25 mm
40 mm
65 mm
100 mm
C. 65 mm
Haunch
Spandril
Voussoirs
Skewbacks
25 to 50 mm
30 to 125 mm
50 to 100 mm
75 to 125 mm
Centring
Actual laying of arch work
Striking of centring
None of the above
Bay window
Casement window
Lantern window
Dormer window
A mortar joint having a concave finishing in brick masonry, is called keyed joint
A mortar joint projecting beyond the face of a masonry wall, is called tucked joint
A mortar joint having a recess in it, is called ruled joint
All the above
In king post truss, one vertical post is used
In a queen post truss, one vertical post is used
In a queen post truss, two vertical posts are used
None of these
50 cm
60 cm
80 cm
90 cm
55 cm
70 cm
85 cm
100 cm
Upper flange of top tier
Lower beam of lower tier
Ends of external beams
None to these
Verticals
Reveals
Jambs
None of these
10 m
20 m
30 m
40 m
The bearing capacity of a pile is defined as the load which can be sustained by the pile without producing excessive settlement
The safe bearing capacity of a pile is obtained by dividing the ultimate bearing capacity with a suitable factor of safety
The factor of safety for piles is taken as 6
All the above
In a king post truss, principal rafter and tie beams are jointed together with a bridle joint
Joint between the principal rafter and the king post is made by making tenon and mortise respectively
Joint between strut and king post, is generally of mortise and tenon type
All the above
The retaining wall should be structurally capable to resist the applied earth pressure
The section of the retaining wall should be so proportioned that it may not overturn by the lateral pressure
The retaining wall should be safe against sliding
To drain off water from the earth retained, weep holes are provided near the top of the retaining wall
Lantern window
Dormer window
Louvered window
Rash window
1 day
4 days
7 days
14 days
There is no horizontal tie beam
There is a horizontal tie at the feet of rafters only
There is a horizontal tie at almost the middle of rafters only
There are two horizontal ties, one at the feet and other at the middle of the rafters
12
18
24
25
Granite
Chalk
Marble
Slate
Draining sub-soil water
Ramming crushed stone in soil
Driving sand piles
Watering surface of soil
Machine foundations
Factory building
Tall structures
All the above
Combined footing
Strap footing
Raft footing
None of these
Trowelling
Laying
Grouting
Placing
A tube of about 2 metres length and 20 cm diameter with a cutting edge
A flap valve at the bottom of tube is provided to extract the soil sample
The tube is raised and lowered by 4 thick rope moving over a pulley suspended on a tripod stand
All the above
Auger boring
Percussion drilling
Diamond drilling
Wash boring
Cleat
Stop
Horn
None of these
Heat insulation
Sound insulation
Prevention of dampness
All the above
Bat
Header
Stretcher
Closer
Distance of C.G. of the loads from the smaller column = 3.00 m
The length of the foundation slab = 7.00 m
Area of footing slab = 11.00 m2
All the above
9 cm × 9 cm × 9 cm
9 cm × 9 cm × 4.5 cm
9 cm × 4.5 cm × 9 cm
1.8 cm × 4.5 cm × 9 cm