Home
Current Affairs January 2024

What is the correct answer?

4

If the gross vehicle weight of a truck is 30 tonne and rolling resistance is 30 kg/tonne, then the tractive effort required to keep the truck moving at a uniform speed is

A. 30 kg

B. 300 kg

C. 900 kg

D. 1000 kg

Correct Answer :

C. 900 kg


Related Questions

What is the correct answer?

4

Consider the following operations:
1. Drilling
2. Blasting
3. Mucking
4. Placing steel
5. Placing concrete
The correct sequence of these operations in tunnel construction is

A. 1, 2, 4, 3, 5

B. 1, 3, 2, 4, 5

C. 1, 2, 3, 4, 5

D. 1, 3, 4, 2, 5

What is the correct answer?

4

PERT analysis is based on

A. Optimistic time

B. Pessimistic time

C. Most likely time

D. All the above

What is the correct answer?

4

The time with which direct cost does not reduce with the increase in time is known as

A. Crash time

B. Normal time

C. Optimistic time

D. Standard time

What is the correct answer?

4

Pick up the correct statement from the following:

A. Forward pass is used for calculating earliest expected time

B. Backward pass is used for calculating the latest occurrence time

C. Maximum value of earliest expected time is used if there is more than one value of any event

D. All the above

What is the correct answer?

4

The original cost of an equipment is Rs.10,000. Its salvage value at the end of its total useful life of five years is Rs. 1,000. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be

A. Rs. 8,800

B. Rs. 7,600

C. Rs. 6,400

D. Rs. 5,000

What is the correct answer?

4

PERT is

A. An analytic in concept

B. Limited of event oriented diagrams

C. Used for research and development projects

D. All the above

What is the correct answer?

4

Free float for any activity is defined as the difference between

A. Its earliest finish time and earliest start time for its successor activity

B. Its latest start time and earliest start time

C. Its latest finish time and earliest start time for its successor activity

D. Its earliest finish time and latest start time for its successor activity

What is the correct answer?

4

If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is

A. 4 days

B. 6 days

C. 10 days

D. 16 days

What is the correct answer?

4

Frequency distribution curves

A. Having a single lump, are called uninodal curves

B. If symmetrical, are called normal curves

C. If not symmetrical, are called skew curves

D. All the above

What is the correct answer?

4

Henry Gantt developed Bar charts for planning and scheduling of projects in

A. 1880

B. 1900

C. 1920

D. 1940

What is the correct answer?

4

For the execution of a project, a contractor is

A. A person

B. A firm

C. An agency

D. All the above

What is the correct answer?

4

A critical ratio scheduling

A. Determines the status of each activity

B. Adjusts automatically changes in activity progress

C. Is a dynamic system

D. None of these

What is the correct answer?

4

Which of the following earth moving machines has the shortest cycle time?

A. Drag line

B. Hoe

C. Clam shell

D. Dipper shovel

What is the correct answer?

4

If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is

A. 500 cum

B. 1000 cum

C. 1500 cum

D. 2000 cum

What is the correct answer?

4

Crash project duration is obtained by summing the

A. Normal durations for all the activities

B. Crash durations for all activities

C. Crash durations for all the activities along the critical path obtained by taking into account the normal duration for all the activities

D. Crash durations for all the activities along the critical path obtained by taking into account the crash duration for all the activities

What is the correct answer?

4

For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is

A. 1

B. 2

C. 3

D. 4

What is the correct answer?

4

Total float for any activity is defined as the difference between

A. Its latest finish time and earliest start time for its successor activity

B. Its latest start time and earliest start time

C. Its latest start time and earliest finish time

D. Its earliest finish time and earliest start time for its successor activity

What is the correct answer?

4

The performance of a specific task in CPM, is known

A. Dummy

B. Event

C. Activity

D. Contract

What is the correct answer?

4

Which of the following is a weakness of bar chart?

A. Interdependencies of activities

B. Project progress

C. Uncertainties

D. All of the above

What is the correct answer?

4

PERT technique of network analysis is mainly useful for

A. Small projects

B. Large and complex projects

C. Research and development projects

D. Deterministic activities

What is the correct answer?

4

A golden rule for the procurement of construction stones, suggests

A. 100% at the site

B. 67% at the site and 33% under procurement

C. 50% at the site and 50% under procurement

D. 33% at the site and 67% under procurement

What is the correct answer?

4

Railway projects are treated as

A. Light construction

B. Heavy construction

C. Industrial construction

D. None of these

What is the correct answer?

4

The difference between the time avail-to do a job and the time required to do the job, is known as

A. Event

B. Float

C. Duration

D. Constraint

What is the correct answer?

4

Grader is used mainly for

A. Trimming and finishing

B. Shaping and trimming

C. Finishing and shaping

D. Finishing, shaping and trimming

What is the correct answer?

4

Pick up the correct statement from the following:

A. The difference of latest occurrence time and earliest expected time, is called slack

B. The activities connecting the events having zero slack, lie on the critical path

C. The critical path consumes the maximum time

D. All the above

What is the correct answer?

4

Economic saving of time results by crashing

A. Cheapest critical activity

B. Cheapest noncritical activity

C. Costliest critical activity

D. Costliest noncritical activity

What is the correct answer?

4

Military organisation is known as

A. Line organisation

B. Line and staff organisation

C. Functional organisation

D. None of these

What is the correct answer?

4

A machine is purchased for Rs. 10,000,00 and has an estimated life of 10 years. The salvage value at the end of 10 years is Rs. 1,50,000. The book value of the machine at the end of 5 years using general straight line method of evaluation of depreciation is

A. Rs. 4,75,000

B. Rs. 5,75,000

C. Rs. 6,50,000

D. Rs. 8,50,000

What is the correct answer?

4

The part of a derrick crane include (i) Mast (ii) Boom (iii) Bull wheel (iv) Jack Of these statements

A. (i), (ii) and (iv) are correct

B. (ii), (iii) and (iv) are correct

C. (i), (iii) and (iv) are correct

D. (i), (ii) and (iii) are correct

What is the correct answer?

4

Critical path lies along the activities having total float

A. Positive

B. Negative

C. Zero

D. Same