Home
Current Affairs January 2024

What is the correct answer?

4

The maximum amount of dust which may be permitted in aggregates is

A. 5% of the total aggregates for low workability with a coarse grading

B. 10% of the total aggregates for low workability with a fine grading

C. 20% of the total aggregates for a mix having high workability with fine grading

D. All the above

Correct Answer :

D. All the above


Related Questions

What is the correct answer?

4

The rock which is not calcareous, is:

A. Lime stone

B. Chalk

C. Laterite

D. None of these

What is the correct answer?

4

An aggregate which passes through 25 mm I.S. sieve and is retained on 20 mm sieve, is said to be flaky if its least dimension is less than

A. 22.5 mm

B. 18.5 mm

C. 16.5 mm

D. 13.5 mm

What is the correct answer?

4

The aggregate impact value of the aggregate used in

A. Building concrete is less than 45

B. Road pavement concrete is less than 30

C. Runway concrete is less than 30

D. All the above

What is the correct answer?

4

A T-shaped retaining wall mainly consists of

A. One cantilever

B. Two cantilevers

C. Three cantilevers

D. Four cantilevers

What is the correct answer?

4

Higher workability of concrete is required if the structure is

A. Made with cement concrete

B. Thick and reinforced

C. Thin and heavily reinforced

D. Thick and heavily reinforced

What is the correct answer?

4

The load factors for live load and dead load are taken respectively as

A. 1.5 and 2.2

B. 2.2 and 1.5

C. 1.5 and 1.5

D. 2.2 and 2.2

What is the correct answer?

4

Maximum percentage reinforcement in case of slabs is limited to

A. 2

B. 4

C. 6

D. 8

What is the correct answer?

4

During erection, the pile of length l is supported by a crane at a distance of

A. 0.207 l

B. 0.293 l

C. 0.707 l

D. 0.793 l From the driving end of pile which rests on the ground

What is the correct answer?

4

The ratio of the length to breadth of a wooden float, is

A. 4.5

B. 5.5

C. 6.5

D. 7.5

What is the correct answer?

4

The percentage of the aggregate of F.M. 2.6 to be combined with coarse aggregate of F.M. 6.8 for obtaining the aggregates of F.M. 5.4, is

A. 30 %

B. 40 %

C. 50 %

D. 60 %

What is the correct answer?

4

The increased cohesiveness of concrete, makes it

A. Less liable to segregation

B. More liable to segregation

C. More liable to bleeding

D. More liable for surface scaling in frosty weather

What is the correct answer?

4

In a pile of length l, the points of suspension from ends for lifting it are located at

A. 0.207 l

B. 0.25 l

C. 0.293 l

D. 0.333 l

What is the correct answer?

4

The maximum percentage of chemical ingredient of cement is that of

A. Magnesium oxide

B. Iron oxide

C. Silica

D. Lime

What is the correct answer?

4

The purpose of reinforcement in pre-stressed concrete is

A. To provide adequate bond stress

B. To resist tensile stresses

C. To impart initial compressive stress in concrete

D. All of the above

What is the correct answer?

4

According to IS: 4561978, minimum slenderness ratio for a short column is

A. Less than 12

B. Less than 18

C. Between 18 and 24

D. More than 24

What is the correct answer?

4

The percentage of reinforcement in case of slabs, when high strength deformed bars are used is not less than

A. 0.15

B. 0.12

C. 0.30

D. 1.00

What is the correct answer?

4

For ensuring quality of concrete, use

A. Single sized aggregates

B. Two sized aggregate

C. Graded aggregates

D. Coarse aggregates

What is the correct answer?

4

If the effective working time is 7 hours and per batch time of concrete is 3 minutes, the output of a concrete mixer of 150 litre capacity, is

A. 15,900 litres

B. 16,900 litres

C. 17,900 litres

D. 18,900 litres

What is the correct answer?

4

The temperature reinforcement in the vertical slab of a T-shaped R.C. retaining wall is

A. Not needed

B. Provided equally on inner and front faces

C. Provided more on inner face than on front face

D. Provided more on front face than on inner face

What is the correct answer?

4

In a counterfort retaining wall, the main reinforcement in the stem at mid span is provided on

A. Front face only

B. Inner face only

C. Both front face and inner face

D. None of the above

What is the correct answer?

4

To ensure constant moisture content in aggregates

A. Area of each aggregate pile should be large

B. Height of each aggregate pile should not exceed 1.50 m

C. Aggregate pile should be left for 24 hours before aggregates are used

D. All the above

What is the correct answer?

4

Tricalcium aluminate (C3A)

A. Reacts fast with water

B. Generates less heat of hydration

C. Causes initial setting and early strength of cement

D. Does not contribute to develop ultimate strength

What is the correct answer?

4

Pick up the correct statement from the following:

A. Insufficient quantity of water makes the concrete mix harsh

B. Insufficient quantity of water makes the concrete unworkable

C. Excess quantity of water makes the concrete segregated

D. All the above

What is the correct answer?

4

An ordinary Portland cement when tested for its fineness, should not leave any residue on I.S. sieve No. 9, more than

A. 5 %

B. 10 %

C. 15 %

D. 20 %

What is the correct answer?

4

For construction of structures in sea water, the cement generally preferred to, is

A. Portland-pozzolana cement

B. Quick setting cement

C. Low heat Portland cement

D. Rapid hardening cement

What is the correct answer?

4

Sand requiring a high water cement ratio, belongs to

A. Zone I

B. Zone II

C. Zone III

D. Zone IV

What is the correct answer?

4

Ordinary Portland cement is manufactured from

A. Lime stone and clay

B. Gypsum and lime

C. Pozzolana

D. Lime, pozzolana and clay

What is the correct answer?

4

The lower water cement ratio in concrete, introduces

A. Smaller creep and shrinkage

B. Greater density and smaller permeability

C. Improved frost resistance

D. All the above

What is the correct answer?

4

For a good concrete

A. Aggregates should be hard and durable

B. Water should be free from organic materials

C. Cement should be sufficient to produce the required strength

D. All the above

What is the correct answer?

4

When shear stress exceeds the permissible limit in a slab, then it is reduced by

A. Increasing the depth

B. Providing shear reinforcement

C. Using high strength steel

D. Using thinner bars but more in number