The maximum projection of the corbel should not be more than the thickness of the wall
The maximum projection of each corbel course should be limited to a quarter brick at a time
The discontinuous corbels are used to carry heavy concentrated loads
Stretcher bond is generally used for the construction of brick corbel
D. Stretcher bond is generally used for the construction of brick corbel
Trowelling
Laying
Grouting
Placing
Isolated footing is provided under column to transfer the load safely to soil bed
Column footings may have steps or projections in the concrete base
Heavily loaded column base must be provided steel reinforcement in both directions
All the above
The lowest layer consists of consolidated ground
A 10 cm thick clean sand is laid on consolidated ground
A 10 cm lime concrete (1 : 4 : 8) is laid on clean sand
A 10 cm thick cement concrete (1 : 2 : 4) is laid on top layer
One course of headers to three or five course of stretchers
Queen closer in provided in each heading course
The middle course of stretchers is started with a header to give proper vertical joints
All the above
Mortise and tenon joint
Oblique mortise and tenon joint
Butt joint
Mitred joint
Transoms
Horns
Stops
Chocks
Rising of water table
Vibrations caused by traffic movements
Mining in the neighbourhood
All the above
5 mm
10 mm
15 mm
20 mm
Column footing
Grillage footing
Raft footing
All the above
Simplex pile
Vibro pile
Raymond pile
Franki pile
50 N/cm2
100 N/cm2
150 N/cm2
200 N/cm2
Is a downward drag acting on a pile due to downward movement of the surrounding compressible soil relative to the pile
Develops due to lowering of ground water
Both (a) and (b)
Neither (a) not (b)
2 metres
2.5 metres
3 metres
None of the above
Ground level
Plinth level
Water table level
Midway ground level and water-table level
Granite
Chalk
Slate
Sand stone
Auger boring
Percussion drilling
Diamond drilling
Wash boring
In Flemish bond, headers and stretchers are laid alternately in the same course
In Flemish bond every header in each course lies centrally over every stretcher of the underlying course
In English bond, stretchers are laid in every course
In English bond, headers and stretchers are laid in alternate courses
h/4
1/2 h
h
2 h
Lantern window
Dormer window
Louvered window
Rash window
Both A and R is true and R is the correct explanation of A
Both A and R is true but R is not the correct explanation of A
A is true but R is false
A is false but R is true
Recessed pointing
Weather pointing
V-pointing
Tuck pointing
Plain cement concrete is equally strong in compression as well as in tension
Slump test is performed to check concrete strength
Curing of concrete is done for proper compaction of cement
Fineness modulus is the index number expressing the relative sizes of both coarse and fine aggregates
Undergoes volumetric changes
Swells excessively when wet
Shrinks excessively when dry
All the above
Equal to width of stairs
Half the width of stairs
Twice the width of stairs
One fourth the width of stairs
Two directions without break in the slope on each side
Two directions with break in the slope on each side
Four directions without break in the slope on each side
Four directions with break in the slope on each side
Cleat
Stop
Horn
None of these
Under-ream pile
Friction pile
Bearing pile
Sheet pile
Is not suitable for deposits containing very coarse gravel
Hinders the ground water observations and permeability test
Is not economical for holes of less than 10 cm
All the above
H-pile
Pipe pile
Screw pile
Disc pile
2 cm
4 cm
6 cm
8 cm