Construction Planning and Management MCQ Question with Answer

Construction Planning and Management MCQ with detailed explanation for interview, entrance and competitive exams. Explanation are given for understanding.

Download Construction Planning and Management MCQ Question Answer PDF

Question No : 36
If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is

30 kg
300 kg
900 kg
1000 kg

Question No : 37
Which of the following earth moving machines has the shortest cycle time?

Drag line
Hoe
Clam shell
Dipper shovel

Question No : 38
Final technical authority of a project lies with

Assistant Engineer
Executive Engineer
Superintending Engineer
Chief Engineer

Question No : 39
Mobilization advance up to 10% of the cost of work is given to a contractor

On commencement of work at site for payment of loan taken by him
For the purchase of construction materials
For the payment of advances to labour and other staff
For all activities required to start the work at site on finalization of the contract document

Question No : 40
An event is indicated on the network by a number enclosed in

A circle
A square
A triangle
All the above

Question No : 41
In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having

Longest duration
Highest cost slope
Least cost slope
Shortest duration

Question No : 42
Which one of the following represents an activity?

Excavation for foundation
Curing of concrete
Setting of question paper
All the above