Pick up the incorrect statement from the following:

A. The function of foundation is to distribute the load of super structure over a large bearing area

B. No timbering is required for shallow trenches

C. Shallow foundations can be constructed on made-up soil

D. Black cotton soil is very good for foundation bed

Correct Answer :

D. Black cotton soil is very good for foundation bed


Related Questions

What is the correct answer?

4

Engineering news formula for obtaining safe bearing capacity of pile for drop hammer, is,

A. Q = Wh/6 (S + 2.5)

B. Q = Wh/2.5 (S + 6)

C. Q = (W × 6)/h (S + 2.5)

D. Q = (W × 2.5)/6 (S + h)

What is the correct answer?

4

To stagger vertical joints in successive courses of a wall, a piece of brick is generally used at the end of the course, which is known as

A. Bat

B. Header

C. Stretcher

D. Closer

What is the correct answer?

4

An arch may fail due to

A. Uneven settlement of abutments

B. Sliding of voussoirs

C. Crushing of the material

D. All the above

What is the correct answer?

4

The type of arch generally constructed over a wooden lintel or over a flat arch for the purpose of carrying the load of the wall above is

A. Segmental arch

B. Pointed arch

C. Relieving arch

D. Flat arch

What is the correct answer?

4

To ensure that supporting area of an offset footing of a boundary wall is fully compressive, the C.G. of load must act

A. At the centre of the base

B. Within the middle third of the base

C. Within the middle fifth of the base

D. Neither (a), (b) nor (c)

What is the correct answer?

4

The vertical side member of a shutter frame, is known

A. Style

B. Reveal

C. Mullion

D. Post

What is the correct answer?

4

Pick up the correct statement from the following:

A. Cavity of a cavity wall should start near ground level

B. Cavity of a cavity wall should terminate near eaves level of sloping roof

C. Cavity of a cavity wall should terminate near coping of flat roof with parapet wall

D. All the above

What is the correct answer?

4

The floor is rubbed with oxalic acid, for making its surface

A. Free from voids

B. Glossy

C. Durable

D. Uniform

What is the correct answer?

4

The single stage well point system of dewatering an excavation can be used if the depth of excavation does not exceed

A. 5 m

B. 10 m

C. 15 m

D. 20 m

What is the correct answer?

4

Pick up the correct statement from the following:

A. Plain cement concrete is equally strong in compression as well as in tension

B. Slump test is performed to check concrete strength

C. Curing of concrete is done for proper compaction of cement

D. Fineness modulus is the index number expressing the relative sizes of both coarse and fine aggregates

What is the correct answer?

4

Bearing capacity of soils cannot be improved by

A. Draining sub-soil water

B. Ramming crushed stone in soil

C. Driving sand piles

D. Watering surface of soil

What is the correct answer?

4

In clay soil

A. Swelling and shrinkage characteristics prevail

B. Consolidation continues even after several years of construction

C. Differential settlement is generally prevalent

D. All the above

What is the correct answer?

4

The vertical sides of a door and window openings provided in a wall, are known as

A. Verticals

B. Reveals

C. Jambs

D. None of these

What is the correct answer?

4

Pile foundations are suitable for

A. Water logged soils

B. Soft rocks

C. Compact soils

D. Multi-storeyed buildings

What is the correct answer?

4

The nominal thickness of one brick wall in mm, is

A. 90 mm

B. 150 mm

C. 190 mm

D. 200 mm

What is the correct answer?

4

The stone whose crushing strength is maximum, is

A. Granite

B. Chalk

C. Slate

D. Sand stone

What is the correct answer?

4

During percussion drilling

A. Ground water observations are hindered due to entry of the slurry in the soil below the bottom of the hole

B. Caving or mixing of strata are caused in soft soils or cohesionless soils

C. The soil to a considerable depth below the bottom of the hole gets disturbed

D. All the above

What is the correct answer?

4

In which of the following directions, the strength of timber is maximum?

A. Parallel to grains

B. 45° to grains

C. Perpendicular to grains

D. Same in all directions

What is the correct answer?

4

A pre-stressed concrete pile is

A. Easy to handle

B. Lighter in weight

C. Extremely durable

D. All the above

What is the correct answer?

4

Raft foundations are used for:

A. Providing increased area of foundation over poor bearing capacity of soil

B. Spanning over small soft or loose pockets

C. Counter acting the hydrostatic effect

D. All the above

What is the correct answer?

4

The form work from the underside of slabs, can be removed only after

A. 1 day

B. 4 days

C. 7 days

D. 14 days

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. In Flemish bond, headers and stretchers are laid alternately in the same course

B. In Flemish bond every header in each course lies centrally over every stretcher of the underlying course

C. In English bond, stretchers are laid in every course

D. In English bond, headers and stretchers are laid in alternate courses

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. Horizontal D.P.C. is provided at plinth level in internal walls

B. D.P.C. is provided under door and verandah openings

C. Vertical D.P.C. is not provided in internal walls

D. Cement concrete is a rigid damp-proofing material

What is the correct answer?

4

Dutch bond is a modification of

A. English bond

B. Stretcher bond

C. Header bond

D. Single Flemish bond

What is the correct answer?

4

For brick construction, the lime-sand mortar, is

A. 1 : 1

B. 1 : 2

C. 1 : 3

D. 1 : 4

What is the correct answer?

4

The vertical members fixed between steps and hand rail, are known

A. Balusters

B. Strings

C. Newel posts

D. Soffits

What is the correct answer?

4

The horizontal timber piece provided at the apex of a roof truss which supports the common rafter is called

A. Ridge board

B. Hip rafter

C. Eaves board

D. Valley rafter

What is the correct answer?

4

A floor constructed with 3 mm marble chips, is known

A. Mosaic floor

B. Terrazzo floor

C. Chips floor

D. Marble floor

What is the correct answer?

4

A covering of concrete placed on the exposed top of an external wall, is known as

A. Cornice

B. Coping

C. Frieze

D. Lintel

What is the correct answer?

4

Pick up the correct statement from the following:

A. The cost of square rooms is less

B. The expenditure on the foundation and roof for the double storeyed building is nearly half of that for the ground storeyed building

C. The cost of construction of a house may be minimised by restricting the height floors

D. All the above