A circle
A square
A triangle
All the above
D. All the above
Instructions by the executive engineers
Construction measurements
Issue of store equipments
Names of the casual labour
1 and 4 are correct
2 and 3 are correct
1 and 4 are correct
1 and 2 are correct
An engineer
An architect
An owner
All the above
1
2
3
4
The float may be positive, zero or negative
If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed
If the float of an activity is negative, delay in its performance is bound to delay the completion of project
All the above
Event
Float
Duration
Constraint
Drag line
Hoe
Clam shell
Dipper shovel
Acquisition of land
Selection of site
Fmalisation of alignment of work
All the above
Having a single lump, are called uninodal curves
If symmetrical, are called normal curves
If not symmetrical, are called skew curves
All the above
Moist loam
Sand and gravel
Good common earth
Wet sticky clay
The detailed estimated cost based on detailed design
The several alternatives of the project that have been considered
The soil survey, traffic survey, concept design and approximate cost
The contract documents for inviting tenders
Concrete cured
Fixing of door
Plastering of walls
Selecting sites
Identify the activities which can be delayed without affecting the total float of preceding activity
Identify the activities, which can be delayed without affecting the total float of succeeding activity
Establish priorities
Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities
The activity is the time consuming part of a project
The beginning and end of a job, are called events
The activity which consumes maximum time, is called a node
Logically and sequentially connected activities and events form a network
Rs. 8,43,750
Rs. 8,75,000
Rs. 10,50,000
Rs. 11,56,250
Decreasing the direct cost and increasing indirect cost
Increasing the direct cost and decreasing the indirect cost
Increasing the direct cost and indirect cost both
Decreasing the direct cost and indirect cost both
The various functions under each activity, are shown by one bar on Bar Charts
Bar chart establishes the interdependency of one event on another
Only approximate percentage of the completed work is reported
None of these
Longest duration
Highest cost slope
Least cost slope
Shortest duration
Rs. 8,800
Rs. 7,600
Rs. 6,400
Rs. 5,000
1880
1900
1920
1940
500 cum
1000 cum
1500 cum
2000 cum
Small projects
Large and complex projects
Research and development projects
Deterministic activities
Preparation of estimate
Survey of the site
Initiation of proposal
Preparation of tender
The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity
The difference between the maximum time available for the job and actual time it consumes, is called total float
The difference between the latest start time and earliest start time of an activity, is called total float
None of these
1, 2 and 3 are correct
1 and 4 are correct
2, 3 and 4 are correct
1, 2 and 4 are correct
Minimum time
Maximum time
Maximum cost
Minimum cost
Yes, because of heavier overheads and handling cost
Yes, because of the very high order of quality control for the factory made components
No, because of repetitive manufacture of a number of elements
No, because of savings in site labour
Unity of command
Effective control at all levels
Delegation of authority
All the above
30 kg
300 kg
900 kg
1000 kg
Crash time
Normal time
Optimistic time
Between normal time and crash time