4

For a wall carrying heavy load on low bearing capacity soil,

A. Lean concrete bed is provided

B. Thick concrete bed is provided

C. Reinforced concrete bed is provided

D. Both (a) and (c) of the above

Correct Answer :

D. Both (a) and (c) of the above


Related Questions

What is the correct answer?

4

The voussoir placed at crown of an arch, is known as a

A. Key

B. Soffit

C. Springer

D. Haunch

What is the correct answer?

4

The stone masonry of finely dressed stones laid in cement or lime, is

A. Random rubble masonry

B. Coursed rubble masonry

C. Dry rubble masonry

D. Ashlar masonry

What is the correct answer?

4

Pick up the correct statement from the following:

A. Cavity of a cavity wall should start near ground level

B. Cavity of a cavity wall should terminate near eaves level of sloping roof

C. Cavity of a cavity wall should terminate near coping of flat roof with parapet wall

D. All the above

What is the correct answer?

4

The term string is used for

A. The underside of a stair

B. Outer projecting edge of a tread

C. A sloping member which supports the steps in a stair

D. A vertical member between two treads

What is the correct answer?

4

Pick up the correct statement from the following:

A. The bearing capacity of a pile is defined as the load which can be sustained by the pile without producing excessive settlement

B. The safe bearing capacity of a pile is obtained by dividing the ultimate bearing capacity with a suitable factor of safety

C. The factor of safety for piles is taken as 6

D. All the above

What is the correct answer?

4

The piece of a brick cut with its one corner equivalent to half the length and half the width of a full brick, is known as

A. Queen closer

B. Bevelled closer

C. King closer

D. Half king closer

What is the correct answer?

4

While designing a stair, the product of rise and going is approximately kept equal to

A. 350

B. 420

C. 450

D. 500

What is the correct answer?

4

Couple roof is used for spans

A. 3.5 m or less

B. 3.5 m but less than 5 m

C. 5 m but less than 6.5 m

D. 6.5 m but less than 8 m

What is the correct answer?

4

The minimum distance between the centres of bulb of diameter du, of a multi under reamed piles, is

A. du

B. 1.25 du

C. 1.5 du

D. 1.75 du

What is the correct answer?

4

The loose pockets in soil mass can be bridged safely by providing a raft foundation provided the soft area is smaller than

A. The column spacing

B. One-third the column spacing

C. Half the column spacing

D. Three-fourth the column spacing

What is the correct answer?

4

The maximum total settlement for raft foundation on clayey soils should be limited to

A. 25 mm

B. 25 to 40 mm

C. 40 to 65 mm

D. 65 to 100 mm

What is the correct answer?

4

Single Flemish bond consists of

A. Double Flemish bond facing and English bond backing in each course

B. English bond facing and double Flemish bond backing in each course

C. Stretcher bond facing and double Flemish bond backing in each course

D. Double Flemish bond facing and header bond backing in each course

What is the correct answer?

4

A wooden block fixed on back side of a door frame on its post, is known as

A. Cleat

B. Stop

C. Horn

D. None of these

What is the correct answer?

4

The mortar in which both cement and lime are used as binding materials, is called

A. Cement mortar

B. Lime mortar

C. Fire resistant mortar

D. Gauged mortar

What is the correct answer?

4

In verandah floors outward slope is

A. 1 in 40

B. 1 in 50

C. 1 in 60

D. 1 in 70

What is the correct answer?

4

Gravels

A. Are cohesionless aggregates

B. Vary in size between 2 to 20 mm

C. Never swell when they come into contact with water

D. All the above

What is the correct answer?

4

In case of foundations on sandy soil, maximum permissible differential settlement, is usually limited to

A. 15 mm

B. 25 mm

C. 35 mm

D. 45 mm

What is the correct answer?

4

The wedge shaped bricks forming an arch ring, are called

A. Soffits

B. Voussoirs

C. Haunches

D. Spandrils

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. Horizontal D.P.C. is provided at plinth level in internal walls

B. D.P.C. is provided under door and verandah openings

C. Vertical D.P.C. is not provided in internal walls

D. Cement concrete is a rigid damp-proofing material

What is the correct answer?

4

The members which support covering material of a sloping roof, are

A. Rafters

B. Purlins

C. Battens

D. Struts

What is the correct answer?

4

The window which is provided on a sloping roof of a building, is called

A. Lantern window

B. Dormer window

C. Louvered window

D. Rash window

What is the correct answer?

4

Pile foundation is generally provided if soil is

A. Compressible

B. Water logged

C. Made up

D. All the above

What is the correct answer?

4

The skirting/dado in a bath roof should be upto

A. Ceiling

B. 15 cm above floor level

C. 200 cm

D. Level of the tap

What is the correct answer?

4

For the construction of flyovers in sandy soils, the type of foundation provided, is

A. Strap footing

B. Raft footing

C. Combined footing

D. Pier footing

What is the correct answer?

4

The bearing capacity of a water logged soil, may be improved by

A. Grouting

B. Chemical action

C. Drainage

D. Compaction

What is the correct answer?

4

Pick up the correct statement from the following:

A. Louvered door is generally provided in bath rooms

B. Flush door is generally provided in dining room

C. Revolving door is generally provided in cinema halls

D. Sliding door is generally provided in show rooms

What is the correct answer?

4

The disease of dry rot in timber is caused by

A. Lack of ventilation

B. Alternate wet and dry conditions

C. Complete submergence in water

D. None of the above

What is the correct answer?

4

The black cotton soil

A. Undergoes volumetric changes

B. Swells excessively when wet

C. Shrinks excessively when dry

D. All the above

What is the correct answer?

4

If height of the first storey of a building is 3.2 m and riser is 13 cm, the number of treads required, is

A. 12

B. 18

C. 24

D. 25

What is the correct answer?

4

Pick up the correct statement from the following:

A. The sand in the sand pile is well compacted

B. The sand is kept moist at the time of placing and tamping

C. Sand piles are generally used under column loads

D. All of the above