Post

Question No : 34
The floor is rubbed with oxalic acid, for making its surface

Free from voids
Glossy
Durable
Uniform

Question No : 35
Pick up the incorrect statement from the following:

In Flemish bond, headers and stretchers are laid alternately in the same course
In Flemish bond every header in each course lies centrally over every stretcher of the underlying course
In English bond, stretchers are laid in every course
In English bond, headers and stretchers are laid in alternate courses