Question No : 36
If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is
Question No : 37
Which of the following earth moving machines has the shortest cycle time?
Question No : 38
Final technical authority of a project lies with
Question No : 39
Mobilization advance up to 10% of the cost of work is given to a contractor
Question No : 40
An event is indicated on the network by a number enclosed in
Question No : 41
In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
Question No : 42
Which one of the following represents an activity?