Home
Current Affairs January 2024

What is the correct answer?

4

The art of bringing the floor to a true level surface by means of screeds, is called

A. Topping

B. Bedding

C. Screeding

D. None of these

Correct Answer :

C. Screeding


Related Questions

What is the correct answer?

4

To support a heavy structure in sandy soil, the type of foundation generally used, is

A. Combined footing

B. Raft footing

C. Pier footing

D. Strap footing

What is the correct answer?

4

In the construction of arches, sand box method is used for

A. Centring

B. Actual laying of arch work

C. Striking of centring

D. None of the above

What is the correct answer?

4

The black cotton soil

A. Undergoes volumetric changes

B. Swells excessively when wet

C. Shrinks excessively when dry

D. All the above

What is the correct answer?

4

The least bearing capacity of soil is that of

A. Hard rock

B. Moist clay

C. Soft rock

D. Coarse sandy soil

What is the correct answer?

4

Open test pit is only suitable upto a depth of

A. 2 metres

B. 2.5 metres

C. 3 metres

D. None of the above

What is the correct answer?

4

In case of multi-storeyed buildings, the forms to be removed first are

A. Sides of beams and girders

B. Column forms

C. Bottom of beams and girders

D. All the above at the same time

What is the correct answer?

4

The form work from the underside of slabs, can be removed only after

A. 1 day

B. 4 days

C. 7 days

D. 14 days

What is the correct answer?

4

A wooden block fixed on back side of a door frame on its post, is known as

A. Cleat

B. Stop

C. Horn

D. None of these

What is the correct answer?

4

Pick up the incorrect statement from the following:

A. In king post truss, one vertical post is used

B. In a queen post truss, one vertical post is used

C. In a queen post truss, two vertical posts are used

D. None of these

What is the correct answer?

4

Grillage foundation

A. Is used to transfer heavy structural loads from steel columns to a soil having low bearing capacity

B. Is light and economical

C. Does not require deep cutting as the required base area with required pressure intensity is obtained at a shallow depth

D. All the above

What is the correct answer?

4

An arch constructed with finely dressed stones, is known

A. Ashlar arch

B. Rubble arch

C. Gauged arch

D. Axed arch

What is the correct answer?

4

The maximum bearing capacity of soil is that of

A. Black cotton soil

B. Loose fine sandy soil

C. Dry coarse sandy soil

D. Hard rocks

What is the correct answer?

4

The taper of precast concrete pile should not be more than

A. 1 cm per metre length

B. 2 cm per metre length

C. 4 cm per metre length

D. 5 cm per metre length

What is the correct answer?

4

The service area in a building means the area occupied by

A. Stairs

B. Toilets

C. Light and shafts

D. All the above

What is the correct answer?

4

The foundation in which a cantilever beam is provided to join two footings, is known as

A. Strip footing

B. Strap footing

C. Combined footing

D. Raft footing

What is the correct answer?

4

The form Work including the props can be removed from beams, only after

A. 3 day

B. 7 days

C. 14 days

D. 21 days

What is the correct answer?

4

The strength of brick masonry in 1:6 cement mortar, is

A. 20 tonnes/m2

B. 40 tonnes/m2

C. 50 tonnes/m2

D. 60 tonnes/m2

What is the correct answer?

4

The members which support covering material of a sloping roof, are

A. Rafters

B. Purlins

C. Battens

D. Struts

What is the correct answer?

4

Depth of lean concrete bed placed at the bottom of a wall footing, is kept

A. 10 cm

B. 15 cm

C. Equal to its projection beyond wall base

D. Less than its projection beyond wall base

What is the correct answer?

4

For plastering the exposed brick walls, the cement sand mortar should be

A. 1 : 2

B. 1 : 3

C. 1 : 4

D. 1 : 6

What is the correct answer?

4

The stone whose crushing strength is maximum, is

A. Granite

B. Chalk

C. Slate

D. Sand stone

What is the correct answer?

4

For brick construction, the lime-sand mortar, is

A. 1 : 1

B. 1 : 2

C. 1 : 3

D. 1 : 4

What is the correct answer?

4

The window which is provided in flat roof of a room, is known

A. Dormer window

B. Lantern window

C. Louvered window

D. Sky window

What is the correct answer?

4

The width of the hollow space between two walls of a cavity wall should not exceed

A. 5 cm

B. 7.5 cm

C. 10 cm

D. 15 cm

What is the correct answer?

4

The pile which is provided with a bulb filled with concrete at its lower end, is known as

A. Simplex pile

B. Mac-Arthur pile

C. Raymond pile

D. Franki pile

What is the correct answer?

4

Sum of tread and rise must lie between

A. 300 to 350 mm

B. 400 to 450 mm

C. 500 to 550 mm

D. 600 to 650 mm

What is the correct answer?

4

Pick up the correct statement from the following:

A. Sand consists of coarse particles of silica formed due to the disintegration of rocks

B. The grains of sand are not affected by frost

C. Sand beds are permeable and do not allow water to rise up between pores due to capillary action

D. All the above

What is the correct answer?

4

Pick up the correct statement from the following:

A. The first coat of stucco plaster is called scratch coat

B. The second coat of stucco plaster is called brown coat

C. The third coat of stucco plaster is called white coat

D. All the above

What is the correct answer?

4

Which one of the following activities is not correct as applicable to brick corbels?

A. The maximum projection of the corbel should not be more than the thickness of the wall

B. The maximum projection of each corbel course should be limited to a quarter brick at a time

C. The discontinuous corbels are used to carry heavy concentrated loads

D. Stretcher bond is generally used for the construction of brick corbel

What is the correct answer?

4

A cut in frame of a door to receive the shutter, is called

A. Louver

B. Stop

C. Horn

D. Rebate